ID Task Name Duration Start Finish b '17 13 Feb '17 20 Feb '17 27 Feb '17 06 Mar '17 13 Mar '17 20 Mar '17 27 Mar '17
T F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F
1 Install Hydro Turbine 30 days Mon 13/02/17 Fri 24/03/17
2 Site Portion 10 days Mon 13/02/17 Fri 24/02/17
3 Mobilization 2 days Mon 13/02/17 Tue 14/02/17 13/02 14/02
5 External Spool pipe installation 3 days Mon 20/02/17 Wed 22/02/17 20/02 22/02
10 After install check 1 day Sat 04/03/17 Sat 04/03/17 04/03 04/03
11 Performance check 3rd 1 day Sun 05/03/17 Sun 05/03/17 05/03 05/03
14 Start Run Plant 3 days Sat 04/03/17 Tue 07/03/17 04/03 07/03
15 Final check performance 2 days Wed 08/03/17 Thu 09/03/17 08/03 09/03