Testing and Commissioning Procedure of Air
Handling Unit (AHU)
(REDCO)
RTC/082/2013
Document No.:
~~~~~ Revision iB
Document Type PRO - Procedure
Revision History
M009-SPH-TCH-PR0-00026 Page 1 of 2 1
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
I I I
I
I
I
Ci.,pqc.WI c..J.:::.U L..:..J-! CK:.~
S AUDI B IN L AO IN G R OU P IIIBK
SPH-.JV
GREEN LINE- ELEVATED & AT-GRADE
f\edco International
M009-SPH-TCH-PRO-00026 Page 2 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
TABLE OF CONTENTS
LIST OF APPENDICES ..................................................................................................... 4
HARDCOPY DISTRIBUTION LIST ................................................................................... 5
ABBREVIATIONS ............................................................................................................. 6
1 PURPOSE .................................................................................................................. 7
1.1 General issues ................................................................................................................ 7
1.2 Purpose ........................................................................................................................... 7
2 SCOPE ........................................................................................................................ 7
2.1 Interdependence with Management Plans .................................................................... 7
2.2 Revision of T&C Procedure Documents ........................................................................ 9
2.3 Testing and Commissioning Stages .............................................................................. 9
3 ROLES AND RESPONSIBILITIES ........................................................................... 10
3.1 (SKM Air Conditioning - Manufacturer) / Representative ............................................11
3.2 Sub-Contractor ...............................................................................................................11
4 RESOURCES............................................................................................................ 12
4.1 Labour.............................................................................................................................12
4.2 Equipment Used .............................................................................................................13
4.2.1 General Equipment used for this activity:................................................................13
5 QUALITY ASSURANCE/ QUALITY CONTROL....................................................... 14
6 HEALTH, SAFETY, ENVIRONMENT ....................................................................... 14
6.1 Lockout/Tagout Procedure ............................................................................................14
6.2 Hazardous Waste Management .....................................................................................15
7 Risk Assessment..................................................................................................... 15
8 METHODOLOGY ...................................................................................................... 15
8.1 PSAT (Partial Stand-Alone Test) ...................................................................................15
8.1.1 Pre-Request For PSAT...............................................................................................15
8.2 SAT (Stand-Alon Test) ...................................................................................................18
8.2.1 Commissioning and Start-Up ....................................................................................18
8.2.2 FAN Start-Up ..............................................................................................................19
8.2.3 Cooling Coil for AHU .................................................................................................19
8.2.4 Air Flow and Static Pressure Measurements ...........................................................20
8.2.5 Sound Test .................................................................................................................20
Test Acceptance Criteria.......................................................................................................20
8.3 MEP System Integration Test (SIT) ...............................................................................20
8.4 System Performance Test (SPT) ...................................................................................21
M009-SPH-TCH-PRO-00026 Page 3 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
LIST OF APPENDICES
Appendix 1 – Risk Assessment
Appendix 2 – Test Form
M009-SPH-TCH-PRO-00026 Page 4 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
HARDCOPY DISTRIBUTION LIST
This document is not controlled when printed. The controlled version is held by the Document
Controller on the Project Server’s valid Documents Folder.
008
010
011
012
* The final distribution may be modified after consultation with Main Contractor.
** It is the responsibility of the Station Manager to provide this T &C Procedure to the respective
Project or Site Engineers and obtain sign off that they have received and understood the
document. Please refer to the communication protocol
M009-SPH-TCH-PRO-00026 Page 5 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
ABBREVIATIONS
M009-SPH-TCH-PRO-00026 Page 6 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
1 PURPOSE
1.1 General issues
This document is to present the T&C Procedure as required by subcontract documents for Green
Line Elevated & At Grade Project.
This document was composed exclusively for the Qatar Railway ‘Green Line Elevated & at Grade’
Project. All the requirements listed in the above referred tender document were taken into account.
The company has Quality Management System Certificate of ISO 9001: 2008, Certificate of ISO
14001: 2004 of Environmental Management System. Furthermore, it applies the BS OSHAS
18001: 2007 on Occupational Health and Safety Management System.
1.2 Purpose
The purpose of this T&C Procedure is to explain step by step method for Testing and
Commissioning of Air Handling Unit (AHU) guidelines contained herein so as to ensure that the
job execution complies with project requirement and serves the intended function to satisfactory
level.
2 SCOPE
Scope of this PRO is the Testing and Commissioning of Air Handling Unit (AHU)
This document includes the following either in the main body or in the Appendices:
The following documents are referred to either to support the implementation of the T&C Procedure
or are a pre-requisite to its implementation:
M009-SPH-TCH-PRO-00026 Page 7 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
x SPE:
x MAR:
x MS:
x ITP:
Document No. Document Name
M009-REI-MEP-ITP-00042 Inspection and Test Plan for Testing & Commissioning of Air Handling Unit
x Plans:
Document No. Document Name
M009-SPH-TCH-PLN-00005 Project Testing & Commissioning Plan
M009-SPH-QMS-PLN-00005 Project Quality Plan
M009- SPH-PRJ-PLN-00003 Project Controls Plan
M009- SPH-HMS-PLN-00009 Health and Safety Plan
M009- SPH-PRM-PLN-00002 Information Management Plan
M009- SPH-DCM-PLN-00002 Electronic Document Management Plan (EDMS)
M009-REI-RSK-PLN-00001 Risk Management Plan
M009- SPH-SHM-PLN-00003 Interface Management Plan
M009-SPH-EMP-PLN-00026 Construction Waste Management Plan
M009-SPH-TCH-PRO-00026 Page 8 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
2.2 Revision of T&C Procedure Documents
The revision of this T&C Procedure shall be done when:
STAGE STAGE
STAGE NAME RESPONSIBLTY REMARKS
NO ABBRE
Stage 1 FAT Factor Acceptance Test REDCO For stage (1 & 2) Covered IRN Refer to Testing &
Commissioning Plan (MEP Subcontractor) #
Stage 2 IT Installation Test REDCO M009-SPH-MEP-PLN-00003 (ANNEXUTE-A2)
Stage 3 P-SAT Partial Standalone Test REDCO
Part of this procedure
Stage 4 SAT Standalone Test REDCO
Stage 5 SIT System Integration Test L&T For Stage (5 & 6) by L&T (BACS PRO & ITP)
M009-SPH-MEP-ITP-40003
Stage 6 SPT System Performance Test L&T PRO#M009-SPH-MHV-PRO-00033
M009-SPH-TCH-PRO-00026 Page 9 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
I I I
I
I
I
~..:2~ 1 ~.:2UL.:.M~~
SAUD I BI N L AO I N C R OUP
,~
...,. ... IIIBK
-----------------------------
SPH-.JV
GREEN LINE- ELEVAT ED & AT-GRADE f\edco International
3 ROLES AND RESPONSIBILITIES
Below the Appendix B Shown all concerns responsibilities.
Exam ple fo r RACI Matr ix Guideline fo r MEP Testing & Commissioning Plan
Appendix B - Attachment B - 2
_.,. -~
Comm issioning Authority
~
..
Cl.
~ !!c:: .. ...
0
~ .!: .!: .;
Cl.
~
- Approve (sign-off) c:: c:: Cll
~ u
.!: 1!.' 0 0
Contributor ~
c: "'
~
Cll
~ ~
Cl.
.!: ~~..
Cll
u .t tl
2
u
Cl
......
8 Cl.
c::
...8
u "'
~=
oil
t- ....
c:: t: ~
In formed
Cll
a::
:::J
oil
t- "'~
u
!.
:I:
c..
V)
...
c:: c::
8
"' "'
c c c
c c
c
Page 17
M009-SPH-TCH-PRO-00026 Page 10 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
3.1 (SKM Air Conditioning - Manufacturer) / Representative
The Supplier/Manufacturer (Mannai Trading & Contracting - Supplier) Representative shall be
inspect all power termination/connections and AHU installation as per manufacturer requirements.
After inspection/confirmation power of equipment shall be switched on and he will witness the
testing.
3.2 Sub-Contractor
The Sub-Contractor is responsible for ensuring that the overall requirements are understood and
followed by all parties involved in testing commissioning. All personnel involved in the works will
be responsible for their own action/omission, be accountable for any unsafe actions/conditions
in which they created and to ensure that they follow the safe working procedure of the approved
Procedure.
Subcontractor's key personnel will have the roles and responsibilities as below:
a) T&C Manager The T&C Manager is responsible for Verifying the testing work carried out
in accordance with the requirements of the contract. And ensuring the quality standards set
for the Testing work are achieved and the work team adhere to the QA/ QC and HSE
requirements of the contract.
b) T&C Site Engineer T&C Site Engineer is responsible for Ensuring that the works are being
carried out in accordance with contract requirements and this T&C Procedure. He will
manage the testing activities to ensure that the team carries out the works in time with the
delivery schedule. Implementation of and adherence of the team to the QA/ QC and HSE
policies and procedure.
c) QA / QC Engineer - He is responsible and accountable for conducting surveillance and
inspection duties at various stages of the project delivery to ensure compliance to contract
requirements and to QA / QC requirements. He will ensure that the necessary corrective
action is undertaken against any recorded non-conformance. He will work in close
coordination with all the inter-related disciplines and stakeholders of the project. He is
responsible for preparation of all QA/QC related documents/procedures etc. Work in close
coordination with Supervision Engineer and Main Contractor’s QC Engineer to fulfil the QC
requirements and reports to QC Manager.
M009-SPH-TCH-PRO-00026 Page 11 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
responsible for checking the construction works. He will be responsible and accountable to
take reasonable care of himself and the safety of others working nearby. He will make sure
that all the workforce is briefed about the task related hazards, control measures and
availability and use of the relevant PPEs.
h) Technicians/Helpers - They will be responsible and accountable for the safety of themselves
and the others who can be affected by their work activities and shall be responsible for
installing the equipment at the exact location marked by the surveyor and according to the
shop drawings, to perform safely physical installation, handling the material and required
equipment, positioning and installation of materials shall ensure quality installations. Duties
include using, supplying or holding materials or tools, and cleaning work area and
equipment. They will make sure that required work permit has been received from the
relevant authorities and the control measures mentioned in the permit are being adhered
to.
All the workforce is responsible and accountable to take reasonable care of their safety and
safety of the others working nearby them. They will be responsible and accountable to
adhere to all the HSSE rule and regulations told them in Induction trainings, TBTs and
STARRT briefings. They will also be responsible to use the PPE’s provided to them for their
safety and also not to alter with them.
4 RESOURCES
The following equipment and material are anticipated to be used in carrying out the works:
4.1 Labour
Following personnel of the specialized subcontractor will be working at site. The number and
organization may be changed to suit the work requirements
M009-SPH-TCH-PRO-00026 Page 12 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
4.2 Equipment Used
4.2.1 General Equipment used for this activity:
Note:
x All Instrument should valid calibration Certificate and certificate should be available on site
at the time of testing
x Equipment may be substituted subject to availability and actual requirements on the day.
x The type and quantities of equipment are subject to change to suit the site requirements and
to meet the construction program.
M009-SPH-TCH-PRO-00026 Page 13 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
5 QUALITY ASSURANCE/ QUALITY CONTROL
Package Project Director is responsible of pre-working control and shall provide specific resources
to the work to be performed and have to determinate the verification, validation, monitoring,
inspection to the work as well as criteria for product acceptance and quality record needed.
Items which are a part of, or intended to be used permanently on, any of the systems of the project
shall not be used as an element of the testing setups for the purposes of testing.
The concerned Site Engineer or General Foreman will be responsible to ensure compliance for
these operations and the site QA / QC Engineer will carry out quality control checks and report the
inspection results.
x All workers will receive a site induction and be issued with PPE (hard hat, safety glasses,
safety vest, safety shoes) including hard hat with a SPH Inducted sticker before entering to
site to work.
x Regular Tool Box talks are held and attendance logged.
x The Emergency Response Plan is in place and will be strictly adhered to.
x In the event of any accident the HSE Incident Escalation Matrix will be followed at all times.
x Specific HSE Hazards are mitigated in the Risk Assessment.
x To prevent accident during the implementation of the above activities, all relevant safety
measures shall be strictly implemented by the site engineers and the HSE team.
x Tags used must be highly visible with prominent warning to warn employees of the
danger of reenergising the equipment
x Tags must be durable and be securely fastened to the lockout device
x Tag details must be completed in full
7. Test the energy device controls to ensure equipment is de-energized and locked out.
M009-SPH-TCH-PRO-00026 Page 14 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
8. Place key of safety padlock in Group Lockout Box and secure Group Lockout Box with
their own personal padlock.
9. Each person working on the equipment should put their own personal padlock on the
Group Lockout Box prior to commencing any work.
10. Perform activity and do not bypass the lockout. The activity shall be done in conjunction
with and as set out in a ‘Permits to Work’ document.
11. On completion of activities, follow the agreed procedures to reactivate the equipment.
x Remove any blocks put in place and re-install any safety guards.
x Remove personal padlock from Group Lockout Box
x Once all personal padlocks have been removed from the Group Lockout Box, keys
to the safety padlocks are removed and used to remove all lockout devices and
tags.
x Re-start the equipment and test to ensure all is ok.
x Cancel the ‘Permits to Work’ and sign off the work.
x Let the relevant employees know that the equipment is ready for use.
x Fire prevention systems and pollution control equipment will be provided for storage
facilities where necessary, to prevent fires or the releases of hazardous materials
to the environment;
x Containers intended for hazardous waste disposal will not be used for other
purposes unless they are specifically labelled for that purpose. Rusty, dented or
defective containers for waste accumulation or storage will not be used;
x Hazardous waste will be retained in a secure area with an impervious bunded base;
x Secondary containment is required for liquid hazardous waste or other waste that
might be released into the environment, such as dusts, powders, and shavings.
x The conceptual design for the hazardous waste storage facility is part of the CWMP.
x Hazardous waste will be disposed of in the area designated by municipality.
Incompatible hazardous wastes will not be transported together.
7 Risk Assessment
The Risk Assessment for this work is attached in Appendix 1.
8 METHODOLOGY
8.1 PSAT (Partial Stand-Alone Test)
Air handling unit commissioning will not commence until the installation mechanical and
electrical IRE signed off.
Verify and confirm that the AHU installation completion checklists are available and duly
signed by concerned parties.
x All Duct work installation are completed, and all IRE are approved.
M009-SPH-TCH-PRO-00026 Page 15 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
x Ensure there is valid permit to work is issue.
x Ensure that IRN are prepared by construction and Approved by all parties.
x Ensure all CHW system are Flushed out Properly and IRE are approved.
x Duct access doors are securely closed.
x VCD and all others damper should be open Position.
x MCC panels are installed and commissioned.
x Ensure sample of test pack has been prepared.
x Ensure that lock out tag out in place.
x Ensure HSE in place.
x Ensure that as build / red line drawing have been provided.
x Ensure approved Procedure is on the site.
1. Ensure that the clearance from manufacturer/supplier before power supply connection
to the equipment.
2. Ensure that the Air Handling Unit (AHU) installation is complete and mechanical
completion is approved.
3. Ensure that no damage has occurred between mechanical completion and During
Pre-commissioning.
4. Check AHU installation as per the approved shop drawing and manufacture
recommendation.
5. Check for proper electrical power, control panel and earthing connection as per
approved drawing and all field wiring to be pre- tested for continue and insulation
resistance.
6. Verify the correct voltage phase and cycles.
7. Initial check and verification of the following items prior to any start-up are required.
8.1.1.1 FAN
1. Check if:
x There are no objects within a range of the fan, which might be sucked into
the wheel once the fan is turned on.
x The fan's wheel rotates freely, without any friction against the casing
elements.
x The fan's designed rotary speed will not be exceeded.
x All dampers on the ventilation ducts network are set and fully open.
x The motor rotation direction is the same as a direction of the arrow placed
on the fan's casing (switch on the fan by pulsing). If they are arranging in
different directions, change with each other any two phases in the motor
connection box or change rotation direction on the frequency converter.
2. Wheel is balance and with the appropriate type.
3. Bearings are properly lubricated as per supplier recommendation.
4. Drive is aligned.
5. Drive set screw tight.
6. Belt tension acceptable and location of pulleys is in line.
7. Transit bolts removed.
8. Base is level and free.
9. Vibration isolators (Springs & Compression) installed and no obstruction.
8.1.1.2 FILTERS
M009-SPH-TCH-PRO-00026 Page 16 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
8.1.1.3 MOTOR
8.1.1.4 Electrical
1. Check pipe connection Chilled water supply and Return properly connected.
2. Valves open and set
3. Piping leakage
4. Check for fin spacing and condition
5. Check for obstruction or debris
6. Air Vents installed and functional
7. Condensate drain complete and connected
1. Visually check for doors and casing integrity, leaks and any signs of damage
2. Check for adequate clearance around unit for service.
3. Check if all components are accessible for maintenance.
4. Check all doors can be opened & Closed easily.
1. Duct system cleaning, pressure and leak test is done and inspected.
2. Following the successful conclusion of pre- commissioning, the air handling unit will be
run, and an initial volume acquired with the dampers set and fixed at full fresh air (supply
side) and full discharge air (return side).
3. Check to see that the running current of the fan motor can be controlled manually to
compensate for high amperage due to operating without the bag filter.
M009-SPH-TCH-PRO-00026 Page 17 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
4. The fresh air and supply air quantities will now be set preferentially. There will be NO
return air at this time. Return air dampers should be fully closed.
5. Measurements on the A.H.U will be obtained for and will generally include motor
running current, fan speed, motor speed, on / off coil temperatures and static pressure
readings across components.
1. The building envelope should ideally be complete i.e. a permanent or temporary doors
and windows fitted. Internal rooms to be clean and free of debris.
2. All control and regulating dampers should be fully open and systems should be clean and
dirt free.
3. Commissioning filters should be installed to protect the cooling coils during the operation
of this equipment. High efficiency bag filters SHOULD NOT be installed.
1. Obtain the results of both Dynamic and Static flushing procedures prior to starting any
pumps.
2. Obtain the results of the “Pump alignment”
3. Obtain the results of chemical treatment and analysis to ensure that the chilled water
lines are protected against corrosion and that PH and, Fe and turbidity levels are
consistent with the current CIBSE guidelines.
4. Establish that there is a procedure in place to monitor chemical levels throughout the
duration of the temporary operation.
5. Ensure that all heating / chilled water pipes have been fully insulated and that there are
no breaks which, could cause damage to, or destroy the vapor seal.
6. Ensure that all manual control valves and isolation valves are in the “Fully Open”
position, and that the by-pass valve is closed
7. Ensure that the strainer is clean.
8. Ensure that either temporary or permanent pressure gauges are installed on the supply
and return sides of the pumps. And AHU’s
9. Re-check the water pressure drop across the coil and present the required flowrate thru
any manual balancing device installed in the system.
10. Follow the pre-start-up check as listed in attached checklist. Once all parameters have
been met, the system can be safely energized and run.
After a successful completion of this stage, Pre-Commissioning Certificate (PCC) will be
released.
1) Ensure that all the Pre-Commissioning checks are carried out successfully.
2) The pre- commissioning & commissioning of the AHU shall be completed prior to
commissioning of the AHU. The same shall be carried out in line with the approved
procedure.
3) The objective of air handling commissioning is as follows: To ensure that the correct
unit has been installed as per equipment schedule / project specification.
4) Ensure that all the fan rotation, electrical interlocks, vibrations, noise, motor amps, fan
rpm, volts, frequency, speed, the correct chilled water flowrate and the required
pressure drops across each component the correct chilled water flowrate and the
required pressure drops across each component of the air handling units are within
the manufacturer’s specified limits.
M009-SPH-TCH-PRO-00026 Page 18 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
5) Ensure that the air handling unit is delivering the required air volume and in relation to
the required supply temperature and return temperature. Also, ensuring that the actual
total air volume meets the required flowrates in each air terminal.
6) Ensure that the air handling unit satisfies the required space pressurization in respond
to the required supply air, return air and fresh air.
1) All electrical, water & ductwork connections of the unit must be completed by a
qualified person.
2) Check that all electrical connections comply with the wiring diagram and the thermal
protection is operational.
3) Completely stress-free connections are essential. The pipework of the coils should be
arranged to facilitate easy removal of the coil for maintenance purposes.
4) Check that the coil connections and valves are not leaking. If there are leaks, rectify
the problem.
M009-SPH-TCH-PRO-00026 Page 19 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
5) Cooling coil sections are fitted with condensate drains. Check that these are properly
fitted to allow draining and avoid air suction and water carry-over.
6) Check piping for any leaks. Open or close valve to check for proper operation.
7) Ensure that no air bypass occurs within the AHU and that proper sealing is carried out.
8) For chilled water, proprietary corrosion inhibitor should be considered in the water
remembering that the coils are made of copper tubes on the fluid side.
9) Never to use untreated or improperly treated water in unit coils which may cause
scaling, erosion, corrosion, algae, etc.
1) Select the type of instrument required for the tests. Liquid manometers or digital
micro manometers Are recommended for the static pressure test. Pitot tube set of
proper length with inclined liquid Manometers or digital micro manometers are
recommended for the flow test.
2) Ensure system ductwork is installed and 100% complete.
3) Take the static pressure measurements.
4) Perform Pitot tube Traverse test.
5) Calculate the air flow by multiplying the average air velocity by the area of the
traverse.
6) Record the readings on the test sheet.
7) Acceptance criteria as per the Project Specification.
After a successful completion of this stage, Partial Acceptance Certificates (PAC) will be
released.
M009-SPH-TCH-PRO-00026 Page 20 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
Operation and IO Point List.
After a successful completion of this stage, Acceptance Certificate (AC) will be released.
M009-SPH-TCH-PRO-00026 Page 21 of 21
Testing and Commissioning Procedure for Air Handling Unit (AHU) (REDCO)
APPENDIX 1
RISK ASSESSMENT
I WliilJ :~~'!,. ~·.';;'.':O"n~~:m-:
&PH•.JV
~ WBK
QRCitN CU'"'d- tLCVATtD & AT:ORADC
Testing and Commissioning of
~ Air Handling (AHU) Units
R,edco lmemalional
Risk Matrix
CATASTROPHIC 20 25 5 FATALITY
MAJOR NJURY I
CRITICAL 4 12 - 20 4 LLI'ESS
SERIOUS NJURY I
SERIOUS 3 6 9 12 15 3 LLI'ESS
1 2 3 4 5
L t KEL YHOOD VERY VERY A LMOST
UNLIKELY LIKELY
UNLIKELY LIKELY CERTAIN
P~lof4
lt may cause injuries such as
• STARRT briefing to operatives prior to start worl<.
Back Strain. slipped discs
•Manual Handling is to be avoided at all times where ever possible.
Lacerations, crushing of hands
•Use mechanical means wherever possible.
and fingers
• Assess the weight of load before manual handling. 10
Various strains, sprains
•Keep the weight close to your center of gravity.
etc.Cuts, crush injury, severe
•Carry material close to ground while moving.
fatality, property damage.
or broken toes or feet.
Poor illumination, damaged Ensure safe acces & egress to work area is provided. Inspected and tagged.
Ensure proper illumination on access and access routes,
steps/rungs, blocked access.
Steps/rungs inspected and without damage.
materials stored at access.
5 & egress to worl< area
bruises, sprains. severe Ensure handrails are used and proper fooling on steps.
poor housekeeping, cable 6
running on access, no Do not block access by storing materials.
access, signs missing, slip & Proper routing of cables.
Provide inrormation signs.
trip
Ensure good housekeeping always.
Page 2 of 4
STARRT briefing for operatives prior to start wor1<.
Proper Supervision.
Keep the wor1< place free of obstructions by canying out regular housekeeping.
Do not block access by storing materials.
Minor lnjury.cuts. bruises 3 Signs must be displayed to indicate the routes to be taken by persons. changes in routes must be clearty communicated.
Wor1<ing area should be illuminated
• Proper routing of cables.
• Ensure good housekeeping always.
Adversed Wor1<ino Cond~ions • STARRT bnefiOQ for operatives prior lo start wor1<.
Working In cramped wor1< space. • Competent persons.
Preparation for testing and
7 A person will be at risk of protruding • Keep the wor1< place free of obstnuctions by canying out regular housekeeping.
Cornmensioing of AH U
I
sharp objects. heat exhaustion etc. Minor injury ,cuts. bruises • Do not carry tools or materials when using ladder 6
Over-reaching from • Do not lean your body during wor1<ing on ladder or scaffold.
Ladder,Materials being carried up. • Job rotation and adequate supply of drinking water.
Wor1<1ng under poor lightng. • Working area should be illuminated
P• 3 of4
RA Execution SPH • N
- - - --- -- - - - - - ------ --------
ill'l:liml ~ lllillml ~
Probablll
~
ty/Ukelih Conseq Risk l;tiifttmM;i; y m r
What could hurt me I othen or
mmam im act on the environment
Mi'f\tl.hl•••ac.lllr.rntrm
0
u~nce level What must be In pl~ee to prevent harm? (include specific responsibilities where applicable)
Page 4 of 4
APPENDIX 2
CHECK LIST
1111111~ J~ I ii.P_..,'~"u'-"~CJDo=
SAUOI aiNlAOIN CROUP
~
..... WBK ~~ PSAT( Partial Stand Alone Test)
I PRE-COMMISSIONING
SPH · .JV
GREEN LINE- ELEVATED & AT -GRADE f\edco International CHECKLIST FOR AHU
STATION IREREFNO
DWGREF
LOCATION
MESIJTP
MANUFACTURER SYSTEM
SERIAL. NO TYPE
CIIECKEOBY
NO. DESCRIPTION QIVQC Sapt'nision
T&C EncJow<r Dart REMARKS
ERChlter Eooci-r(SE)
I 1>4xumentation
1.6 Ensure thal the equipment are as per specification and as per approved drawings
2 Che<k List
Ensure that the Air Handling Unit (AHU) installation is complete and mec hanical
2. 1
completion is approved.
Ensure that no damage has occurred between mechanical completion and During Pre~
2.2
commissionin '·
Check AHU insrallarion as per the approved shop drawing and manufacture
2.3
recomrnendalion.
2.4 Check tha1 all Wiring are complele for mororized valve and valves are conunissioned.
Check for proper electrical power, control panel and earthing connectio n as per
2.5 approved drawing and all field wiring to be pre· tes ted fo.- contmue and insulation
resistance.
3 FAN
Check if there are no objects within a range o f the fan, which might be sucked into
3. 1
the wheel once the fan is turn on.
Check 1fthe fan's wheel rotates freely, w1thout any fncuo n agamst the casmg
3.2
element.
3.3 Check 1fthe fan 's des1gn rotary speed wlll not exceeded
3.4 Check if all dampers on the ventilation ducts network are set and fully open.
Check if tlle motor rotation direction is the same as the direction of the arrow placed
3.5
on the fan 's casm •
3.6 Wheel is balance and with appropriate type.
4 FILTERS
4 MOTOR
4.4 Earthing and protection device properly arc connected and mstalled
4.5 Drive belt guards are properly fitted and secured
8.2 Ensure the all duct work and pipe connections are completed
Coi1U1lents:
Ntmt
Position
Si&n.atur t
Date
DWG REF
LOCATION
MES/ITP
MANUFACTURER SYSTEM
COUNTRY OF
MODEL NO
ORIGIN
SERIAL NO TYPE
Size Serial No
Serial NO Power KW
External Static
Electrical Supply Volts/Phase!HZ
Ordered Dute: Pressure
Air Volume. Motor Currenr amps
Service Factor
START-UP INSPECTION
Electrical:
START-UP DATA
@ 12.5HZ @ 25.0HZ @ 37.5 HZ .@ SO.OHZ Manual Mode
Measured Amps
Measured Voltage
STATIC PARAMETER FAN/MOTOR SPEED
Design Actual Design Actual
Fresh Air Static Pressure ,Pa Fan Speed , rpm
Namr
Position
Signaturt
Date
J. All rcle\'ant Drawings and Documcu must be anached with it
2. • If Aplicable
I 14-02-18
Form No I M009-REI-QMS-FRM-00 138 I Revision I I lssuc:Oate I
~ SH~
~m ~
,...._ -...J
AIH~'DITIOif%
fOOPMOIT
UNIT
TAG
LOADING POINT
UNIT MODEL :
ISULATION
FLAT ALUM
UNIT VOLTAGE
FILTER SYNTH
VEE ALUM
FILTER SYNTH
AHU DATA
BAG 95%
FILTER 85%
MOTOR POWER KW
DAMPERS/A
DAMPER RIA
FULL LOAD CURRENT AMPS
DAMPER F/A
MIXING BOX
CURRENT DRAWN AMPS
ACCESS DOORS
SHAFT OIL
DESIGN BLOWER SPEED RPM
PVC ELIMINATOR
MAN
BLOWER SPEED TEST RPM AIR VENT
AUTO
MANOMETER
MOTOR HANDING
EXPANSION VAVLE
AIR/WATER TIGHTNESS
COIL HANDOING
BULK HEAD LIGHT
BELT GUARD
DRAIN HANDING
BLOWER MOUNTING
HUMIDIFIER
BLOWER MODEL
SANDTRAP LOWER
BIRD SCREEN
BELT SIZE
FINISH
IPAINT
jGALVANISED
HEATER POWER KW
NAMEPLATE
W .PROOF CNOPY
EXITE, GREASE NIPPLE
PULLEY ALLIGNMENT
BELT TENTION
WINDING INSULATION
DISCHARGE AIR GRILLE
WATER PUMP
I.O.MANUAL
ACRACLAD