ID Task Task Name Duration Start

3rd Quarter Finish


Mode July August
7/30 8/6 8/13 8/20
1 MAINTENANCE DREDGING OF ESCRAVOS SLIPWAY 118 days Mon 8/14/17 Sat 12/9/17
2 Pre-Dredge Survey Activities 15 days Mon 8/14/17 Mon 8/28/17
3 Logistics to Site for Pre-Dredge Survey 2 days Mon 8/14/17 Tue 8/15/17
4 Reconnaissance Survey of Spoil Disposal Site 1 day Fri 8/18/17 Fri 8/18/17
5 Joint CNL and MCNL Pre-dredge/Bathymetric Survey 3 days Sat 8/19/17 Mon 8/21/17
6 Set out areas for bund wall for spoil disposal 3 days Sat 8/19/17 Mon 8/21/17
7 Submit Pre-dredge report to CNL for review/approval 1 day Mon 8/28/17 Mon 8/28/17
8 Pre-Mobilization Activties 16 days Tue 9/5/17 Wed 9/20/17
9 Pre-Mobilization Inspection for complete dredging spread 11 days Tue 9/5/17 Fri 9/15/17
10 Close-out all open items from pre-mob inspection 3 days Sat 9/16/17 Mon 9/18/17
11 Obtain MSRE Clearance for all equipment 1 day Wed 9/20/17 Wed 9/20/17
12 Attend OE Induction for all project personnel 1 day Wed 9/20/17 Wed 9/20/17
13 Mobilization 25 days Thu 9/21/17 Sun 10/15/17
14 Phase 1 25 days Thu 9/21/17 Sun 10/15/17
15 Mobilization of peresonnel, equipment and materials to 2 days Thu 9/21/17 Fri 9/22/17
site for stringing of dredge pipes and bund wall
16 construction
Site Induction and offloading of pipes 21 days Sat 9/23/17 Fri 10/13/17
17 Stringing and coupling of pipes along the slipway 21 days Sat 9/23/17 Fri 10/13/17
18 Preparation of site by survey group (Marking-out & 2 days Sat 10/14/17 Sun 10/15/17
pegging out dumpsite)
19 Construction of bund wall 4 days Sat 9/30/17 Tue 10/3/17
20 Phase 2 4 days Tue 10/10/17 Fri 10/13/17
21 Mobilization of complete dredging spread 2 days Tue 10/10/17 Wed 10/11/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Escravos Slipway Dock
Summary Manual Summary Rollup Progress
Date: Thu 9/14/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start
3rd Quarter Finish
Mode July August
7/30 8/6 8/13 8/20
22 Perform site orientation training for personnel 2 days Thu 10/12/17 Fri 10/13/17
23 Dredging Works 53 days Sat 10/14/17 Tue 12/5/17
24 Dredging of Escravos Slipway (130000 cubic meter) 45 days Sat 10/14/17 Mon 11/27/17
25 Maintenance of bund wall 2 days Tue 11/28/17 Wed 11/29/17
26 Conduct Post-Dredge Survey 4 days Thu 11/30/17 Sun 12/3/17
27 Site clean-up and restoration activities 2 days Mon 12/4/17 Tue 12/5/17
28 Demobilization 4 days Wed 12/6/17 Sat 12/9/17
29 Demobilization of personnel, equipment and materials 4 days Wed 12/6/17 Sat 12/9/17
from site

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Escravos Slipway Dock
Summary Manual Summary Rollup Progress
Date: Thu 9/14/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
4th Quarter
September October November December
8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/3 12/10 12/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Escravos Slipway Dock
Summary Manual Summary Rollup Progress
Date: Thu 9/14/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
4th Quarter
September October November December
8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/3 12/10 12/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Escravos Slipway Dock
Summary Manual Summary Rollup Progress
Date: Thu 9/14/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4

You might also like