PROJECT SCHEDULE SUPPLY & INSTALLATION OF FIRE SUPPRESSION SYSTEM - PFIZER INDONESIA

ID WBS Task Name Duration Start Finish Predecessors Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21
1 1 INSTALASI FIRE FIRE FIGHTING PFIZER GANDARIA 214 days Sun 07/03/21We d 06/10/21
2 1.1 PO Received 1 day Sun 07/03/21 Sun 07/03/21
3 1.2 PRELIMINARY WORKS 161 daysMon 08/03/21 Sun 15/08/21
4 1.2.1 Design Draw ing & Approval Material (Circulating Doc) 21 day s Mon 08/03/21 Sun 28/03/21 2
5 1.2.2 Approved Draw ing & A pproval Material (Design Freeze / IFC) 7 days Mon 22/03/21 Sun 28/03/21 4FS-7 days
6 1.2.3 Purchase Installation Material (Local) 90 day s Mon 22/03/21 Sat 19/06/21 5FS-7 days
7 1.2.4 PIM (Visual & Qty Check only) 2 days Sun 20/06/21 Mon 21/06/21 6
8 1.2.5 Purchase Main Equipment 140 days Mon 29/03/21 Sun 15/08/21 5
9 1.2.6 Site Of f ic e, Warehouse, Fabrication Facility, etc Work 7 days Mon 22/03/21 Sun 28/03/21 4FS-7 days
10 1.3 SERVICES 85 days Tue 22/06/21 Tue 14/09/21
11 1.3.1 Main Equipment Internal QC Check 2 days Mon 16/08/21 Tue 17/08/21 8
12 1.3.2 Deliv ery Installation Material 50 day s Tue 22/06/21 Tue 10/08/21 7
13 1.3.3 Deliv ery Main Equipment 2 daysWed 18/08/21 Thu 19/08/21 11
14 1.3.4 FIRE PROTECT ION PIPING EXTERNAL 63 daysWe d 14/07/21 Tue 14/09/21
15 1.3.4.1 Main Pipe Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
16 1.3.4.2 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 15FS-7 day s
17 1.3.4.3 Fire Sprinkler Installation 45 day s Thu 29/07/21 Sat 11/09/21 15FS-45 days
18 1.3.4.4 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 17FS-7 day s
19 1.3.5 FIRE PROTECT ION PIPING DAT A HALL 63 daysWe d 14/07/21 Tue 14/09/21
20 1.3.5.1 Piping and Pulling Cable f or Fire Alarm & V esda 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
21 1.3.5.2 Fire Alarm Equipment Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
22 1.3.5.3 Cable Termination 10 day s Sun 05/09/21 Tue 14/09/21 21FS-7 day s
23 1.3.5.4 Fire Sprinkler Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
24 1.3.5.5 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 23FS-7 day s
25 1.3.6 PROTECTION PIPING OFFICE AREA 52 days Tue 20/07/21 Thu 09/09/21
26 1.3.6.1 Piping and Pulling Cable f or Fire Alarm 45 day s Tue 20/07/21 Thu 02/09/21 12FS-22 days
27 1.3.6.2 Fire Alarm Equipment Installation 7 days Fri 27/08/21 Thu 02/09/21 26FS-7 day s
28 1.3.6.3 Piping Installation 45 day s Tue 20/07/21 Thu 02/09/21 12FS-22 days
29 1.3.6.4 Accessories Installation 7 days Fri 27/08/21 Thu 02/09/21 28FS-7 day s
30 1.3.6.5 Pump Installation 21 day s Fri 20/08/21 Thu 09/09/21 29FS-14 days
31 1.3.6.6 Cable Termination f or Pump 4 days Mon 06/09/21 Thu 09/09/21 30FS-4 day s
32 1.3.6.7 Fire Sprinkler Installation 30 day s Tue 20/07/21Wed 18/08/21 12FS-22 days
33 1.3.7 FIRE PROTECT ION PIPING GUARD HOUSE 20 days Thu 19/08/21 Tue 07/09/21
34 1.3.7.1 Piping and Pulling Cable f or Fire Alarm 20 day s Thu 19/08/21 Tue 07/09/21 32
35 1.3.7.2 Fire Alarm Equipment Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
36 1.3.7.3 Fire Sprinkler Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
37 1.3.7.4 Equipment Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
38 1.3.8 PORTABLE FIRE EXTINGUISHER INSTALLATION 9 days Fri 20/08/21 Sat 28/08/21
39 1.3.8.1 Data Hall 3 days Fri 20/08/21 Sun 22/08/21 13
40 1.3.8.2 Of f ice A rea 2 days Mon 23/08/21 Tue 24/08/21 39
41 1.3.8.3 External Building 2 daysWed 25/08/21 Thu 26/08/21 40
42 1.3.8.4 Guard House 2 days Fri 27/08/21 Sat 28/08/21 41
43 1.4 TESTING & COM MISSIONING 29 daysWe d 08/09/21We d 06/10/21
44 1.4.1 FIRE PROTECT ION PIPING EXTERNAL 11 daysWe d 08/09/21 Sat 18/09/21
45 1.4.1.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 08/09/21 Tue 14/09/21 17FS-4 day s
46 1.4.1.2 Trouble shooting, Internal Test & Testing FA system 4 daysWed 15/09/21 Sat 18/09/21 45
47 1.4.2 FIRE PROTECT ION PIPING DAT A HALL 7 daysWe d 15/09/21 Tue 21/09/21
48 1.4.2.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 15/09/21 Tue 21/09/21 24
49 1.4.2.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 15/09/21 Tue 21/09/21 22
50 1.4.3 PROTECTION PIPING OFFICE AREA 14 daysWe d 08/09/21 Tue 21/09/21

Task Project Summary Inactive Summary Manual Summary External Milestone

Project: PFIZER Indonesia Split External Tasks Manual Task Start-only Progress
Date: Fri 30/04/21
Milestone External Milestone Duration-only Finish-only Deadline

Summary Inactive Milestone Manual Summary Rollup External Tasks

Created by : Approved by :
PROJECT SCHEDULE SUPPLY & INSTALLATION OF FIRE SUPPRESSION SYSTEM - PFIZER INDONESIA
ID WBS Task Name Duration Start Finish Predecessors Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21
51 1.4.3.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 15/09/21 Tue 21/09/21 24
52 1.4.3.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 08/09/21 Tue 14/09/21 35
53 1.4.4 FIRE PROTECT ION PIPING GUARD HOUSE 7 daysWe d 15/09/21 Tue 21/09/21
54 1.4.4.1 Hydrotest (Internal & Witness by Ow ner) 2 daysWed 15/09/21 Thu 16/09/21 24
55 1.4.4.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 15/09/21 Tue 21/09/21 22
56 1.4.5 Onsite training 1 day Wed 22/09/21Wed 22/09/21 55
57 1.4.6 As-built draw ing and final documentation 14 day s Thu 23/09/21Wed 06/10/21 56

Task Project Summary Inactive Summary Manual Summary External Milestone

Project: PFIZER Indonesia Split External Tasks Manual Task Start-only Progress
Date: Fri 30/04/21
Milestone External Milestone Duration-only Finish-only Deadline

Summary Inactive Milestone Manual Summary Rollup External Tasks

Created by : Approved by :