Client : UBE. Thailand.

MAIN SCHEDULE 4-2-2017


Contracter : PILIN PROJECT CO.,LTD. Modify cooling system at UBE. Thailand. Rev.2

ID Task Name Duration Start Finish b '17 13 Feb '17 20 Feb '17 27 Feb '17 06 Mar '17 13 Mar '17 20 Mar '17 27 Mar '17
T F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F SSMTWT F
1 Install Hydro Turbine 30 days Mon 13/02/17 Fri 24/03/17
2 Site Portion 10 days Mon 13/02/17 Fri 24/02/17
3 Mobilization 2 days Mon 13/02/17 Tue 14/02/17 13/02 14/02

4 Scaffolding 3 days Wed 15/02/17 Fri 17/02/17 15/02 17/02

5 External Spool pipe installation 3 days Mon 20/02/17 Wed 22/02/17 20/02 22/02

6 Platform installation 2 days Thu 23/02/17 Fri 24/02/17 23/02 24/02

7 SHUTS DOWN PERIOD 5 days Sun 26/02/17 Fri 03/03/17


8 See DETAIL SCHEDULE 6 days Sun 26/02/17 Fri 03/03/17 26/02 03/03

9 Commissioning 0 days Sat 04/03/17 Sun 05/03/17 05/03

10 After install check 1 day Sat 04/03/17 Sat 04/03/17 04/03 04/03

11 Performance check 3rd 1 day Sun 05/03/17 Sun 05/03/17 05/03 05/03

12 Remove Scaffolding 2 days Sat 04/03/17 Mon 06/03/17 04/03 06/03

13 Demobilization 2 days Tue 07/03/17 Wed 08/03/17 07/03 08/03

14 Start Run Plant 3 days Sat 04/03/17 Tue 07/03/17 04/03 07/03

15 Final check performance 2 days Wed 08/03/17 Thu 09/03/17 08/03 09/03

16 Final Document 12 days Thu 09/03/17 Fri 24/03/17 09/03 24/03

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: SCHEDULE MODIFY OF COOLING TO Milestone Inactive Milestone Start-only


Date: Sat 04/02/17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress