Contents

1. INTRODUCTION...............................................................................................2
2. SCOPE OF WORK............................................................................................2
3. PREPARATION.................................................................................................2
3.1 INSTALLATION CHECK
3.2 SAMPLING POINT
3.3 FILTER
4. CHILLED WATER PIPE FLUSHING WORK PROCEDURE.............................3
4.1 PROCESS 1
4.2 PROCESS 2
4.3 PROCESS 3
5. CHEMICAL.......................................................................................................4
5.1 CHEMICAL A
5.2 CHEMICAL B
6. PARAMETER....................................................................................................4
6.1 PARAMETER 1
6.2 PARAMETER 2
6.3 PARAMETER 3
7. WATER FLUSHING FLOW CHART.................................................................5-6
8. SAFETY..............................................................................................................7
METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 2 of 7

1.0 INTRODUCTION
The purpose of this statement is a guideline for Flushing Work for the ““CADANGAN
MEMBINA SEBUAH PUSAT PERUBATAN DAN FAKULTI PERUBATAN UCSI
UNIVERSITI DI ATAS SEBAHAGIAN LOT 8317, BANDAR SPRINGHILL, MUKIM
JIMAH, DAERAH PORT DICKSON, NEGERI SEMBILAN DARUL KHUSUS.”
SUPPLY, INSTALLATION, TESTING AND COMMISSIOING OF AIR CONDITIONING
AND MECHANICAL VENTILATION SERVICES.

2.0 SCOPE OF WORK


Generally, the following work on the chilled water pipe can be divided into three parts:
a) Flushing of underground chilled water pipes.
b) Flushing of chilled water pipe in chiller plant room.
c) Flushing of chilled water pipe of main hospital block.
The flushing work shall start from underground chilled water pipe and follow by chilled water
pipe in chiller plant room and finally chilled water pipe in main hospital block.

The flushing work consists of the following processes:


a) Dynamic flushing
b) Chemical flushing
c) Initial Water Treatment

3.0 PREPARATION
Before the flushing work is carried out, the following points shall be considered:
3.1 Installation Check
Prior to commence the flushing work, a thorough inspection shall be carried out on
the pipe works, fittings and plants to ensure the entire system is water tight. All the
isolating valves to other pipe sections besides the flushing section shall be close to
avoid accidental cross contamination between systems.
3.2 Sampling Points
Sampling points shall be taken from the chilled water pipe line.
3.3 Filter
The filters shall be placed in the flushing tank to trap the foreign material in the
pipeline during flushing.
METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 3 of 7

4.0 CHILLED WATER PIPE FLUSHING WORK PROCEDURE


4.1 Process 1
1) Before starting the water flushing, all the ends of the pipe line are ensured to be
connected to each other. Water shall be filled into the system. The isolation
valves of chiller plant room pipeline and main hospital block pipeline shall be
close and ensure that the water of underground pipeline does not mix with other
pipeline.
2) Check and confirm that the water circulates in the entire pipeline.
3) The water filter shall be replaced with new filter if necessary.
4) The flushing shall be continue until the water is deemed fit to be analysed by
Resident Engineer.
5) If the water analysis result is not contouring to the conditions in parameter A,
continue circulation and draining.
6) After Parameter A is achieved for underground pipeline, isolate the underground
pipeline and flush the pipeline in chiller plant room follow by pipeline in main
hospital block. Repeat step 1 to step 5.
4.2 Process 2
1) When parameter A is achieved for underground pipe, chiller plant room and main
hospital block pipeline, dose in chemical A and allow circulation to be on for
minimum 12 hours to achieve Parameter B.
2) If the water analysis result is not contouring to the conditions in Parameter B,
continue circulation.
3) Proceed to Process 3 when Parameter B is achieved.
4.3 Process 3
1) Once the chemical flushing is completed, the water treatment process shall be
commenced. Chemical B shall be dosed into the system and circulate for
minimum of 12 hours.
2) During the period, the water samples shall be taken and monitored. The
chemical reserves and all parameters are ensured to be within control limits
stipulated in Parameter C.
3) When Parameter C is achieved, the pipeline shall be reconnected as close loop.
METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 4 of 7

5.0 Chemical
5.1 Chemical A
JCT A-491, is a surfactant agent and functions as the oil and grease remover
agent during initial chemical flushing.

5.2 Chemical B
JCT L-111, is nitrate and azole treatment technology which functions as the
corrosion inhibitor during water treatment.

6.0 Parameters
6.1 Parameter A

pH Value pH 7 – pH 11
Conductivity (uS/cm) Less than 1000
Total Iron (ppm) Less than 10
Turbidity (NTU) Less than 120

6.2 Parameter B

pH Value pH 7 – pH 11
Conductivity (uS/cm) Less than 1000
Total Iron (ppm) Less than 5
Turbidity (NTU) Less than 60

6.3 Parameter C

pH Value pH 7 – pH 12
Conductivity (uS/cm) Less than 4000
Total Iron (ppm) Less than 5
Turbidity (NTU) Less than 40
Nitrate Ion (ppm) 350-600
METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 5 of 7

7.0 WATER FLUSHING FLOW CHART (CHILLED WATER PIPELINE)

Fill up pipeline with water

Run pump to circulate the


water for underground pipe

Check water quality

No
Achieve
Parameter A

Yes

Start circulate water for


chiller plant room pipeline

Check water quality

Achieve No
Parameter A

Yes

Open all valves to connect pipeline of


underground pipe, chiller plant room
and main hospital block

Circulate water in the pipeline

Check water quality


METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 6 of 7

Achieve No
Parameter A

Yes

Dose in Chemical A

Run pump and circulate for


minimum 12 hours

On line drain water

Check water quality

No
Achieve
Parameter B

Yes

Dose in Chemical B

Circulate for 12 hours

Check water quality

Water Treatment Completed

Sign off Inspection Forms and record.


METHOD STATEMENT FOR FLUSHING WORK

Doc. No. : UAT-UCSI-WMS-012 Rev. No. : 00

Date: 25/2/2016
Page 7 of 7

8.0 SAFETY

8.1 Personal Protective Equipment


i. Prior to work commencing all plant and equipment to be used will be inspected
and confirmed for used by contractor’s safety representative.
ii. Tool Box Meeting shall be conducted on a monthly basis.
iii. Safety briefing shall be conducted prior to the actual work.

8.2 Verification Documents


Prior to work commencement all equipment to be used shall be inspected and
confirmed fit for use by contractor’s safety officer and/or supervisor. Personnel
shall be made aware that the work is potentially dangerous and that if
carelessness or short-cuts are allowed, serious accidents are very likely to occur.
When hoisting the Cooling Tower, no workers shall stand below the hoisting units.
Safety hardness shall be worn when the workers are working at height.