You are on page 1of 10

MKK JOB No.

: TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :1/10

TITLE :
METHOD STATEMENT FOR ROTATING EQUIPMENT INSTALLATION

DOCUMENT NO. :PLP-MKK-M002


PO NO. : TA1000049-P-001(S)
MKK JOB NO. : TA1000049-0000
EQIPMENT : Rotating Equipment
ITEM NO. :

PROJECT NAME : T-2


OWNER : MGC Electrotechno (Thailand) Co., Ltd.
CONTRACTOR : MKK Asia Co.,Ltd
VENDOR : PILIN PROJECT CO., LTD

FOR APPROVAL

REVIEW STAMP
☐ : APPROVED WITH NO COMMENT.
☐ : APPROVED AS NOTED
☐ : COMMENT
☐ : RESUBMIT
This approval does not relieve the Vendor/Subcontractor of his
responsibility to meet all requirement of the CONTRACT
APPROVED BY : DATE :

MKK Asia Co.,Ltd

A 8-Feb-21 Issued for Approval Ramin Y. Chatchawan

REV. DATE DESCRIPTION Prepared By Reviewed By QA Review By Approved By


MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :2/10

CONTENTS
Page

1. PURPOSE 3

2. SCOPE 3

3. REPONSIBILITIES 3

4. GENARAL 3

5. PREPARATION FOR INSTALLATION 4

6. INSTALLATION 6

7. LEVELING OF EQUIPMENT 6

8. GROUTING 7

9. ALIGNMENT OF EQUIPMENT 8

10. INSPECTION AND PREPARATION BEFORE TEST OPERATION 9

11. INSPECTION AFTER TEST OPERATION 10

12. INSPECTION 10
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :3/10

1. PURPOSE
The purpose of this procedure is to establish the methods for the field installation of rotating
equipment at T-2 Project.

2. SCOPE
This procedure describes the requirements for installation, leveling, alignment work of pumps,
compressors including their drivers and auxiliary equipment and other rotating equipment.

This procedure describes only general requirement for installation, so the manufacturer’s installation
manuals/instructions shall also be applied for execution of installation.

3. RESPONSIBILITIES
3.1 This procedure shall be provided by the CONTRACTOR’s mechanical engineer, reviewed by
the QA/QC department and approved by COMPANY before use.
3.2 The CONTRACTOR’s mechanical engineer is responsible for supervising these activities
required by this procedure.

4. GENERAL
4.1 The installation work shall comply with the requirements specified herein, the relevant drawings
and the requirements of the applicable safety codes or regulations of the locality. Any conflicts or
questions would be found among this specification, the drawings and the others shall be referred to
CONTRACTOR for resolution.
4.2 All work shall be performed under the CONTRACTOR engineer or his authorized representative.
4.3 Instruments and tools to be used in leveling and alignment shall satisfy the conditions shown in
the Table 1.

Instruments Service Item Size and Accuracy

Spirit level made of steel Length 200mm and longer, sensitivity 2/100mm

Length 200mm and longer,sensitivity 5/100mm


Leveling Straight edge made of steel Length 1,500mm(Ibeam type)

Length 500mm(Ibeam type)

Dial gauge with magnetic base Min. graduation 1/100mm

Thickness gauge made of steel Length of leaf 100-150mm,width of leaf 10-15mm


Alignment Length of leaf 200-300mm

Taper gauge made of steel Length of leaf 150mm,width of leaf 10-15mm

Right angle ruler made of steel Effective length 300mm,width 300mm

Vernier caliper Length 200mm, graduation 5/100mm(inner and outer use)


MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :4/10

5. PREPARATION FOR INSTALLATION


Prior to starting the work, the following shall be conformed to be satisfactory under witness of the
CONTRACTOR engineer. Any defects found shall be referred to be CONTRACTOR engineer and
repaired or improved properly and immediately in accordance with the instruction of the
CONTRACTOR engineer.
5.1 Foundation
5.1.1 Foundation shall be checked before installation for the following items.
1) Curing period of foundation concrete.
2) Dimensions.
3) Positions (center marking) and height (level marking).
4) Disorders in the foundation concrete, such as abnormal concentration of aggregates,
porous state.
5) Size of anchor bolts, and damage or rust of threaded parts.
6) Dimension and cleanliness of anchor boxes, if anchor box type is applied.
5.1.2 Treatment of the surface of the foundation, such as chipping and fitting, shall be carried out as
follows.
1) Foreign matters shall be completely removed.
2) Foundation surface shall be chipped slightly for the part on which the mortar padfor liner
plates is formed.
5.2 Anchor Bolts
5.2.1 The following conditions of the anchor bolts embedded in the foundation shall be checked
against the drawings or with a steel template for the major equipment.
1) Position - Tolerance shall be 1.5mm from the dimension indicated on the related
equipment drawing.
2) Projection - The projection of the bolts above the foundation surface shall be proper
length relative to the final level of the foundation finish.
3) Inclination - There must be no inclination of the bolts which may prevent the equipment
base plate from fitting smoothly.
4) Condition of bolts and nuts - Threaded parts shall be completely coated with grease or
machine oil allowing the nuts is unscrewed smoothly.
5.2.2 Anchor bolts with pipe sleeves to allow adjustment of the final positioning of the bolt shall be
checked with the following.
1) Position - Anchor bolts shall be accurately located as shown on the related equipment
drawing.
2) Projection - The projection of the bolts above the foundation surface shall be proper
length relative to the final level of the foundation finish.
3) Sleeve - Unless otherwise specified in the Instruction Manual, pipe sleeves shall be
approximately 50mm larger in diameter than anchor bolt.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :5/10

5.2.3 When anchor holes are used for anchor bolts, the anchor bolts shall be installed in the anchor
hole after the equipment is temporarily placed in the right position. After the grouted mortar has
sufficiently hardened, leveling work shall be provided. Anchor holes shall be cleaned before
temporary installation of the equipment.
5.3 Liners
5.3.1 Liners to be used, in general, shall be made of carbon steel, unless otherwise specified in the
specific instructions by the manufacturer, etc.
5.3.2 Liners shall be arranged so that the load of the equipment is uniformly distributed on the
foundation within allowable load. In general, the liners shall be placed as near as possible to both
side of each anchor bolt.
7.4 Checking of Equipment
5.4.1 Prior to the installation, the following check to the equipment shall be made:
1) Appearance of equipment, such as damage and rust free condition.
2) The number and appearance of auxiliaries.
3) Size of the anchor bolts and damage and rust of the threaded parts, if anchor box type is
applied.
4) Orientation marking.
5) Marking of center of gravity.
6) Lifting points.
5.4.2 Oil and other foreign matters stuck on the surface of legs, beds, frames, etc, which will be in
contact with the grouting mortar, shall be entirely removed.
5.5 Condition and Protection of Equipment
5.5.1 Unpacking shall be performed under witness of the CONTRACTOR Engineer. All spare parts
and dismantling tools, etc., shall be repacked and returned to the warehouse as instructed by the
CONTRACTOR Engineer. Delicate parts, such as level oilers, capillary tubes, etc., shall be
removed in accordance with the instructions of the CONTRACTOR Engineer. The removed parts
shall be stored and maintained in the warehouse properly.
5.5.2 After being thoroughly inspected, the equipment shall be transported to the jobsite.
5.5.3 The condition of the machined surfaces shall be checked, and if necessary, the machined
surfaces shall be coated properly with a suitable rust preventative.
5.5.4 Temporary covers on all openings shall be tightened firmly and shall not be removed during
installation until the related pipelines are to be connected thereto.
5.5.5 The bottom face of the base plate shall be cleaned. When oil, grease, dirt or any loose
particles are found, it shall be washed off by water or other suitable solvents before installation.
5.5.6 Coupled equipment shall be uncoupled and left uncoupled until the no-load test for the driver
is finished. Coupling elements with clear identifications shall be stored properly in the warehouse.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :6/10

6. INSTALLATION
Installation of equipment shall be executed in accordance with this procedure taking precautions so
that the anchor bolts and foundations will not be damaged and the equipment not distorted.
When anchor holes are used, the curing time of the grout mortar filled in the holes shall be checked
before the starting of the leveling work.

7. LEVELING OF EQUIPMENT
7.1 Liners and Wedges
7.1.1 In general, liners and wedges shall be prepared as indicated in Table 2. The dimensions may
be modified as necessary or each application

7.1.2 A pair of wedges shall be used and the inclined surface of each wedge shall be contact with
each other more than 60 percent of the surface.
7.1.3 Liners and wedges shall be located on both sides of each anchor bolt and shall be placed
close to the anchor bolts. Where the distance between the anchor bolts is larger than 80cm, extra
liners and wedges shall be located between the anchor bolts to prevent the base plate from bending.
7.1.4 The concrete surface where the liner plates will be placed shall be chipped smoothly and be
cleaned completely.
7.1.5 A final check shall be made to ensure that the center of the equipment matches the center line
marked of the foundation.
7.2 Leveling
7.2.1 Leveling shall be performed using a spirit level on the machined surface of the driver base
plate, or on the suction flange or discharge flange of the vertical nozzles on the top of the
equipment unless otherwise specified. Leveling shall be measured laterally in the direction of the
shaft. Adjustments shall be made by inserting or removing liners and wedges.
7.2.2 The maximum tolerance from the level shall be 0.5mm, unless otherwise specified in the
Instruction Manual.
7.2.3 After leveling is finished the lockouts of the anchor bolts shall be tightened firmly.
7.2.4 After the lockouts of the anchor bolts are tightened firmly, the liners and wedges shall be tack-
welded to each other, and any excess in the liners and wedges shall be cut off with a gas cutter.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :7/10

8. GROUTING (if any)


8.1 Preparation for Grouting
The top of surface of the foundation shall be wetted thoroughly with fresh water prior to the grouting
work. If pipe sleeves are used for anchor bolts, standing water in the sleeves shall be removed by a
manual air pump, etc.
8.2 Material
8.2.1 Non-shrinking mortar shall be used under the outer frame of the base plate and in the
sleeves. Portland cement may be used in the base plate and in the sleeves to grout the equipment,
unless otherwise specified in the Instruction Manual.
8.2.2 The mixing ratio of non-shrinking mortar, portland cement, and clean fine sand, and the ratio
of water to cement shall be as specified by the non-shrinking mortar manufacturer.
8.2.3 The mixing ratio of portland cement and clean fine sand shall be 1 : 2 in volume, and the ratio
of water, to cement shall be less than 40 percent in volume, unless otherwise specified.
Compressive strength of epoxy and non-shrink cementations is 630 kg/cm2 at 7 days.
8.3 Grouting Procedure
8.3.1 Sleeves used for anchor bolts shall be filled with grouting mortar under witness of the
CONTRACTOR engineer after which, grouting for the outer frame of the base plate shall be done in
accordance with par. 4.2.1, unless otherwise specified in the Instruction Manual.
8.3.2 The base plate shall be grouted as follows :
1) The base plate shall be grouted ram the grout hole.
2) The grout shall cover all wedges and liners.
3) All trapped voids under the base plate shall be vented to allow full penetration of the
grouting mortar.
8.3.3 The surface of the mortar outside the base plate shall be finished smoothly.
8.3.4 All liners and wedges shall not be removed.
8.3.5 Grouting shall be inspected using light hammering to confirm that the mortar is filled fully in
the base plate voids and no cracks shall occur on the hardened surface.
8.3.6 Compressive Strength Test Grouting shall be sample, cured, and tested for compressive
strength in accordance with ASTM C172, C31 and C39. Compressive test cylinder shall be
prepared in oneset cylinder per each mixing batch for test/and all tests must be carried out in testing
laboratory.
8.4 Epoxy Grouting
8.4.1 Grout for base-mounted or skid-mounted reciprocating machinery or critical centrifugal/rotary
compressors and pumps including drivers shall be epoxy type. Compliance with minimum
requirements of equipment vendors regarding grout materials and installation is mandatory.
Handling and placement of proprietary grouts shall be in strict accordance with the manufacturer's
recommended practice.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :8/10

8.4.2 Procedure
1) All surfaces must be clean, free from standing water and all loosely adhering particles.
Cement latency must be removed, by mechanical means.
2) Mix with a slow speed electric drill for 1-2 minutes. Then add the aggregate and continue
mixing until a homogeneous mortar is achieved.
3) Application
- When grouting under bearing hates, ensure there is sufficient pressure to maintain
movement of the grout. Air must be allowed to escape.
- For large volumes, apply in more than one layer, ensuring that the previous layers have
hardened and cooled.
4) Clean all tolls and equipment immediately after use with thinner.

9. ALIGNMENT OF EQUIPMENT
9.1 Initial Alignment
9.1.1 After completion of the grouting and prior to connecting piping, alignment of equipment shall
be performed as follows :
9.1.2 The parallelism of the end surface of the equipment coupling hub and the driver coupling hub,
the clearance between the coupling hubs, and the parallelism of the center lines of the shafts hall
be measured with a dial gauge at the four points at 90 degree intervals, and shall be adjusted by
inserting shims under the lug or the saddle of the driver and/or speed exchanger.
9.1.3 Tolerance of alignment shall be indicated in Table 3. The material of the shims for alignment
shall be of brass or of stainless steel. The size of the shims shall be at least 150mm in width, and
0.03, 0.04, 0.05, 0.1, 0.2, 0.5, 1 and 2mm in thickness, and if legs or saddles of the equipment are
smaller than 150mm in which, the size of the shims shall be the same as the width of the equipment.

Item Tolerance
Parallelism of center lines of shafts 0.05mm
Parallelism of surfaces of coupling hubs 0.1mm(diameter of coupling)

9.2 Alignment after Connecting Piping


After the suction and discharge nozzles are connected to piping, and the CONTRACTOR engineer
informed that all piping work such as installation of permanent supports, and hydraulic testing, if any,
are completed for the connected piping, alignment of the equipment shall be rechecked as follows :
9.2.1 Prior to commencing the final cold alignment, the suction and discharge piping shall be
disconnected and piping alignment such as off center, clearance, and parallelism between the
piping and connection flanges of the equipment nozzles shall be checked by visual inspection.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :9/10

9.2.2 When any misalignment is found in the piping during the above inspection, the information
shall be given to the CONTRACTOR engineer.
9.2.3 After the piping alignment check is completed and/or misalignment of piping is corrected, the
suction and discharge piping shall be connected to the equipment nozzles and the final cold
alignment of the equipment shall be checked with a dial gauge.
9.2.4 Any offset on the alignment of the equipment found as a result of the piping connections shall
be corrected as follows :
1) Offset values of 0.2mm or less shall be adjusted by inserting or removing shims under
the lug or saddle or the driver and/or speed exchangers without correcting and piping
alignment.
2) Offset values exceeding 0.2mm shall be reduced by correcting the suction and/or
discharge piping by burning or re-adjusting the pipe support, and, if necessary, the suction
and/or discharge piping shall be disconnected and be welded again to correct alignment of
the equipment and this welding joint shall be done NDE and hydraulic testing.
9.3 Final Check
After completing alignment, the follow shall be ascertained :
9.3.1 By revolving the coupling by the hand or a turning device in the direction of the arrow mark,
the equipment should rotate easily,
9.3.2 The direction or rotating of the driver shall be the same as indicated by the arrow mark.
9.3.3 After the above and an instrumental check and a no-load test of the drive, the equipment shall
be coupled and be capable of being rotated again easily by the hand or a turning device. If the
equipment has any protection device such as a turbine trip system, it shall be tested before coupling.
9.3.4 The setting of the coupling guard shall be checked.

10. INSPECTION AND PREPARATION BEFORE TEST OPERATION


10.1 General
Prior to the test operation of the equipment, the following confirmation shall be made under witness
of the CONTRACTOR engineer and vendor.
10.1.1 Chemical cleaning and oil flushing, if specified, have been finished.
10.1.2 The equipment can be rotate easily in the direction of the arrow mark by the hand. After this
inspection, the coupling shall be installed and lubricated properly. The coupling guard shall be
installed firmly.
10.1.3 All just preventatives, oil, grease, etc., used to protect the equipment during construction
shall be removed using solvents.
10.1.4 The equipment shall be filled with the proper lubricants as instructed in the Instruction
Manual.
10.1.5 All accessories, such as pressure gauges, safety valves etc., shall be installed properly.
MKK JOB No. : TA1000049-0000
Docu. No.:PLP-MKK-M002
VENDOR PRINT Rev. No: A
PILIN PROJECT CO., LTD. Page :10/10

10.2 Running Test


After completing the installation work, a running test for each equipment, without load shall be done
under the witness of the Engineer's/Company's representative. If any unusual sound, vibration of oil
leakage in found during the running test, the operation shall be stopped until the corrective
countermeasures are taken.
10.3 Hot Alignment
10.3.1 For equipment operated at high temperatures, if so specified in the Instruction Manual, the
difference in height between the centers of the equipment and driver shall be checked and adjusted
to operate under hot conditions.
10.3.2 The value of the hot alignment shall be clearly indicated on the name plate to be attached to
the coupling guard or shall be clearly painted of the coupling.

11. INSPECTION AFTER TEST OPERATION


11.1 Inspection of Alignment
11.1.1 The equipment shall be test operated under normal condition. After a steady operation is
attained, the driver shall be stopped and the hot alignment of the coupling shall be inspected
immediately. Any re-adjustment necessary shall be made by inserting or removing the shims under
the saddle of the driver or numbers the pedestal of the equipment. After adjustment, the equipment
shall be operated under normal condition for several hours and the alignment shall be rechecked in
accordance with para. 9.1 through para. 9.3.
11.1.2 The equipment shall be operated only with prior permission of the CONTRACTOR Engineer.

12. INSPECTION
Inspection shall be made to assure that all the requirement prescribed in para. 5.0 through 11.0
have been done satisfactorily. All inspection and alignment records of the equipment shall be
submitted to Engineers.

You might also like