Document History
Revision Review/Approv
Revision Date Status Originator Acceptance
Details ed
For
01 21.05.15 FA C.K. M.E.
Acceptance
For
00 16.04.15 FI C.K. M.E.
Information
Status code:
İÇİNDEKİLER
1. INTRODUCTION ......................................................................................................................................4
2. REFERENCE DOCUMENT.........................................................................................................................4
3. PERSONNEL AND RESPONSIBILITIES.......................................................................................................4
3.2. SITE HSE TEAM ...................................................................................................................................5
3.3. SITE QA/QC TEAM ..............................................................................................................................5
3.4. PIPING FOREMAN...............................................................................................................................5
3.5. RIGGER ...............................................................................................................................................5
3.6. BANKS MAN........................................................................................................................................5
EQUIPMENT LIST ............................................................................................................................................6
4. EXECUTION OF WORK ............................................................................................................................6
4.1. SCOPE OF APPLICATION .....................................................................................................................6
4.2. Preliminaries.......................................................................................................................................7
4.2.1. Safety Consideration ......................................................................................................................7
5. DETAILS FOR IMPLEMENTATION............................................................................................................8
5.1. PLANNING ..........................................................................................................................................8
5.2. PREPARATION / EXECUTION ..............................................................................................................8
5.3. POSTWORK.........................................................................................................................................9
VENTECH CPFII PROJECT
METHOD STATEMENT FOR
AIR BLOWING ON PIPE LINES
DOC.: REV.: 00 DATE :18.03.2014 Page 4 / 9
1. INTRODUCTION
The purpose of this work instruction is to describe the system that will be employed for Air
Blowing before Hydrostatic/ Pneumatic Testing of the process piping. Air blowing shall be
carried out using compressor/s which is part of equipment spread -1 for pneumatic Testing.
This procedure also describes all necessary HSE precautions related to plant, equipment,
tools, manpower and supervision requirements to satisfy permit issuing authorities that the
work have been adequately planned for a safe and efficient execution.
2. REFERENCE DOCUMENT
NO PERSONNEL
1 Construction Manager
2 Site Engineer
3 HSE Superintendent
4 HSE Officer
5 QA/QC Supervisor
6 Piping Foreman
7 Pipefitter
8 Helper
9 Rigger
10 Electrician
Site Management Team has overall responsibility to ensure that all steps in the schedule of
piping work will be proceed adequately and also will follow Method Statement and Procedures
with all requirements. Site management team is also responsible for providing all engineering
VENTECH CPFII PROJECT
METHOD STATEMENT FOR
AIR BLOWING ON PIPE LINES
DOC.: REV.: 00 DATE :18.03.2014 Page 5 / 9
support such as formulating, calculation, drawings, control points and related vendor package
documentation to facilitate timely, safe and efficient work progress. Coordinate all phases of
construction with other parties working in the vicinity of the erection area.
3.5. RIGGER
Responsible for managing all lifting operations using inspected lifting equipment and by the
methods identified on the Risk Assessment.
EQUIPMENT LIST
NO EQUIPMENT
1 Man lift
2 Pick up
3 Welding Machine
4 Grinding Machine
5 Electrode Oven
6 Drill Machine
7 Hand Tools
8 Tirfor
9 Compressor
4. EXECUTION OF WORK
4.2. Preliminaries
All other activities inside the barricaded area must be suspended during cleaning;
personnel not involved with the water flushing should evacuate the area.
Precommissioning Test Sheet: is to be prepared prior to the starting of the operation. Notice
to the commissioning team shall be sent together with Test Sheet and colored mark-up
P&ID's.
Fittings, hoses and connections will be of a class and rating equal to, or greater than the
pressure required to carry out air blowing operations (maximum of --- barg) and will carry
current certification.
In Operating Systems to be blown at the same time that construction activities are in
progress, preventive actions should be taken (communication, stoppage of work on the
lines to be flushed, etc.).
Check that line supports and temporary connections near blow outlet are adequate to avoid
line movements without control.
Before removing any line accessories, it must be checked that line is fully depressurized
and empty.
Drain points should never be cleared with wire and/or other manual tools if line is not
completely depressurised.
All points which require operations must be accessible.
All activities will be covered by a work permit. Air blowing will be covered by a "Cold Work
Permit". The work permit will be issued by the VENTECH supervisor assigned to the task
and signed by the designated responsible team member.
All electric equipment which can be affected by air blowing drainage (motors, junction
boxes, etc.) should be protected with plastic covers and de-energized.
During air blowing, design pressure of the system must not be exceeded.
VENTECH CPFII PROJECT
METHOD STATEMENT FOR
AIR BLOWING ON PIPE LINES
DOC.: REV.: 00 DATE :18.03.2014 Page 8 / 9
Specific procedures shall state maximum pressure to be used and mitigations steps to be
taken. Maximum system pressure and relevant precautions measures shall be included in
the system commissioning procedure.
Before starting the work check the availability of eye wash installations, fire extinguishers,
communications, etc
System to be blown shall be isolated from other systems connected to it.
All pressurizing hoses connections to be restrained by using whip checks and will be tied
down to immovable objects, at periodic intervals. The vent discharge point will also be
routed to a safe location away from any conflicting activities and barriers erected
accordingly.
All hand tools and consumable materials should be checked in every shift.
Site condition via roads, access and egress should be checked in every shift.
Contractor should be informed before commencement to work on all scaffolding
requirements and after completion it can be started.
All staffs and workers should have personnel training, induction and minimum necessaries
Sufficient number of H2S clips should be ready on site.
Make sure all required work permits have been issued and received prior to commence any
work.
5.1. PLANNING
• Rupture disks
• Orifice plates, turbines flow meters and other flow meter elements
• In-line mixers / In-line strainers
• Spray nozzles
• Analyzer probes
• Control valves
• Relief valves
• Manometers and pressure transmitters
• Thermometers and temperature transmitters
Prior to commencement of air blowing activities all relevant parties who will
witness the activity shall be advised 24 hours prior to commencement of work. Also,
before the commencement of blowing, the route shall be checked at site by the
Commissioning group in charge of this system with the prepared detailed procedure.
It is essential that any equipment removed is adequately preserved to prevent
damage.
5.3. POSTWORK
Drainage shall be adequately carried out, especially for lines working with oil.
Pipes concerned shall be reinstated as per P & I Diagrams and all temporary piping,
fittings and spools will be removed.
Suitable protective measures shall be taken for pipes where air blowing has been
completed, to ensure ingress of dirt does not occur.
Master cleaning P & I Diagrams shall be updated.
After blowing, the corresponding record sheet shall be sign off by all parties
confirming the acceptance of the work. This record will be included in the
corresponding Dossier.
After the completion of erection, scale, dirt, welding electrodes, slag, and other foreign
material should be removed from the lines. Particular attention should be paid to the
cleaning of all important lines.
Ventech will make the judgment of whether the result of the flushing is satisfying or not