:DOPS-HVAC-MS-003
REV. No. 00
METHOD OF STATEMENT Date : 01–Feb–2021
Page 1 of 12
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.
TABLE OF CONTENTS
1.0 PURPOSE
To ensure that Installation of New HVAC Equipment’s is performed safely, efficiently and in
accordance with UCTC/ ENPPI/ Saudi Aramco standards/ checklists, Manufacturer
requirements and job specifications.
This method statement is applicable for the Installation Air Handling Units, Air Cooled
Condenser Units, Fresh Air Handling Units, Package Air Conditioning Units, Exhaust Fan,
Starter Panel and DDC for the project as mentioned in the Specifications & Approved Shop
Drawings.
2.0 SCOPE
The scope of this method statement is to ensure the correct Installation of the New HVAC
Equipment’s. This procedure is to be read in conjunction with the relevant ITP, outlining the
responsibility and the quality verification to be performed by various parties.
This method Statement shall cover the Installation AHU / ACCU, PACU, EF, EDH, DDC & SP
in line with project requirements as in the Approved Shop Drawings, specifications &
manufacturer’s instructions.
3.0 REFERENCE
SAIC-K-4027 - Saudi Aramco Inspection Checklist (Air Moving Apparatus DX Unit Installation)
SAIC-K-4028 - Saudi Aramco Inspection Checklist (Air Filteration Device Receiving)
SAIC-K-4029 - Saudi Aramco Inspection Checklist (Air Filtration Device Installation)
SAIC-K-4039 - Saudi Aramco Inspection Checklist (ACCU Installation)
NFPA 70 - National Fire Protection Association
SAF-01 - General Requirements for Safety & Fire Protection
SAF-02 - Environmental, Health and Safety Management
SAF-12 - Electrical Safety
SAF-13 - Work Permit, Isolation of Energy and Hazardous Work
SAF-21 - PPE
SAF-24 - Hazardous Materials in Portable Containers
SAF-25 - Incident Reporting and Investigation
IFC Drawing - HVAC Equipment’s Schedule, Location & Foundation Drawings
Latest Approved shop drawings intended for HVAC (Equipments Schedule, Foundation & Location).
4.0 DEFINITIONS
SA : Saudi Aramco
ENPPI : Engineering for the Petroleum and Process Industries
UCTC : United Caravan Trading & Contracting
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control
WIR : Inspection and Test Request
MIR : Material Verification Record
IFC : Issue for Construction
AHU : Air Handling Unit
ACCU : Air Cooled Condenser
PACU : Package Air Handling Unit
EF : Exhaust Fan
EDH : Electrical Duct Heater
DDC : Digital Direct Control Panel
SP : Starter Panel
DS : Disconnect Switch
Ref. No. :DOPS-HVAC-MS-003
REV. No. 00
METHOD OF STATEMENT Date : 01–Feb–2021
Page 6 of 12
5.0 RESPONSIBILITIES:
5.1 Project Manager
The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
6.0 Equipment’s
Following tools shall be arranged before starting the job.
a) Boom Truck
b) Froklift
c) Tool Box.
d) Measuring Tape.
e) Hack Saw Blade with Frame
f) Spirit Level
g) Angle
h) Electric Drill Machine
i) Step Ladders
j) Electric welding machine. (if required)
k) Torque Wrench
l) Grinding Machine
m) Pressure Gauge
n) Hammer
o) Water Level Marker
p) Mobile Scaffolds
q) Staging Platforms
Ref. No. :DOPS-HVAC-MS-003
REV. No. 00
METHOD OF STATEMENT Date : 01–Feb–2021
Page 8 of 12
7.0 PROCEURE
AHU / ACCU, PACU, EF, EDH, DDC & SP units are normally shipped & despatch for goods
condition and carefully loaded in containers with crating / boxing. Hence, in case of transit
damage, supplier must be informed immediately as per Saudi Aramco receiving check list
SAIC-K-4001, SAIC-K-4002, SAIC-K-4004 & SAIC-K-4028, etc.
Special care must be taken to ensure that units are offloaded from containers. Rough handling
can result in damage to aluminium framework and double skin panels. It is possible to lift the
sections by slings or by forklift as per SAF-24.
All the received units shall be checked & inspected to ensure that it is complying with the
approved material submittals prior to site storage.
To ensure that deterioration of the AHU / ACCU, PACU, EF, EDH, DDC & SP does not occur
during storage, it is recommended to store the equipment in covered conditions that are protected
from weather elements and accidental damage as per the SAF-24.
All following HVAC Equipment’s AHU / ACCU, PACU, EF, EDH, DDC & SP shall be
protected with plastic/ tarpaulin or shall not be removed from the shipping package unless
otherwise instructed to do so.
All packages for the equipment reaching the site shall be identified as per package list.
7.4.1 Safety
All site safety rules & regulations shall be complied with SAF-01.
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved
in the installation and shall be recorded.
All operatives will be equipped with minimum personnel protective equipment; hard hat,
coveralls, safety boots, safety glasses as per SAF-21.
The persons using cleaning fluid and solvent cement have to wear hand gloves.
Ensure only qualified personnel shall install, test & commissioned the equipment.
During Testing & Commissioning, (which will be done on later stage) display warning sign
Ref. No. :DOPS-HVAC-MS-003
REV. No. 00
METHOD OF STATEMENT Date : 01–Feb–2021
Page 9 of 12
Delivered AHUs & ACCUs, FAHUs & ACCUs, PACUs and CCU shall have been
inspected & approved via MVR by the client prior to installation at site.
All Installations & Testing of Duct works have been completed & approved by the
client also achieve the Saudi Aramco HVAC Standards such as SAES-K-001, SAES-
K-100, SAES-K-101 & SATIP-K-001, etc.
Relevant documents or certificates shall be presented at the time of inspection if
required by the client.
Permission to start or Civil Clearances prior to installation has been given by the main
contractor.
All relevant Shop drawings for the installation of the equipment shall be available &
approved by the client. No installation shall be done without Approved Shop Drawings
and follow the Saudi Aramco check list for installation such as SAIC-K-4005, SAIC-
K-4029 & SAIC-K-4039, etc.
Installation activities shall only commence when all associated works by the Civil such
as clearing of work place, water proofing, etc. have been verified & completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site as per SAF-13.
Inspect the relevant area for any possible clashes with other services.
Check for other services, making sure that there is no interference between each service
& adequate access to work and for future maintenance can be maintained.
7.4.2.3 Assembly
Between the sides of the sections that shall be connected, it must be inserted a
continuous foam gasket for airtight seal.
Push the sections towards one another, making sure that they are lined up with one
another.
Ref. No. :DOPS-HVAC-MS-003
REV. No. 00
METHOD OF STATEMENT Date : 01–Feb–2021
Page 10 of 12
System lay-out should take into consideration of possible coil withdrawal. All
connecting pipework must be properly insulated.
Cooling Coils system design, pipe connections and valve arrangement must be
checked. Flow & return connections are clearly identified on the unit panels and pipe
work must be connected accordingly, preferably through flexible couplings to avoid
transmission of any vibration from the piping to coil. Excessive tightening torque
might damage the coils. Pipe work must be supported independently to the coil or to
the unit.
Condensate Drains: All cooling coils must be individually trapped and connected to
drain with adequate pitch for easy flow. Depending on the ambient temperature and
plant location, it is recommended to insulate the condensate drain pipework.
After inspecting the work area, ensure that it is totally ready for installation. Then
the required equipment shall be moved to the place of installation.
Check the EF’s regarding dimensions and orientation as per approved Shop
Drawing.
Electrical power Cable (from Unit to Starter Panel), control wiring and grounding
shall be carried out as detailed in approved shop drawing.