Professional Documents
Culture Documents
:DOPS-HVAC-MS-002
REV. No. 00
METHOD OF STATEMENT Date : 31–Jan–2021
Page 1 of 12
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.
TABLE OF CONTENTS
1.0 PURPOSE.............................................................................................................. 4
2.0 SCOPE .................................................................................................................. 4
3.0 REFERENCES ...................................................................................................... 4
4.0 DEFINITIONS....................................................................................................... 5
5.0 RESPONSIBILITIES ............................................................................................. 6
5.1 PROJECT MANAGER ....................................................................................................... …6
5.2 CONSTRUCTION MANAGER ......................................................................................... …6
5.3 SITE ENGINEER ................................................................................................................... 6
5.4 QA / QC ENGINEER ............................................................................................................. 6
5.5 SITE FOREMAN .................................................................................................................... 7
5.6 SAFETY OFFICER ................................................................................................................ 7
5.7 STORE KEEPER .................................................................................................................... 7
6.0 EQUIPMENTS ...................................................................................................... 7
7.0 PROCEDURES...................................................................................................... 8
7.1 GENERAL REQUIEMENTS ................................................................................................. 8
7.2 MATERIAL TRANSPORT / DELIVERY............................................................................. 8
7.3 STORAGE ON SITE STORE ................................................................................................ 9
7.4 SEQUENCE OF INSTALLATION FOR THE HVAC DUCT INSTALL- BASE ................ 9
7.4.1 SAFETY ......................................................................................................................... 9
7.4.2 HVAC DAMPERS ...................................................................................................... 9
7.4.2.1 PRE-INSTALLATION PROCEDURE FOR HVAC DAMPER ............................... 9
7.4.2.2 INSTALLATION PROCEDURE FOR VD & MVD ............................................. 10
7.4.2.3 INSTALLATION PROCEDURE FOR FD, CFSD & MFSD ................................. 11
7.4.3 HVAC AIR TERMINALS ......................................................................................... 11
7.4.3.1 PRE- INSTALLATION PROCEDURE FOR HVAC AIR TERMINALS ...................11
7.4.3.2 INSTALLATION PROCEDURE FOR GRILLES, DIFFUSERS & STL ....................12
Ref. No. :DOPS-HVAC-MS-002
REV. No. 00
METHOD OF STATEMENT Date : 31–Jan–2021
Page 4 of 12
1.0 PURPOSE
This method statement is applicable for Installation of all the HVAC Duct Install- Base like Air
Terminals (Grilles, Diffusers & Registers), Sand Trap Louvers, Volume Control Damper,
Motorized Volume Control Damper, Fire Damper, Smoke Damper, Combination of Fire- Smoke
Damper & Motorized Fire-Smoke Damper for the project as mentioned in the Specifications &
Approved Shop Drawings.
The purpose of generating this method statement is to define the procedure & work sequence for
the correct practices to ensure that Installation of HVAC Duct Install-Base is performed safely,
efficiently and in accordance with UCTC, ENPPI & Saudi Aramco standards/ checklists,
Manufacturer requirements and job specifications for the Installation of HVAC Air Terminals,
Dampers through the guidelines contained herein so as to ensure that the job execution complies
with the requirements of the contract specification & approved shop drawings to which will serve
for the intended function to the satisfactory level for all applicable areas of the project.
2.0 SCOPE
The scope of this method statement is to ensure the correct Installation of the HVAC Duct Install-
Base. This procedure is to be read in conjunction with the relevant ITP, outlining the responsibility
and the quality verification to be performed by various parties.
This method statement covers all processes related to Installation of HVAC Dampers like Volume
Control Dampers, Motorized Volume Control Dampers, Fire Dampers, Smoke Damper,
Combination of Fire-Smoke Damper & Motorized Fire & Smoke Dampers and also shall cover
the Air Terminals Installation like Grilles, Diffusers, Registers, Louvers & Sand Trap Louvers in
line with project requirements as indicated in the Approved Shop Drawings, specifications &
manufacturer’s instructions.
3.0 REFERENCE
SAES-K-001 - Saudi Aramco Engineering Standard (Design & Installation of Heating Ventilating
and Air Conditioning System)
SAES-K-100 - Saudi Aramco Engineering Standard (Saudi Aramco Mechanical {HVAC} Code)
Ref. No. :DOPS-HVAC-MS-002
REV. No. 00
METHOD OF STATEMENT Date : 31–Jan–2021
Page 5 of 12
SAES-K-101 - Saudi Aramco Engineering Standard (Regulated Vendors List for Heating,
Ventilating and Air Conditioning {HVAC} Equipment)
SAIC-K-4009 - Saudi Aramco Inspection Checklist (Air Terminals, VD, EDH Receiving)
4.0 DEFINITIONS
SA : Saudi Aramco
ENPPI : Engineering for the Petroleum and Process Industries
UCTC : United Caravan Trading & Contracting
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control
IFC : Issue for Construction
VD : Volume Control Damper
FD : Fire Damper
SD : Smoke Damper
CFSD : Combination of Fire & Smoke Damper
MVD : Motorized Volume Control Damper
MFSD : Motorized Fire & Smoke Damper
AT : Air Terminals (Grille, Diffusers & Registers)
STL : Sand Trap Louvers
Ref. No. :DOPS-HVAC-MS-002
REV. No. 00
METHOD OF STATEMENT Date : 31–Jan–2021
Page 6 of 12
5.0 RESPONSIBILITIES:
5.1 Project Manager
The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
6.0 Equipment’s
Following tools shall be arranged before starting the job
a. Tool Box.
b. Measuring Tape.
c. Marker
d. Half round file
e. Wooden half round file
f. Hack Saw Blade with Frame
g. Wood-saw
h. Spirit Level
i. Angle
Ref. No. :DOPS-HVAC-MS-002
REV. No. 00
METHOD OF STATEMENT Date : 31–Jan–2021
Page 8 of 12
j. Electric Drill Machine with Concrete Bit Set & Metal Bit Set
k. Step Ladders
l. Electric welding machine. (if required)
m. Torque Wrench
n. Anchor punch
o. Chain Block
p. Marking line-dori
q. Screw driver (flat & Star)
r. Spanner (Ring & Open End - 4mm to 32 mm & Adjustable – Small & Big)
s. Rivet Gun
t. Grinding Machine
u. Pressure Gauge
v. Hammer
w. Mallet (Wood & Rubber)
x. Water Level Marker
y. Mobile Scaffolds
z. Staging Platforms
7.0 PROCEURE
7.1 General Requirements
All the materials received at site shall be as per the approved technical material submittal and to be
inspected upon receipt & approved by the QA/QC engineer prior in proceeding with the installation.
Any discrepancies, damages etc., should be reported to the supplier for rectification or replacement
& to be removed from site immediately.
All construction/inspection/testing works shall be carried out in accordance with the specifications &
to be done by qualified Mechanical Engineers and shall be checked and approved by HVAC
Subcontractor Construction Manager along with QA/QC Engineer.
Contractor has to clarify the procedure for material delivery to the site through consultant Engineer
at site.
7.4.1 Safety
All site safety rules & regulations shall be complied with.
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in
the installation and shall be recorded.
All operatives will be equipped with minimum personnel protective equipment; hard hat,
coveralls, safety boots, safety glasses.
The persons using cleaning fluid and solvent cement have to wear hand gloves.
Ensure only qualified personnel shall install, test & commissioned the equipment.
During Testing & Commissioning, (which will be done on later stage) display warning sign
boards necessarily provided and barricade the area whenever necessary.
Only competent, experienced & trained personnel shall perform all the required activities stated
in this method statement.
Ensure that all operatives fully understand the method of these activities.
Lift or handle HVAC Dampers using sleeve or frame. Do not lift the HVAC Dampers
using blades, linkage, actuators or jack-shafting. Do not drag, step on, apply excessive
bending, twisting or racking.
Do not install screws in damper frame that will interfere with unexposed blade linkage
and prevent damper blades from opening and/ or closing.
HVAC Dampers must be installed into the duct opening square and free of twist or other
misalignment.
HVAC Dampers must not be squeezed or stretched into duct or opening. Out of square,
racked, twisted or misaligned installations can cause excessive leakage and/ or torque
requirements to exceed damper/ actuator design.
HVAC Dampers actuators must be kept clean, dry & protected from dirt, dust and other
foreign materials prior to and after installation.
HVAC Dampers must be sufficiently covered as to prevent overspray if wall texturing
or spray painting will be performed within 1.5m of the damper. Excessive dirt or foreign
material deposits on damper can cause excessive leakage and/ or torque requirements to
exceed damper/ actuator design.
Suitable access for actuator’s maintenance must be provided for damper inspections &
servicing. Where it is not possible to achieve sufficient size access, it will be necessary
to install a removable section of duct.
All electrical or pneumatic connections to the HVAC Dampers actuators shall be made
in accordance to the manufacturer’s recommendations. Only qualified personnel shall
perform this activity.
Verify power requirements before wiring the actuators.
Damper blades, axles & linkage must operate without binding. Before system
operation, cycle dampers after installation to assure proper operation. All sections
should open & close simultaneously.
All relevant Shop drawings for the installation of the equipment shall be available
& approved by the consultant. No installation shall be done without Approved Shop
Drawings.
Installation activities shall only commence when all associated works by the Civil
has been completed.
Safe access shall be provided by the Main Contractor thru Work Permit in
coordination with the Safety in charge at site.
Check the exact location of installation for the Grilles, Diffusers, Sand Trap Louvers
as per the approved shop drawings.
Check for other services, making sure that there is no interference between each
service & adequate access to work and for future maintenance can be maintained.
7.4.3.2 Installation Procedure for Grilles, Diffusers & Sand Trap Louvers
Ensure plenum or terminal boxes openings are compatible for Grilles, Diffusers,
Louvers to be installed.
Ensure that plenums are correctly acoustically lined.
Install sub-frame in the duct opening as manufacturer’s recommendation and ensure
that Grilles, Diffusers, Louvers shall be installed correctly as per the direction of
flow.
Prepare Grilles, Diffusers, Sand Trap Louvers by installing sealing material to the
internal side of the mating flange, carefully locate Grilles, Diffusers, Sand Trap
Louvers into sub-frame and locate locking screws and tighten until correct level and
the alignment is attached.
Make sure that screws should be fixed into a metal / wooden frame which sits in
counter sunken holes through border.
If the aperture is in masonry, the hole locations should be marked, then drilled and
plugged to give more positive fixing.
Concealed rear bracket fixing is for use when a hidden fixing is required but the
installation prohibits the use of clip fixing.
For fixing of Grilles, Diffusers, Sand Trap Louvers without dampers, the Grilles, 4
way Diffusers & Sand Trap Louvers are positioned into opening with metal/ wooden
frame screws are fixed through the brackets fixed into the stack of Grilles, Diffusers,
& Sand Trap Louvers to the frame holes.
For Grilles, Diffusers, Sand Trap Louvers with dampers, the dampers can be fixed
with Grilles, Diffusers & Sand Trap Louvers border by clip or rivets and damper is
fixed by screwing to the duct opening. Otherwise the damper alone can be directly
screwed to the duct chute.
After final alignment, carefully tighten the Grilles, Diffusers, & Sand Trap Louvers
until airtightness is achieved.
Ensure that all Grilles, Diffusers & Sand Trap Louvers are left in closed position and
protection shall be provided until handing over.
Ensure that each installation of Grilles, Diffusers, & Sand Trap Louvers is
undamaged, clean and screwed tight prior to inspection.
After all installation has been done, raise immediate inspection for approval