Professional Documents
Culture Documents
Page 1
ID Task Task Name Duration Start
3rd Quarter Finish
Mode July August
7/30 8/6 8/13 8/20
22 Perform site orientation training for personnel 2 days Thu 10/12/17 Fri 10/13/17
23 Dredging Works 53 days Sat 10/14/17 Tue 12/5/17
24 Dredging of Escravos Slipway (130000 cubic meter) 45 days Sat 10/14/17 Mon 11/27/17
25 Maintenance of bund wall 2 days Tue 11/28/17 Wed 11/29/17
26 Conduct Post-Dredge Survey 4 days Thu 11/30/17 Sun 12/3/17
27 Site clean-up and restoration activities 2 days Mon 12/4/17 Tue 12/5/17
28 Demobilization 4 days Wed 12/6/17 Sat 12/9/17
29 Demobilization of personnel, equipment and materials 4 days Wed 12/6/17 Sat 12/9/17
from site
Page 2
4th Quarter
September October November December
8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/3 12/10 12/17
Page 3
4th Quarter
September October November December
8/20 8/27 9/3 9/10 9/17 9/24 10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/3 12/10 12/17
Page 4