Testing and Commissioning Procedure
for FM 200 System
(REDCO)
RTC/082/2013
Document No.:
00031
Revision History
Rev. No. Description of Revision Date of Revision
M009-SPH-TCH-PR0-00031 Page 1 of 23
M009-SPH-TCH-PRO-00031 Page 2 of 23
M009-SPH-TCH-PRO-00031 Page 3 of 23
M009-SPH-TCH-PRO-00031 Page 4 of 23
008
010
011
012
* The final distribution may be modified after consultation with Main Contractor.
** It is the responsibility of the Station Manager to provide this Procedure to the respective
Project or Site Engineers and obtain sign off that they have received and understood the
document. Please refer to the communication protocol.
M009-SPH-TCH-PRO-00031 Page 5 of 23
M009-SPH-TCH-PRO-00031 Page 6 of 23
1.2 Purpose
The purpose of this Procedure is to explain step by step method for Testing and
Commissioning of FM200 System through the guidelines contained herein so as to ensure that
the job execution complies with project requirement and serves the intended function to
satisfactory level.
2 SCOPE
Scope of this Procedure (PRO) for Testing and Commissioning of FM200 system.
This document includes the following either in the main body or in the Appendices:
x Methodology for Testing and Commissioning of FM200 System.
x Equipment and materials used.
x HSE Assessment & Risk Assessment.
NOTE: For Check List refer to ITP (M009-REI-PRO-ITP-00046)
x NFPA 130 Standard for Fixed Guide Way Transit and Passenger Rail Systems
x BS CP 352 Mechanical ventilation and air conditioning in buildings
x NFPA 2001 Clean Agent Fire Extinguishing system
x NFPA 72 National Fire Alarm and Signaling Code.
x Qatar Construction Specifications 2010 (QCS 2010)
x Employer's requirement volume 4& 6
M009-SPH-TCH-PRO-00031 Page 7 of 23
x MES:
Document No. Document Name
M009-SPH-FRS-MES-00007 Method Statement for installation of FM200 system
FM 200 Fire Suppression & Detection System for ELE (CL-38) Room
M009-SPH-FRS-DWG-GWST080-L1-11223
at Concourse Level.
FM 200 Fire Suppression & Detection System for BMS Room (CL-53)
M009-SPH-FRS-DWG-GWST080-L1-11225
Room at Concourse Level.
FM 200 Fire Suppression & Detection System for SCR Room (CL-86)
M009-SPH-FRS-DWG-GWST080-L1-11226
Room at Concourse Level.
FM 200 Fire Suppression & Detection System for Third Party (CL-80)
M009-SPH-FRS-DWG-GWST080-L1-11229
Room at Concourse Level.
FM 200 Fire Suppression & Detection System for ELE (CL-81) Room
M009-SPH-FRS-DWG-GWST080-L1-11231
at Concourse Level.
FM 200 Fire Suppression & Detection System for ELE (CL-77) Room
M009-SPH-FRS-DWG-GWST080-L1-11233
at Concourse Level.
FM 200 Fire Suppression & Detection System for ELE (AG-29) Room
M009-SPH-FRS-DWG-GWST080-AG-11123
At Grade Level.
M009-SPH-TCH-PRO-00031 Page 8 of 23
FM 200 Fire Suppression & Detection System for UPS (L1-11) Room
M009-SPH-FRS-DWG-GWST080-L1-11023
At Lower Level.
FM 200 Fire Suppression & Detection System for MV/LV (L1-12) Room
M009-SPH-FRS-DWG-GWST080-L1-11025
At Lower Level.
FM 200 Fire Suppression & Detection System for TELL/IT (L1-8) Room
M009-SPH-FRS-DWG-GWST080-L1-11026
At Lower Level.
FM 200 Fire Suppression & Detection System for UPS (L1-17) Room
M009-SPH-FRS-DWG-GWST080-L1-11027
At Lower Level.
FM 200 Fire Suppression & Detection System for MV/LV (L1-16) Room
M009-SPH-FRS-DWG-GWST080-L1-11028
At Lower Level.
x MAR:
M009-SPH-MEP-MAR-00265 Material Submittal for FM 200 Pipe Fittings (Threaded & Grooved) - Shield-UK
x MIR:
M009-SPH-TCH-PRO-00031 Page 9 of 23
M009-REI-FRS-MIR-00041 Inspection for Painted Fire Fighting Pipes for FM 200 System
M009-REI-FRS-MIR-00065 Inspection for FM 200, Gas Containers with Liquid Level Indicators & Nozzles
x ITP:
x Plans:
Document No. Document Name
M009-SPH-TCH-PLN-00005 Project Testing & Commissioning Plan
M009-SPH-QMS-PLN-00005 Project Quality Plan
M009- SPH-PRJ-PLN-00003 Project Controls Plan
M009- SPH-HMS-PLN-00009 Health and Safety Plan
M009- SPH-PRM-PLN-00002 Information Management Plan
M009- SPH-DCM-PLN-00002 Electronic Document Management Plan (EDMS)
M009-SPH-RSK-PLN-00004 Risk Management Plan
M009- SPH-SHM-PLN-00003 Interface Management Plan
M009-SPH-EMP-PLN-00026 Construction Waste Management Plan
STAGE STAGE
STAGE NAME RESPONSIBLTY REMARKS
NO ABBRE
Stage 1 FAT Factor Acceptance Test REDCO For stage (1 & 2) Covered IRN Refer to Testing &
Commissioning Plan (MEP Subcontractor) #
Stage 2 IT Installation Test REDCO M009-SPH-MEP-PLN-00003 (ANNEXUTE-A2)
Stage 3 P-SAT Partial Standalone Test REDCO
Part of this procedure
Stage 4 SAT Standalone Test REDCO
Stage 5 SIT System Integration Test L&T For Stage (5 & 6) by L&T (BACS PRO &ITP)
M009-SPH-MEP-ITP-40003
Stage 6 SPT System Performance Test L&T M009-SPH-MHV-PRO-00033
M009-SPH-TCH-PRO-00031 Page 10 of 23
SPH JV, Subcontractor and PMC etc responsibilities are as below according to Qatar Rail Guideline.
M009-SPH-TCH-PRO-00031 Page 11 of 23
SPH-JV
GROUP BK
-- 'lQ Company
!l ~ R e.
~~
e
.!: ~ a Q
Contributo;t ~
B ~ ~
"C
1:
&.
I
tl:
~
i
..0 ....
~ ==
c...
~
...
~ c
.3
"'
c c c
c c
c
c A c
c
A
A
c c
c
A C
M009-SPH-TCH-PRO-00031 Page 12 of 23
4.1 Labour
Following personnel of the specialized subcontractor will be working at site. The number and
organization may be changed to suit the work requirements.
3 T&C Engineer 1
4 Supervisor 1
5 Foremen’s 3
6 QA/QC Inspector 1
7 Technician 5
8 Helper 10
1. Digital Multimeter
2. Continuity Tester
3. Torque Wrench
Note:
x All Instrument should valid calibration Certificate and certificate should be available on site at
the time of testing
x Equipment may be substituted subject to availability and actual requirements on the day.
x The type and quantities of equipment are subject to change to suit the site requirements and to
meet the construction program.
M009-SPH-TCH-PRO-00031 Page 13 of 23
Items which are a part of, or intended to be used permanently on, any of the systems of the
project shall not be used as an element of the testing setups for the purposes of testing.
The concerned Site Engineer or General Foreman will be responsible to ensure compliance for
these operations and the site QA / QC Engineer will carry out quality control checks and report
the inspection results.
x All workers will receive a site induction and be issued with PPE (hard hat, safety glasses,
safety vest, safety shoes) including hard hat with a SPH Inducted sticker before entering
to site to work.
x Regular Tool Box talks are held, and attendance logged.
x The Emergency Response Plan is in place and will be strictly adhered to.
x In the event of any accident the HSE Incident Escalation Matrix will be followed at all
times.
x Specific HSE Hazards are mitigated in the Risk Assessment.
x To prevent accident during the implementation of the above activities, all relevant safety
measures shall be strictly implemented by the site engineers and the HSE team.
x Tags used must be highly visible with prominent warning to warn employees of the
danger of reenergising the equipment
M009-SPH-TCH-PRO-00031 Page 14 of 23
7. Test the energy device controls to ensure equipment is de-energized and locked out.
8. Place key of safety padlock in Group Lockout Box and secure Group Lockout Box with
their own personal padlock.
9. Each person working on the equipment should put their own personal padlock on the
Group Lockout Box prior to commencing any work.
10. Perform activity and do not bypass the lockout. The activity shall be done in
conjunction with and as set out in a ‘Permits to Work’ document.
11. On completion of activities, follow the agreed procedures to reactivate the equipment.
x Remove any blocks put in place and re-install any safety guards.
x Remove personal padlock from Group Lockout Box
x Once all personal padlocks have been removed from the Group Lockout Box, keys
to the safety padlocks are removed and used to remove all lockout devices and
tags.
x Re-start the equipment and test to ensure all is ok.
x Cancel the ‘Permits to Work’ and sign off the work.
x Let the relevant employees know that the equipment is ready for use.
x Fire prevention systems and pollution control equipment will be provided for
storage facilities where necessary, to prevent fires or the releases of hazardous
materials to the environment;
x Containers intended for hazardous waste disposal will not be used for other
purposes unless they are specifically labelled for that purpose. Rusty, dented or
defective containers for waste accumulation or storage will not be used;
x Hazardous waste will be retained in a secure area with an impervious bunded
base;
x Secondary containment is required for liquid hazardous waste or other waste that
might be released into the environment, such as dusts, powders, and shavings.
x The conceptual design for the hazardous waste storage facility is part of the
CWMP.
x Hazardous waste will be disposed of in the area designated by municipality.
Incompatible hazardous wastes will not be transported together.
7 Risk Assessment
The Risk Assessment for this work is attached in Appendix 1.
M009-SPH-TCH-PRO-00031 Page 15 of 23
M009-SPH-TCH-PRO-00031 Page 16 of 23
T&C
G..,.,le
. 1_ .
FAT Factory
Acceptance
Certificate
IRE
Installation I I Construction Drawing Design
Start from right t o
left
Stage 1 Stage 2
•
IRN
Stage 3 --+- (Constru c t ion
complete)
PSAT
Stage 4
SAT
(TAB
Ve ntilation
S y s tems)
Ll(lnteg~~~ion
t o BACS
control)
of
StageS
HVACsystems ~----,-----------------._
QCDD
Stage 6
S y stem Staff Training
Performance & Handove r
•
Test (SPT) PCCW issued
Page 11
S :\MEP & PSA\ MEP\20 T esting and Commissioning\4 Guideline
M009-SPH-TCH-PRO-00031 Page 17 of 23
8.1.2 Pre-Commissioning
This Check shall be conducted to verify the continuity loop resistance and correct polarity of
wiring connections in all devices for each loop to ensure operation of the FM200 System.
Test Procedure.
x Set the Digital multi-meter to continuity test mode (indicate with a buzzer symbol).
x Check the continuity of loop in and out cables and the polarity of their connections
on each device in a loop.
x A buzzer sound will be heard if a continuity exists, otherwise the conductor is either
broken or wrongly wire. Check the wirings until correct continuity test result is
obtained.
x Measured the resistance of each loop with the digital multi-meter and record the
actual reading in the attached test form.
This test shall be conducted to ensure the healthiness of the insulation of the loop cables/
wires such that no conductors are either shorted or grounded. It has to be conducted with
the power supply disconnected. Detectors and other voltage sensitive device/equipment
must also be disconnected from circuits undergoing insulation resistance test. Failure to
observe this precaution may result in serious damage necessitating costly replacements.
a) Core 1 to Earth.
Testing Procedure.
x Set the voltage of the insulation resistance tester to 500VDC.
x Put the test leads between core 1 and earth conductor.
x Press the test button to apply the test voltage and record the insulation resistance
reading in the attached test form.
b) Core2 to Earth.
Testing Procedure
x Set the voltage of the insulation resistance tester to 500VDC.
x Put the test leads between core 2 and earth conductor.
M009-SPH-TCH-PRO-00031 Page 18 of 23
A puff test or flow is to performed on the piping network to verify that flow is continuous and
the piping and nozzles are unobstructed.
Test procedure.
x Check and ensure that the piping network for the FM 200 system is completed
including the nozzles.
x Connect the piping network to an air compressor + air dyer unit which will be the
source of dry air to be used for the puff test or flow test.
x Release dry air and let if low on the piping network for the puff test.
x Check each nozzle in the protected area/room and verity if there is proper air
discharge on each on nozzle.
x Record test results in the attached test form.
Acceptance Norm: Results of the checks and verification must confirm that the piping
network and the nozzles are unobstructed.
The purpose of the room integrity test is to quantify leakage from an enclosure and use the
total leakage area to provide a prediction of the enclosure’s ability to retain FM-200 and to
enable an assessment to be made of the enclosure’s structure in respect of overpressure
venting requirements.
The procedure involves the fitting of variable speed fan unit into an existing doorway by
means of an adjustable doorframe and using the fan to pressurize and/or De-pressurize the
enclosure with a known (or measured) quantity of air.
The first part use a fan that quantifies the leakage sites within the enclosure and provided a
calculation of the effective leakage rate. The effective leakage rate can then be used in
calculations to determine the requirements for additional pressure relief venting.
The second part of the test involves us a computer model to predict whether FFM-200 gas
would be held for a specific period of time at an agreed height of interest.
The two parts of the enclosure integrity testing are as follows.
M009-SPH-TCH-PRO-00031 Page 19 of 23
The equipment to be used to test the integrity of the space consists of the following.
a) Variable speed fan with a suitable frame of mounting in a doorway or opening.
b) Pressure gauges and thermometers.
c) Computer- With software retorted discharge simulator version HA 6.1 HP.
1. Ensure that the FM200 system is conducted a visual inspection shall be first be
carried out. The test shall include the following.
2. Ensure that the FM200 was installed within approved design calculation and shop
drawing.
3. Check each device operation and verify correct labelling/location display in the
FSCP.
4. The system has been completely pneumatically pressure leak tested in a closed
circuit in 10 minutes at 40 psi; verify that the pressure at end has not dropped more
than 20% in accordance with NFPA 2001.
5. Ensure the cable test has been completed.
6. The wire and cable are properly terminated to the FM200 and power supply is
available both normal and emergency.
7. The cable shall verify that has been installed in fully accordance of approved design.
8. Ensure all installed piping are in proper size fitting and location within accordance of
approved material submittal and shop drawing.
9. Verify if the pipes are properly supported and clearance near to nozzle is acceptable.
10. Ensure cylinder is properly fixed.
11. Ensure the final amount of FM200 shown on the cylinder tag shall be based on as
built measurement of the enclosure integrity test of each room.
12. Ensure the detectors alarm bell & other accessories are installed as per approved
shop drawing.
13. Ensure the battery is free from corrosion or leakage. Tightness of connection shall be
checked.
14. Testing of all the devices under battery supply has to be contacted.
15. Ensure the room integrity test is completed.
Before performing preliminary functional test, which will result in operation of alarms
notify all concerned personal who may be affected.
It shall be noted also to ensure that before carrying out Pre- functional testing the IVO
and IRM are to be kept disconnected from the cylinders.
Test Procedure.
1) Smoke Detector Test.
M009-SPH-TCH-PRO-00031 Page 21 of 23
When system functional test is completed each agent storage container will be
reconnected so that activation of the impulse release modules will release the agent. The
system will return to its fully operational design condition. The alarm receiving office and
all concerned personal at the end user’s facility will be notified that the system functional
test is completed and that the system has returned to full service condition.
M009-SPH-TCH-PRO-00031 Page 22 of 23
After a successful completion of this stage, Acceptance Certificate (AC) will be released.
M009-SPH-TCH-PRO-00031 Page 23 of 23
RISK ASSESSMENT
Appendix 1
~ ~~"""""-
RISK ASSESSMENT
l!.I!J.&l.LI
JAUOI •tllll40tH (aOiJf' ....,. WBK
...
SP H - J\1
GREEN LINE - ELEVATED & iT:ciUOI
Testing & Commissioning of FM 200
~ System.
International
2 I 3 4 5
l iKELYHOOD VERY VERY ALMOST
UNLIKELY LIKELY
UNLIKELY LIKELY CERTAIN
Ensure safe access & egress to WOI1< area Is provided. Inspected and tagged.
Ensure proper illumination on access and access routes,
Steps/rungs inspected and without damage.
Engtneer I HSE
Ensure handrails are used and proper fooling on steps.
2 Cuts. bru1ses. sprains. severe injury 16 6 IReoresentatove 1 FOfeman
Do not block access by storing materials.
Operator
Proper routing of cables.
Provide information signs.
Ensure good housekeeping always.
Page l of 4
Ensure safe access and egress to~ area.
Lift using correct lifting principle i.e. feet apart. finmly grip load, keep load close to lhe body, keep back
avOid twisting ex bend•ng too much, when lifting from ground; bend knees and lift weight us•ng your
_muscles.
Ensure good housekeeping in lhe area,
Watch oul for un even surfaces.
and lnp, repetitive worl<, poor
Ensure no spillage or slippery surface.
Iillumination, protruding sharp objects. Ensure proper gloves are used along with other PPE. Site Eng1neer I HSE
materials to work slacking, stacking al strain/sprain, cuts, crush
3 12 Engage additional help is the load Is too heavy. 6 Representative I Foreman
height, starting matenals . fracture
• Proper storage of materials i.e. no storing near edge, improper height. nol blocking access ways etc. Operator
COSHH items, unsafe
• Ensure proper illumination in the area.
Ensure protruding objects are covered.
• Ensure MSDS for COSHH items.
·Do not store excess of flammable materials at site.
• Bring only quantity required for lhe day.
• Ensure no hot works in the area.
• Ensure fire extinguisher is available near by.
Pogo Z of 4
Mobilizing materials to work
area.
Stle Eng1neer I HSE
58 10
Representative I Foreman
Mobilizing matenals to work STARRT briefing for operatives prior to start work.
area. Competent persons.
Keep the wor1< place free of obstructions by carrying out regular housekeeping. S1te Eng1neer I HSE
5C •nJury, cuts, brv1ses 3 9 Do not carry tools 01' materials when using ladder Representative I Foreman
Do not lean your body during working on ladder 01' scaffold. Opera tO< I Rtgger
Job rotation and adequate supply of drinking water.
Wort<ing area should be illuminated
Poge 3 of4
• STARRT briefing to operatives
• Obtain LOTO Permit to wor1<.
• Only competent persons shall be deployed for testing activity.
• Ensure shop drawings and method statements are verified and bnefed to all.
Burns. cuts. severe 1njury. 3 3 9 Cordon off the test area and do not allow unauthorized persons. Post sognage's.
IReoresentat1ve I Foreman
Ensure proper iHumination in !he area.
Set the resistance lest device for cable and 500 Volts for wires
Earthing shall be installed as per verified shop drawings and project specifications.
Ensure test equipment shall have valid calibration certificates.
P~4 of4