Professional Documents
Culture Documents
: TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :1/10
TITLE :
METHOD STATEMENT FOR ROTATING EQUIPMENT INSTALLATION
FOR APPROVAL
REVIEW STAMP
☐ : APPROVED WITH NO COMMENT.
☐ : APPROVED AS NOTED
☐ : COMMENT
☐ : RESUBMIT
This approval does not relieve the Vendor/Subcontractor of his
responsibility to meet all requirement of the CONTRACT
APPROVED BY : DATE :
CONTENTS
Page
1. PURPOSE 3
2. SCOPE 3
3. REPONSIBILITIES 3
4. GENARAL 3
6. INSTALLATION 6
7. LEVELING OF EQUIPMENT 6
8. GROUTING 7
9. ALIGNMENT OF EQUIPMENT 8
12. INSPECTION 10
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :3/10
1. PURPOSE
The purpose of this procedure is to establish the methods for the field installation of rotating
equipment at T-2 Project.
2. SCOPE
This procedure describes the requirements for installation, leveling, alignment work of pumps,
compressors including their drivers and auxiliary equipment and other rotating equipment.
This procedure describes only general requirement for installation, so the manufacturer’s installation
manuals/instructions shall also be applied for execution of installation.
3. RESPONSIBILITIES
3.1 This procedure shall be provided by the CONTRACTOR’s mechanical engineer, reviewed by
the QA/QC department and approved by COMPANY before use.
3.2 The CONTRACTOR’s mechanical engineer is responsible for supervising these activities
required by this procedure.
4. GENERAL
4.1 The installation work shall comply with the requirements specified herein, the relevant drawings
and the requirements of the applicable safety codes or regulations of the locality. Any conflicts or
questions would be found among this specification, the drawings and the others shall be referred to
CONTRACTOR for resolution.
4.2 All work shall be performed under the CONTRACTOR engineer or his authorized representative.
4.3 Instruments and tools to be used in leveling and alignment shall satisfy the conditions shown in
the Table 1.
Spirit level made of steel Length 200mm and longer, sensitivity 2/100mm
5.2.3 When anchor holes are used for anchor bolts, the anchor bolts shall be installed in the anchor
hole after the equipment is temporarily placed in the right position. After the grouted mortar has
sufficiently hardened, leveling work shall be provided. Anchor holes shall be cleaned before
temporary installation of the equipment.
5.3 Liners
5.3.1 Liners to be used, in general, shall be made of carbon steel, unless otherwise specified in the
specific instructions by the manufacturer, etc.
5.3.2 Liners shall be arranged so that the load of the equipment is uniformly distributed on the
foundation within allowable load. In general, the liners shall be placed as near as possible to both
side of each anchor bolt.
7.4 Checking of Equipment
5.4.1 Prior to the installation, the following check to the equipment shall be made:
1) Appearance of equipment, such as damage and rust free condition.
2) The number and appearance of auxiliaries.
3) Size of the anchor bolts and damage and rust of the threaded parts, if anchor box type is
applied.
4) Orientation marking.
5) Marking of center of gravity.
6) Lifting points.
5.4.2 Oil and other foreign matters stuck on the surface of legs, beds, frames, etc, which will be in
contact with the grouting mortar, shall be entirely removed.
5.5 Condition and Protection of Equipment
5.5.1 Unpacking shall be performed under witness of the CONTRACTOR Engineer. All spare parts
and dismantling tools, etc., shall be repacked and returned to the warehouse as instructed by the
CONTRACTOR Engineer. Delicate parts, such as level oilers, capillary tubes, etc., shall be
removed in accordance with the instructions of the CONTRACTOR Engineer. The removed parts
shall be stored and maintained in the warehouse properly.
5.5.2 After being thoroughly inspected, the equipment shall be transported to the jobsite.
5.5.3 The condition of the machined surfaces shall be checked, and if necessary, the machined
surfaces shall be coated properly with a suitable rust preventative.
5.5.4 Temporary covers on all openings shall be tightened firmly and shall not be removed during
installation until the related pipelines are to be connected thereto.
5.5.5 The bottom face of the base plate shall be cleaned. When oil, grease, dirt or any loose
particles are found, it shall be washed off by water or other suitable solvents before installation.
5.5.6 Coupled equipment shall be uncoupled and left uncoupled until the no-load test for the driver
is finished. Coupling elements with clear identifications shall be stored properly in the warehouse.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :6/10
6. INSTALLATION
Installation of equipment shall be executed in accordance with this procedure taking precautions so
that the anchor bolts and foundations will not be damaged and the equipment not distorted.
When anchor holes are used, the curing time of the grout mortar filled in the holes shall be checked
before the starting of the leveling work.
7. LEVELING OF EQUIPMENT
7.1 Liners and Wedges
7.1.1 In general, liners and wedges shall be prepared as indicated in Table 2. The dimensions may
be modified as necessary or each application
7.1.2 A pair of wedges shall be used and the inclined surface of each wedge shall be contact with
each other more than 60 percent of the surface.
7.1.3 Liners and wedges shall be located on both sides of each anchor bolt and shall be placed
close to the anchor bolts. Where the distance between the anchor bolts is larger than 80cm, extra
liners and wedges shall be located between the anchor bolts to prevent the base plate from bending.
7.1.4 The concrete surface where the liner plates will be placed shall be chipped smoothly and be
cleaned completely.
7.1.5 A final check shall be made to ensure that the center of the equipment matches the center line
marked of the foundation.
7.2 Leveling
7.2.1 Leveling shall be performed using a spirit level on the machined surface of the driver base
plate, or on the suction flange or discharge flange of the vertical nozzles on the top of the
equipment unless otherwise specified. Leveling shall be measured laterally in the direction of the
shaft. Adjustments shall be made by inserting or removing liners and wedges.
7.2.2 The maximum tolerance from the level shall be 0.5mm, unless otherwise specified in the
Instruction Manual.
7.2.3 After leveling is finished the lockouts of the anchor bolts shall be tightened firmly.
7.2.4 After the lockouts of the anchor bolts are tightened firmly, the liners and wedges shall be tack-
welded to each other, and any excess in the liners and wedges shall be cut off with a gas cutter.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :7/10
8.4.2 Procedure
1) All surfaces must be clean, free from standing water and all loosely adhering particles.
Cement latency must be removed, by mechanical means.
2) Mix with a slow speed electric drill for 1-2 minutes. Then add the aggregate and continue
mixing until a homogeneous mortar is achieved.
3) Application
- When grouting under bearing hates, ensure there is sufficient pressure to maintain
movement of the grout. Air must be allowed to escape.
- For large volumes, apply in more than one layer, ensuring that the previous layers have
hardened and cooled.
4) Clean all tolls and equipment immediately after use with thinner.
9. ALIGNMENT OF EQUIPMENT
9.1 Initial Alignment
9.1.1 After completion of the grouting and prior to connecting piping, alignment of equipment shall
be performed as follows :
9.1.2 The parallelism of the end surface of the equipment coupling hub and the driver coupling hub,
the clearance between the coupling hubs, and the parallelism of the center lines of the shafts hall
be measured with a dial gauge at the four points at 90 degree intervals, and shall be adjusted by
inserting shims under the lug or the saddle of the driver and/or speed exchanger.
9.1.3 Tolerance of alignment shall be indicated in Table 3. The material of the shims for alignment
shall be of brass or of stainless steel. The size of the shims shall be at least 150mm in width, and
0.03, 0.04, 0.05, 0.1, 0.2, 0.5, 1 and 2mm in thickness, and if legs or saddles of the equipment are
smaller than 150mm in which, the size of the shims shall be the same as the width of the equipment.
Item Tolerance
Parallelism of center lines of shafts 0.05mm
Parallelism of surfaces of coupling hubs 0.1mm(diameter of coupling)
9.2.2 When any misalignment is found in the piping during the above inspection, the information
shall be given to the CONTRACTOR engineer.
9.2.3 After the piping alignment check is completed and/or misalignment of piping is corrected, the
suction and discharge piping shall be connected to the equipment nozzles and the final cold
alignment of the equipment shall be checked with a dial gauge.
9.2.4 Any offset on the alignment of the equipment found as a result of the piping connections shall
be corrected as follows :
1) Offset values of 0.2mm or less shall be adjusted by inserting or removing shims under
the lug or saddle or the driver and/or speed exchangers without correcting and piping
alignment.
2) Offset values exceeding 0.2mm shall be reduced by correcting the suction and/or
discharge piping by burning or re-adjusting the pipe support, and, if necessary, the suction
and/or discharge piping shall be disconnected and be welded again to correct alignment of
the equipment and this welding joint shall be done NDE and hydraulic testing.
9.3 Final Check
After completing alignment, the follow shall be ascertained :
9.3.1 By revolving the coupling by the hand or a turning device in the direction of the arrow mark,
the equipment should rotate easily,
9.3.2 The direction or rotating of the driver shall be the same as indicated by the arrow mark.
9.3.3 After the above and an instrumental check and a no-load test of the drive, the equipment shall
be coupled and be capable of being rotated again easily by the hand or a turning device. If the
equipment has any protection device such as a turbine trip system, it shall be tested before coupling.
9.3.4 The setting of the coupling guard shall be checked.
12. INSPECTION
Inspection shall be made to assure that all the requirement prescribed in para. 5.0 through 11.0
have been done satisfactorily. All inspection and alignment records of the equipment shall be
submitted to Engineers.