Professional Documents
Culture Documents
0 OBJECTIVE
a. Contract Document
b. ACMV Shop Drawing
c. Material Approval
d. SMACNA – HVAC DUCT CONSTRUCTION
e. MS 1780:2017 Smoke Control System Using Natural (Displacement) or
Powered (Extraction) Ventilation.
f. MS 1472:2017 Smoke Control in Protected Escape Routes Using Pressurization
Fan.
4.0 RESOURCES
4.1 MATERIALS
ITEM DESCRIPTION
1 Safety Shoes
2 Safety Helmet
3 Safety Belts/Harness
Upon delivery materials at site, the ducting, insulations and its accessories shall be
unloaded carefully and stored in a designated area by the main contractor. Materials
should be stacked neatly and well protected to avoid damage from weather, dirt and
misconduct by others at site.
The receiving inspection is carried out to ensure that the incoming materials will not be
used until it has be inspect and verified for conformance of using submitted material
approvals. Inspection and verification shall be done on the Material Delivery Order
(DO) and be evidenced by the receiving inspection form which shall be performed by
the resident engineer representing the client on site. The inspection shall be conducted
by the Sub contractor’s Site Supervisor, Main Contractor’s Engineer, Inspector of Work
(IOW), Resident Engineer and employer’s representative. Rejection or acceptance of
material delivery shall be by the discretion of the Resident Engineer on site.
6.0 REQUIREMENT
6.1 DESCRIPTION
Work of this section shall conform to the requirements of the contract documents.
7. Aluminum Ductwork
6.3 SUBMITTALS
6.5 MATERIAL
7.1 GENERAL
Upon delivery and unloading, a visual inspection on the ductworks and its accessories
will carried out. Work may then begin. Proper scaffolding and safety precaution is to be
adopted and to be witnessed and approved by consultant’s RE/COW & PMJ’s Engineer.
Prior to the installations of the ductworks, check and study the approved shop drawings.
The anchor bolts are then installed based on routings and each hanging rods are
installed. The hangers distance shall be at a distance of 2100mm apart. After each
hanging rods are installed, an angle iron is cut to length based on the distance of each
rod and installed with washer and nut.
7.3.1 General
All sheet metal ductwork shall be constructed and installed in accordance with the latest
SMACNA recommendation, and the sheet metal duct construction table as shown in
Appendix E&F. The fabrication in factory shall be based on the measurement from
approved shop drawing. Refer to Appendix E, F & G for the ductwork installation
details.
Shop drawing shall be submitted and coordinated with other services. The shop drawing
also shall indicate the duct installation location, duct sizes, access panel, and type of
insulation and damper locations. Due to site accuracy and condition, the last joining
section or final locations indicating offsets or transition will be measured at site.
All fabricated ducts per batch shall be marked for identification with location and gauge
thickness, and check by the sub-contractor supervisor before installation. The important
points to be checked for are any damages to the fabricated ducts, correct construction
and reinforcement, approved type of materials used, size and gauge, seam joints and
sealant.
After the ductworks are fabricated in the factory, the sheet metals are delivered to site
where the ductworks will be installed. The ductworks are then connected using slip joint
or TDC joints depending on the ductwork construction table of Appendix E & F.
For slip joints, the ductworks are connected which “clip joints” and after completion,
duct sealant is applied around these joints. As for TDC joints, the joints are connected
together with a gasket in between. Once the connection is correct, TDC connectors will
be installed at all sides of the ductworks. After this process is done, duct sealant is
applied around the joint.
All brackets shall be galvanized. Generally, the spacing between each bracket shall be
2100mm; more quantity will be used at the corner, fittings and at main branch tee off
point. The duct riser support shall refer to the Appendix G.
7.5 Smoke Spill Ventilation, Staircase and Lift Lobby Pressurization Ductworks
7.5.1 General
The duct installation is similar to air ventilation ductwork. Please refer to section 7.3 for
reference. All smoke spill ventilation ductworks shall follow the duct gauges below:
All kitchen exhaust duct shall be 1.0mm Stainless Steel. The ductworks shall be cut to
length in the factory and delivered to site for installation. All joints of the ductworks
shall be welded connections and grease arresting gutter with 25mm scupper and drain
plug.
Access door at not greater than 3000mm from the bend depending on site condition and
location to install the access door at proper location.
7.6.2 Installation Sequence
1. Check the layout of ductwork routing on site using the approved shop drawings
and based on actual site condition after the coordination with other sub-
contractors.
2. Measure, fabricate and install duct hanger and support. Length of hanger rod is
measured to meet the correct level and shall be slightly longer, sufficient to fix
the nut below.
3. Weld duct in sections and install on the duct support. Install the main ductwork
line first, follow by the branch of the duct network.
4. Check duct levels with reference to the marked reference level line as per
provided by the builders.
5. Weld and install bends, tees, dampers, offsets, and take-off and similar fittings
necessary to complete the ductwork system for the balancing and full operation
of the air distribution system.
6. Install dampers and access doors as indicated in the approved shop drawings.
1. All the ductworks penetrating fire rated walls and concrete slabs must be
installed with a 2 hour fire rated fire damper.
2. Ductworks penetrating fire rated walls must be installed with a curtain type fire
damper.
3. Ductworks penetrating concrete slabs must be installed with blade type fire
damper.
4. The fire dampers are first installed onto fire rated walls/ slab and rock wool is
installed on the remaining gap between the fire damper and the fire rated brick
wall/slab.
5. After the installations of the fire damper, the ductworks are then connected to
the fire dampers via slip/TDC joints with Appendix G as a reference.
6. Access panel will be provided on the ductworks for every fire damper locations
for future inspection and maintenance.
The in-process inspection shall be carried out to ensure conformance of the installation
works. “Work Inspection Request” (WIR) form shall be forwarded to the Clerk of
Work/ Resident Engineer to request for an inspection to be carried out on that particular
work. The inspection shall meet the requirement in the approved methodology.
Delivery to site