Professional Documents
Culture Documents
Pressurization Unit
PRO - Procedure
03
04 --Issued
Issuedfor
forApproval
SONO
REDCO 07-02-2019
21/02/2019
07-02-2019
21/02/2019
21/02/2019
07-02-2019
21/02/2019
07-02-2019
07-02-2019
21/02/2019
0.1
1 21/02/2019
07-02-2019
II:! ci.!.':lq.c:.w.JI L.:.J .':IU LJ~ Cic. ~
SAUD I B INL AO I N G R OU P ldBK
SPH · JV
GREEN LINE - ELEVATED & AT-GRADE 1\edco International
Testing and Commissioning Procedure for
Pressurization Unit
(REDCO)
RTC/082/2013
Document No.:
00043 11
Revision IB
Document Type PRO- T&C Procedure
Revision History
Rev. No. Description of Revision Date of Revision
0.1 First Issue 15 AUG 2018
M009-SPH-TCH-PR0-00043 Page 1 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
Total Number of Pages: 18 including front pages and excluding appendices
M009-SPH-TCH-PRO-00043 Page 2 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
TABLE OF CONTENTS
LIST OF APPENDICES ..................................................................................................... 4
HARDCOPY DISTRIBUTION LIST ................................................................................... 5
ABBREVIATIONS ............................................................................................................. 6
1 PURPOSE .................................................................................................................. 7
1.1 General issues ............................................................................................................... 7
1.2 Purpose .......................................................................................................................... 7
2 SCOPE ........................................................................................................................ 7
2.1 Interdependence with Management Plans ................................................................... 7
2.2 Revision of T&C Procedure Documents ...................................................................... 8
2.3 Testing and Commissioning Stages ............................................................................ 9
3 ROLES AND RESPONSIBILITIES ........................................................................... 10
3.1 Manufacturer / Representative (Xylem water Solution-ltaly) .....................................11
3.2 Sub-Contractor .............................................................................................................11
4 RESOURCES............................................................................................................ 12
4.1 Labour ...........................................................................................................................12
4.2 Equipment Used ...........................................................................................................13
4.2.1 General Equipment used for this activity: ..................................................................13
5 QUALITY ASSURANCE/ QUALITY CONTROL....................................................... 13
6 HEALTH, SAFETY, ENVIRONMENT ....................................................................... 14
6.1 Lockout/Tagout Procedure ..........................................................................................14
6.2 Hazardous Waste Management ...................................................................................15
7 Risk Assessment..................................................................................................... 15
8 METHODOLOGY ...................................................................................................... 15
8.1 PSAT (Partial Stand Alone Test) ..................................................................................15
8.1.1 Prerequisite for PSAT ...................................................................................................15
8.2 SAT (Stand Alone Test) ................................................................................................17
8.2.1 Pre-Request for SAT .....................................................................................................17
8.2.2 Commissioning /Start-Up .............................................................................................17
8.3 MEP System Integration Test (SIT) ..............................................................................18
8.4 System Performance Test (SPT) ..................................................................................18
M009-SPH-TCH-PRO-00043 Page 3 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
~.:J~IL.:J.:JUL.;..Hi:i.c;~
SAU D I B INL A O IN G R OU P IIIBK
lQCompany
SPH-.JV
GREEN LINE- ELEVATED & AT-GRADE 1\edco International
LIST OF APPENDICES
Appendix 1 – Risk Assessment
Appendix 2 – Check List
M009-SPH-TCH-PRO-00043 Page 4 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
HARDCOPY DISTRIBUTION LIST
This document is not controlled when printed. The controlled version is held by the Document
Controller on the Project Server’s valid Documents Folder.
008
010
011
012
* The final distribution may be modified after consultation with Main Contractor.
** It is the responsibility of the Station Manager to provide this T &C Procedure to the respective
Project or Site Engineers and obtain sign off that they have received and understood the
document. Please refer to the communication protocol
M009-SPH-TCH-PRO-00043 Page 5 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
ABBREVIATIONS
M009-SPH-TCH-PRO-00043 Page 6 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
1 PURPOSE
1.1 General issues
This document is to present the T&C Procedure as required by subcontract documents for Green
Line Elevated & At Grade Project.
This document was composed exclusively for the Qatar Railway ‘Green Line Elevated & at Grade’
Project. All the requirements listed in the above referred tender document were taken into account.
The company has Quality Management System Certificate of ISO 9001: 2008, Certificate of ISO
14001: 2004 of Environmental Management System. Furthermore, it applies the BS OSHAS
18001: 2007 on Occupational Health and Safety Management System.
1.2 Purpose
The purpose of this T&C Procedure is to explain step by step method for Testing and
Commissioning of Pressurization Unit guidelines contained herein so as to ensure that the job
execution complies with project requirement and serves the intended function to satisfactory
level.
2 SCOPE
Scope of this PRO is the Testing and Commissioning of Pressurization Unit
This document includes the following either in the main body or in the Appendices:
The following documents are referred to either to support the implementation of the T&C Procedure
or are a pre-requisite to its implementation:
x SPE:
Document No. Document Name
M009-SPH-MEP-SPE-00001 Mechanical Project Specification
M009-SPH-TCH-PRO-00043 Page 7 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
x DWG’s For Pressurization Unit Location:
Drawing No. Document Name
Al-Riffa Station LOWER GROUND LEVEL 1 CHILLED WATER PUMP ROOM -
M009-SPH-MHV-DWG-GWST080-L1-11017
VAC)
x MAR:
Document No. Document Name
Material Approval Submittal for chilled Water Pressurization Unit and Expansion
M009-SPH-MEP-MAR-00219
Tank – XYLEM Water Solution (ITALY)
x MS:
Document No. Document Name
Method Statement for Installation of Pressurization Unit, Water Softener & Air
M009-SPH-MEP-MES-00048
Separator
x ITP:
Document No. Document Name
M009-REI-MEP-ITP-00084 Inspection and Test Plan for Testing & Commissioning of Pressurization Unit
x Plans:
Document No. Document Name
M009-SPH-TCH-PLN-00005 Project Testing & Commissioning Plan
M009-SPH-TCH-PRO-00043 Page 8 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
x The Project Director requires modifications of T&C Procedure
x There is a significant change in the works methodology.
x The revised T&C Procedure shall be submitted to DVE for SONO and PMC for review
approval.
STAGE STAGE
STAGE NAME RESPONSIBLTY REMARKS
NO ABBRE
Stage 1 FAT Factor Acceptance Test REDCO For stage (1 & 2) Covered IRN Refer to Testing &
Commissioning Plan (MEP Subcontractor) #
Stage 2 IT Installation Test REDCO M009-SPH-MEP-PLN-00003 (ANNEXUTE-A2)
Stage 3 P-SAT Partial Standalone Test REDCO
Part of this procedure
Stage 4 SAT Standalone Test REDCO
Stage 5 SIT System Integration Test L&T For Stage (5 & 6) by L&T (BACS ITP &PRO)
M009-SPH-MEP-ITP-40003
Stage 6 SPT System Performance Test L&T M009-SPH-MHV-PRO-00033
M009-SPH-TCH-PRO-00043 Page 9 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
C4.:::a~t L:.J
SAUDI
.:::au
\.Jot
BINlAOIN
ac q..o..:;u::J
G R O UP IIIBK Company
SPH-.JV
GREE N LINE- ELEVATED & AT-GRADE 1\edco International
Commissioning Authority
...
.; ......
_.,.
l5 !! ~ ~ c!l c!l ...
.;
~
- Approve (sign-off)
... -~
c
"'
-
u 0
~ c .; c!l 0
~ ~ ~ ~ ii 'f ~
Contributor c
8 ...~ c
8
c!l
u
u
Oil
1-
...
.E a ~
"'"'
Oil ::1: c c
.J:I
Informed :::1
1- c.. w 8
"' "'
Page 17
M009-SPH-TCH-PRO-00043 Page 10 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
3.1 Manufacturer / Representative (Xylem water Solution-ltaly)
The Supplier/Manufacturer (XYLEM Water Solution (ITALY) Supplier) Representative shall be
inspect all power termination/connections and AHU installation as per manufacturer requirements.
After inspection/confirmation power of equipment shall be switched on and he will witness the
testing.
3.2 Sub-Contractor
The Sub-Contractor is responsible for ensuring that the overall requirements are understood and
followed by all parties involved in testing commissioning. All personnel involved in the works will
be responsible for their own action/omission, be accountable for any unsafe actions/conditions
in which they created and to ensure that they follow the safe working procedure of the approved
Procedure.
Subcontractor's key personnel will have the roles and responsibilities as below:
a) T&C Manager The T&C Manager is responsible for Verifying the testing work carried out
in accordance with the requirements of the contract. And ensuring the quality standards set
for the Testing work are achieved and the work team adhere to the QA/ QC and HSE
requirements of the contract.
b) T&C Site Engineer T&C Site Engineer is responsible for Ensuring that the works are being
carried out in accordance with contract requirements and this T&C Procedure. He will
manage the testing activities to ensure that the team carries out the works in time with the
delivery schedule. Implementation of and adherence of the team to the QA/ QC and HSE
policies and procedure.
c) QA / QC Engineer - He is responsible and accountable for conducting surveillance and
inspection duties at various stages of the project delivery to ensure compliance to contract
requirements and to QA / QC requirements. He will ensure that the necessary corrective
action is undertaken against any recorded non-conformance. He will work in close
coordination with all the inter-related disciplines and stakeholders of the project. He is
responsible for preparation of all QA/QC related documents/procedures etc. Work in close
coordination with Supervision Engineer and Main Contractor’s QC Engineer to fulfil the QC
requirements and reports to QC Manager.
M009-SPH-TCH-PRO-00043 Page 11 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
f) Supervision Engineer - He is responsible and accountable for checking the compliance of
works to the design, carrying out comprehensive supervision of all construction works and
final approving that the work executed complies with the approved design and be
responsible for checking the construction works. He will be responsible and accountable to
take reasonable care of himself and the safety of others working nearby. He will make sure
that all the workforce is briefed about the task related hazards, control measures and
availability and use of the relevant PPEs.
h) Technicians/Helpers - They will be responsible and accountable for the safety of themselves
and the others who can be affected by their work activities and shall be responsible for
installing the equipment at the exact location marked by the surveyor and according to the
shop drawings, to perform safely physical installation, handling the material and required
equipment, positioning and installation of materials shall ensure quality installations. Duties
include using, supplying or holding materials or tools, and cleaning work area and
equipment. They will make sure that required work permit has been received from the
relevant authorities and the control measures mentioned in the permit are being adhered
to.
All the workforce is responsible and accountable to take reasonable care of their safety and
safety of the others working nearby them. They will be responsible and accountable to
adhere to all the HSSE rule and regulations told them in Induction trainings, TBTs and
STARRT briefings. They will also be responsible to use the PPE’s provided to them for their
safety and also not to alter with them.
4 RESOURCES
4.1 Labour
Following personnel of the specialized subcontractor will be working at site. The number and
organization may be changed to suit the work requirements
M009-SPH-TCH-PRO-00043 Page 12 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
4.2 Equipment Used
4.2.1 General Equipment used for this activity:
Note:
x All Instrument should valid calibration Certificate and certificate should be available on site
at the time of testing
x Equipment may be substituted subject to availability and actual requirements on the day.
x The type and quantities of equipment are subject to change to suit the site requirements and
to meet the construction program.
Items which are a part of, or intended to be used permanently on, any of the systems of the project
shall not be used as an element of the testing setups for the purposes of testing.
The concerned Site Engineer or General Foreman will be responsible to ensure compliance for
these operations and the site QA / QC Engineer will carry out quality control checks and report the
inspection results.
M009-SPH-TCH-PRO-00043 Page 13 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
6 HEALTH, SAFETY, ENVIRONMENT
The Health and Safety Plan will be strictly adhered to at all times.
x All workers will receive a site induction and be issued with PPE (hard hat, safety glasses,
safety vest, safety shoes) including hard hat with a SPH Inducted sticker before entering to
site to work.
x Regular Tool Box talks are held and attendance logged.
x The Emergency Response Plan is in place and will be strictly adhered to.
x In the event of any accident the HSE Incident Escalation Matrix will be followed at all times.
x Specific HSE Hazards are mitigated in the Risk Assessment.
x To prevent accident during the implementation of the above activities, all relevant safety
measures shall be strictly implemented by the site engineers and the HSE team.
x Tags used must be highly visible with prominent warning to warn employees of the
danger of reenergising the equipment
x Tags must be durable and be securely fastened to the lockout device
x Tag details must be completed in full
7. Test the energy device controls to ensure equipment is de-energized and locked out.
8. Place key of safety padlock in Group Lockout Box and secure Group Lockout Box with
their own personal padlock.
9. Each person working on the equipment should put their own personal padlock on the
Group Lockout Box prior to commencing any work.
10. Perform activity and do not bypass the lockout. The activity shall be done in conjunction
with and as set out in a ‘Permits to Work’ document.
11. On completion of activities, follow the agreed procedures to reactivate the equipment.
x Remove any blocks put in place and re-install any safety guards.
x Remove personal padlock from Group Lockout Box
x Once all personal padlocks have been removed from the Group Lockout Box, keys
to the safety padlocks are removed and used to remove all lockout devices and
tags.
M009-SPH-TCH-PRO-00043 Page 14 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
x Re-start the equipment and test to ensure all is ok.
x Cancel the ‘Permits to Work’ and sign off the work.
x Let the relevant employees know that the equipment is ready for use.
x Fire prevention systems and pollution control equipment will be provided for storage
facilities where necessary, to prevent fires or the releases of hazardous materials
to the environment;
x Containers intended for hazardous waste disposal will not be used for other
purposes unless they are specifically labelled for that purpose. Rusty, dented or
defective containers for waste accumulation or storage will not be used;
x Hazardous waste will be retained in a secure area with an impervious bunded base;
x Secondary containment is required for liquid hazardous waste or other waste that
might be released into the environment, such as dusts, powders, and shavings.
x The conceptual design for the hazardous waste storage facility is part of the CWMP.
x Hazardous waste will be disposed of in the area designated by municipality.
Incompatible hazardous wastes will not be transported together.
7 Risk Assessment
The Risk Assessment for this work is attached in Appendix 1.
8 METHODOLOGY
8.1 PSAT (Partial Stand Alone Test)
Pressurization unit commissioning will not commence until the installation mechanical and
electrical IRE signed off.
Verify and confirm that the Pressurization unit installation completion checklists are
available and duly signed by concerned parties.
x All Pipe work installation are completed, and all IRE are approved.
x Ensure there is valid permit to work is issue.
x Ensure that IRN are prepared by construction and Approved by all parties.
x Ensure all CHW system are Flushed out Properly and IRE are approved.
x Duct access doors are securely closed.
x All valves and other Controller should be open Position.
x MCC panels are installed and commissioned.
x Ensure sample of test pack has been prepared.
x Ensure that lock out tag out in place.
x Ensure HSE in place.
M009-SPH-TCH-PRO-00043 Page 15 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
x Ensure that as build / red line drawing have been provided.
x Ensure approved Procedure is on the site.
1. Ensure that the clearance from manufacturer/supplier before power supply connection
to the equipment.
2. Ensure that the Pressurization unit
3. Installation is complete and mechanical completion is approved.
4. Ensure that no damage has occurred between mechanical completion and During
Pre-commissioning.
5. Check Pressurization unit installation as per the approved shop drawing and
manufacture recommendation.
6. Check for proper electrical power, control panel and earthing connection as per
approved drawing and all field wiring to be pre- tested for continue and insulation
resistance.
7. Verify the correct voltage phase and cycles.
8. Initial check and verification of the following items prior to any start-up are required.
8.1.1.1 MOTOR
1. Check for proper lubrication as per supplier recommendation
2. Check belt alignment
3. Isolator is tested, properly terminated and installed
4. Earthing and protection device properly connected and installed as per project specs
5. Motor enclosure is properly selected as per project specs.
6. Terminal box properly installed and correct location
7. Terminals shall be spaced or properly protected to avoid faults within the Box
8. Cable terminations shall comply with the latest edition of I.E.E regulation
9. Factory Acceptance Test of the motor shall be available upon request
8.1.1.2 Electrical
1. All terminal connection properly torques as per specs.
2. Disconnect switch functional and tested.
3. Starters functional, tested and complying with project specification.
4. Fuses complying with project specs.
5. Overload relays correct size and functional.
6. Auxiliary accessories, i.e., indicating lamp, push button, and selector switch Functional
and no sign of damage.
7. Incoming and outgoing power supply cables are correct and tested.
8. Each panel board is individually bonded to main earth bar located in the electrical rooms
and each panel section shall be cross bonded to adjacent panel section earthing
terminal.
M009-SPH-TCH-PRO-00043 Page 16 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
3. Obtain the results of chemical treatment and analysis to ensure that the chilled water
lines are protected against corrosion and that PH and, Fe and turbidity levels are
consistent with the current CIBSE guidelines.
4. Ensure that all heating / chilled water pipes have been fully insulated and that there are
no breaks which, could cause damage to, or destroy the vapor seal.
5. Ensure that all manual control valves and isolation valves are in the “Fully Open”
position, and that the by-pass valve is closed*
6. Follow the pre-start-up check as listed in attached checklist. Once all parameters have
been met, the system can be safely energized and run.
After a successful completion of this stage, Pre-Commissioning Certificate (PCC)
will be released.
1. Ensure that all the PSAT checks are carried out successfully
2. Ensure that pipe alignment is done
3. Ensure the discharge valve is closed
4. Completely open the isolating valve on the suction side of the pump and leave the
discharge isolating/throttle valve partly open.
5. Switch on the electricity supply.
6. Start the pump.
7. Check the direction of rotation of the pump. In case of incorrect rotation, interchange
two phases of the electricity supply.
8. Check for any under vibration/noise (it is just physical hearing of under
vibration/noise during operation).
9. Check current, voltage and rpm of the motor and record the value.
10. Vent the pump during starting by loosening the air vent screw until a steady flow of
liquid runs out of the vent hole.
11. When the piping system has been filled with liquid, slowly open the discharge
isolating/throttle valve until it is completely open.
12. Record pump operating current, pressure and check for smooth pump operation.
Operate pump with-in required duty point.
13. Set the motor overload protection.
14. Check and ensure that the pumps shut off at low water level.
15. The pump may be started for a very short period without being submerged for
checking of the direction of rotation.
M009-SPH-TCH-PRO-00043 Page 17 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
After a successful completion of this stage, Partial Acceptance Certificates (PAC)
will be released.
M009-SPH-TCH-PRO-00043 Page 18 of 18
Testing and Commissioning Procedure for Pressurization Unit (REDCO)
APPENDIX 1
RISK ASSESSMENT
~
~
4./~""'~u~ac.- ~ WBK SAUDI IIJIHADIN G I OUP ...
RISK ASSESSMENT Appendix 1
SPH ·JV
GREEN LINE- ELEV.t.TEO & AT-GRADE
1 2 3 4 5
L IKELYHOOD VERY VERY ALMOST
UNLIKELY LIKELY
UNLIKELY LIKELY CERTAIN
Site
Impact. struck by moving
2 1 ,...,..,"'~..,.., & egress to Imaterials stored at access, poor 1Cuts. bruises, sprains. severe I
4 I 4 16
Ensure handrails are used and proper footing on steps.
6
HSE
Representallve I
· · · cable running on Do not block access by storing materials.
Proper routing of cables. Foreman I
Provide Information signs.
Ensure good housekeeping always
Page I of 4
RA Execution SPH • JV
~ IIm'I'Tol llillm ~
Probabllo Consoq Risk
m!l What could hurt me I others or Impact ~ liW·h"b11rom
mw:m n h ir n
What harm could occur? ...
ty/likeli uence Level What must be in place to revent harm? (includes ecific responsibilities where a plicablel
I I I'
Do not block access by storing materials.
3 3 9 I
nor injury,cuts, bruises
I Signs must be displayed to indicate the routes to be taken by persons, changes in routes must be clearly 4
communicated.
• Working area should be illuminated
• Proper routing of cables.
• Ensure good housekeeping always
Po9" 2 of 4
RA Execution SPH - JV
~ rmm:J IIW:ml ~
a ill
~
i.!liiEil11ii:t :na:m ..
What could hun m~ I others or Impact
'tq:ma.su.,a;:.tm:J.I«dE
ty/Likell Consoq Risk
h uence Level What must be In place to prevent harm? (Includes eCific res onsibillties where a hcable
r:mr.lll!ll WJ:l.I.!.WttJH~
Page 3 of 4
RA EJcecutlon SPH - JV
Page 4 of 4