Installation Procedure
All materials received at site shall be inspected and ensured that the
materials are as per approved material submittal. Any discrepancies,
damages etc. shall be notified and reported for further action.
Material found not suitable for the project shall be removed from site
immediately.
Correct type of back boxes for all the outstations should be installed
as per approved shop drawings / material submittals.
The mounting heights for the Junction boxes should be verified with
approved shop drawings.
All the related documents like latest approved shop drawings and
schematic etc. should be available with installation team.
Site Installation Method Statement
Annunciator: Install with top of panel not more than 72 inches (1830
mm) above the finished floor.
Wiring & Connections Requirements
Verify that hardware and devices are NRTL listed for use with fire-
alarm system before making connections. Make addressable
connections with a supervised interface device to the following
devices and systems. Install the interface device less than 3 feet (1 m)
from the device controller. Make an addressable confirmation
connection when such feedback is available at the device or system
being controlled.
Battery Charger Faults that can arise during the operational lifetime
of a panel. You may observe one of the following Faults;
FA System Testing: