You are on page 1of 11

EP-CM-F-0004-003

CLIENT NAME : THAI PLASTIC AND CHEMICALS PUBLIC COMPANY LIMITED TOTAL: 11 SHEETS

PROJECT NAME : TPR Productivity improvement PG680,740 130 MTPD ( Including Cover )

PROJECT NO. : C-22-1092


LOCATION : RAYONG THAILAND

MECHANICAL DOCUMENT

HYDROSTATIC TEST PROCEDURE

FOR BATCH RTRAINER H3001B

DISTRIBUTION
Master File
Client

Maintenance

Procurement

ENG. DESIGN
EM
PR
PIP
IE
MSE
MRE
EE
CVE
IC
] IA
CONSTRUCTION
PM
CM
CVE
ME
PIP
IE
EE

A IFR = Issue for Review Khanis Y. 12-Nov-22 Khanis Y. 12-Nov-22 Khanis Y. 12-Nov-22
REV. PURPOSE PRED. DATE CHKD. DATE APPD. DATE EM DATE PM DATE

PILIN PROJECT CO.,LTD.

Vendor / Fabricator / Contractor REPCO Doc. No. Client Doc. No. Issued Date

6518-PRO-05-A TPC-000-MSE-PRO-H3001B-05-A - 12-Nov-22


IFS = Issue for Squadcheck IFR = Issue for Review IFE = Issue for Enquiry IFD = Issue for Design IFC = Issue for Construction
IFI = Issue for Information IFP = Issue for Purchase IFF = Issue for Final
EP-CM-F-0004-003

PILIN PROJECT CO.,LTD.

REPCO Doc. No. Rev. Sheet No.


REVISION LIST
TPC-000-MSE-PRO-H3001B-05-A A 2 OF 11

REV. DATE ITEM No. REFERENCE DOCUMENT DESCRIPTION

A 12-Nov-22 - - IFR = Issue for Review


0 22-Jan-18 - - IFC = Issue for Construction
6518-PRO-05-A

1)

2)

3)

4)

5)

6)

7)

8)

9)

10)

11)

12)

13)

14)
6518-PRO-05-A

1 Scope:

1.1

PILIN

1.2

2 Reference Code:

-
-
-
-

2.1

3 Testing Schedule:

3.1

3.2
6518-PRO-05-A

3.3

3.4

4 Pressure Gauges:

4.1

4.2

4.3

4.4

5 Test Medium:

5.1
6518-PRO-05-A

6 Preparation for Pressure Testing:

6.1

6.2

6.3

7 Filling with Test Medium and Venting:

7.1

7.2

7.3

7.4

8 Test Pressure:

8.1

8.2
6518-PRO-05-A

8.3

8.4

PT = (1.5 PST)/S
6518-PRO-05-A

8.5

9 Holding Time, Test Temperature and Close Examination:

9.1

9.2

9.3

Maximum metal
Applicable Code Minimum test metal temperature temperature during
Section close examination

Table (1): Maximum and minimum metal temperatures during Hydrostatic Test.
6518-PRO-05-A

Applicable Code Section Close examination pressure

Table (2): Pressure during close examination.

10 . Test Pressure Release:

10.1

10.2

10.3

11 Repair Case:

11.1
6518-PRO-05-A

12 . HSE Precautions:

12.1

12.2

13 . Report:

13.1

14 Attachments:

-
6518-PRO-05-A