INSPECTION & TEST PLAN Testing & Commissioning of MRL Elevators
Doha Metro - Green Line Elevated & At Grade Doc.: M009-SPH-TCH-PRO-00009 Rev. 1 Date: 01-04-2019 ITP_00009
Intervention Points (# - Engineer/Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - WIR to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - WIR to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The
documents to be submitted for review)
Engineer's
Contractor
Control Documents
Engineer/
# Works
Assistant
3rd Party
Checking Activity to be Responsible Required
Subcon.
Acceptance Criteria Documents
Performed Job function Frequency
Vol. Clause
Intervention Points (# - Engineer/Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - WIR to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - WIR to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The
documents to be submitted for review)
Engineer's
Contractor
Control Documents
Engineer/
# Works
Assistant
3rd Party
Checking Activity to be Responsible Required
Subcon.
Acceptance Criteria Documents
Performed Job function Frequency
Vol. Clause
ITP_00004
Appendix A
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TCP01/F‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 1 of 1
Drawing Ref.:
PRE‐COMMISSIONING CHECKLIST (MRL ELEVATOR)
CIRCUIT DETAILS COLD TEST
INSULATION RESISTANCE (GΩ) Earth
Sl. No. Cable Size No. of Test Volts in
Continuity in Motor Cable (GΩ)
(mm²) Cores DC R‐Y R‐B Y‐B RYB‐N RYB‐E N‐E Ω
1 U
2 V
3 W
NOTE: If Test Volt is 1000VDC, The Acceptance value is not less than 0.5 MΩ
If Test Volt is 500VDC, The Acceptance value is not less than 0.25 MΩ
FIELD WIRING AND VOLTAGE CHECK LIST‐ ELEVATOR
CHECK POINT RESULT
S.NO AREA CHECK ITEM
CMC4 TAC50 TCM Status OK Not Ok
Controller Terminal Controller Terminal Car Top Terminal
1 Car Door Continuity
C1 ‐ C2 CNHV4‐1 ‐ CNHV4‐7 X1‐114 ‐ X1‐115
(CABLE / CONNECTOR No.)
Controller
Controller Terminal Controller Terminal Controller Terminal
7 Power 220 Volt AC
L2 ‐ N S ‐ N L2 ‐ N
Supply
Controller
Controller Terminal Controller Terminal Controller Terminal
8 Power 220 Volt AC
L2 ‐ N T ‐ N L2 ‐ N
Supply
Controller UCM Board Controller Terminal Controller Terminal Low Voltage
9 24 Volt DC
X7.1 ‐ X7.2 P24 ‐ G24 X9‐24V ‐ X9‐0V Supply
Test Instrument Details:
Instrument Name & Calibration Certificate Calibration Date / Due
SI No. Serial No.
Model No. Date
RESULTS:
To be rectified and resubmitted before commissioning
To be rectified / comments will be checked at the beginning of commissioning
Confirmed / OK for commissioning
Remarks:
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TCP01/F‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 1 of 1
Drawing Ref.:
PRE‐COMMISSIONING CHECKLIST (MRL ELEVATOR)
Verified
Sl. No Check List Remarks
OK Not OK
Check the 3 phase power supply, 3ph + N+ E with sufficient capacity to
1
the elevator control cabinet.
Single phase power supply for cabin lighting, 1ph + N+ E with sufficient
2
capacity to the elevator control cabinet.
Scaffoldings should be removed and the hoist way is free from
3
obstructions
All the landing doors are mechanically closed and locked and can’t be
4
opened without the ThyssenKrupp door emergency key
5 All safety devices and switches are in place as well as in circuit
6 All grounding cables are grounded properly and checked
Earth bonding connections between the different elevator parts to be
7
checked.
Check the incoming power and earth wire which are connected to the
8
distribution board.
9 Check the earth wire connected to the Motor
10 Check motor to CPI drive unit wiring
11 Motor cable connection
12 Motor encoder connection
13 Brake coil and brake switches connection
Check the connection between main drive unit and regenerative drive
14
unit.
15 Check drive unit to controller wiring
16 3 Phase Power Supply connection
17 Communication Cable connection
18 Input/output Signals connection
19 Check Braking resistor connected to the CPI
Check the Resistance between U,V and W terminals of Motor and the
20
earth bar and verify to make no short‐circuit
Remarks:
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TCP01/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 1 of 3
Drawing Ref.:
COMMISSIONING RECORD / FINAL INSPECTION SHEET (MRL ELEVATOR)
VERIFIED
Sl.No. DESCRIPTION CRITERIA ACTUAL EN‐81‐1
YES NO
1 GENERAL INFORMATION
1.1 Travel Height m m
1.2 Number of stops :
Front
Rear
Total
1.3 Rated load : kg kg
persons persons
1.6 Power supply :
Voltage 415V
Phase 3Phase+N+E
Main switch rating
Number of poles 4
1.7 Motor Details
1 Make
2 Serial number
3 Type
4 AC voltage
5 Power rating
6 Current rating
7 Class of insulation
8 Full Load current
2 CONTROLLER AREA
2.1 Operational data at mid point of travel under normal operating conditions :
Max. leveling deviation
Car loading Lift Lift motor input
(+ or ‐)5mm
12.6
m/s V A mm mm
Empty up
down
45% up
down
Rated up
down
Note: Calibrated Test weights to be used.
2.2 Safety Gear Test
Perform with empty load & Inspection Speed
Check Automatic Rescue Device(ARD)function that in
case of power failure, the elevator car stops
momentanily and after a delay, the ARD activates
2.3 ____
and should bring the car to the next level and door
should open. If car is already in level, the doors shall
open.
2.4 Check emergency stop switch near the machine 6.4.5
2.5 Check the governor safety swich 9.9.11.1
Inspection of wire rope and rope fastenings
2.6 9.9.6.5
(Governor)
2.7 Check installation of Machine Rope Guard 9.7.1
2.8 Check Machine Room Light is satisfied ____
2.9 Check Machine Room Air Condition ____
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TCP01/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 2 of 3
Drawing Ref.:
COMMISSIONING RECORD / FINAL INSPECTION SHEET (MRL ELEVATOR)
VERIFIED
Sl.No. DESCRIPTION CRITERIA ACTUAL EN‐81‐1
YES NO
2.10 Check Emergency Instructions Displayed ____
3 CAR TOP
Check installation of Counterweight Rope and Car
3.8 9.2.3.1
Rope Thimble rod and split pins
4 CAR ( CABIN ) INSIDE
Check intercom and alarm properly function when
4.5 14.2.3.3
normal power is off
Check emergency light ‐ LCD display act as
4.6 8.17.4
emergency light
Check the clearence between car door and front
4.9 4 to 6 mm 8.6.3
panel
Check the overload indicator and buzzer when the
4.10 14.2.5.3
car has more than 100% of rated load.
Check the device to reverse door whilst closure
4.12 8.8
movement with automatic action
5 ENTRANCES
Check fire man Phase ‐1 operation
Phase 1‐1 ‐ Activate fire signals whether manual
switch located main lobby floor or automatically
from smoke detector activation . The car calls and
5.3 landing calls were ignored. If lift is travelling away EN‐81‐72 5.8.7
from main lobby floor, it is stopped at the next stop
and after that it is directed with out any interruption
to the main lobby floor and door keep open until
reset fire alarm.
Check fire man Phase‐2 operation
Phase 2 ‐ Phase1 has been initiated by an external
signal, the lift shall not operate until fire man switch
5.4 EN‐81‐72 5.8.8
has been operated inside the car It shall not be
possible to register more than one car call
simultaneously.
Check landing door unlocked from out side by the
5.5 7.7.3.2
use of emergency unlocking key
Check the door contact make properly when the
5.6 7.7.3.1.1
doors are released with 7mm gap inbetween
Check the clearence between door and entrance
5.7 4 to 6 mm 7.1
frame
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TCP01/F‐02‐01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 3 of 3
Drawing Ref.:
COMMISSIONING RECORD / FINAL INSPECTION SHEET (MRL ELEVATOR)
VERIFIED
Sl.No. DESCRIPTION CRITERIA ACTUAL EN‐81‐1
YES NO
5.9 Check landing door mechanical locks 7.7.3.2
6 PIT
Check that the buffers are installed as per approved
6.6 ____
layout drawings
7 TRIAL RUN TEST
30 minutes continuous run test of the elevator in
order to assure the smooth
7.1 and proper performance of the unit during
deceleration, acceleration and
travelling between floors.
Test Instrument Details:
Instrument Name & Calibration Certificate
SI No. Serial No. Calibration Date / Due Date
Model No.
Remarks:
NAME
POSITION
DATE
SIGNATURE
Testing & Commissioning of MRL Elevator
PROJECT: DOHA METRO PROJECT TKEQ/TMHP/01
LINE: GREEN LINE ELEVATED & AT GRADE Rev. 1
STATION: AL RIFFA (GWST080) Date:
LIFT No.: Page 1 of 1
Drawing Ref.:
INSPECTION SIGN‐OFF SHEET (HOLD POINT 1)
ACCEPT
REJECT
SI.No. NATURE OF INSPECTION REMARKS
1 Pre‐commissioning checks conducted and records in order.
Inside car operation (COP functions) and signals are checked as
2
per specification.
3 Functioning of all safety devices are checked and are ok.
Tagging and identification of all equipments in the machine area
4
completed.
Functioning of all items on the cartop and inside the hoistway are
5
satisfactory.
Outside hoistway devices operations and signals are fuctioning
6
properly.
7 Functioning of equipments in the pit is satisfactory.
Test run of the elevator is done as per the requirements of the
8
specification.
REMARKS:
NAME
POSITION
DATE
SIGNATURE
Property: TC Dept. Status: Final
M009-SPH-TCH-PRO-00009 Rev. 1 1 of 1 SPH JV - Internal Use Only