You are on page 1of 1

ID Task Name Duration Start Finish

Mar 28, '21 Apr 4, '21 Apr 11, '21 Apr 18, '21
W F S T T S M W F S T T
1 56 days Thu 4/1/21 Thu 6/17/21
2 56 days Thu 4/1/21 Thu 6/17/21
3 Initiating 1 day Thu 4/1/21 Thu 4/1/21
4 Kickoff meeting 1 day Thu 4/1/21 Thu 4/1/21
5 Identify Stakeholders 1 day Thu 4/1/21 Thu 4/1/21
6 Planing 2 days Sun 4/4/21 Mon 4/5/21
7 Communication Plan 2 days Sun 4/4/21 Mon 4/5/21
8 Risk Management Plan 2 days Sun 4/4/21 Mon 4/5/21
9 Quality Management Plan 2 days Sun 4/4/21 Mon 4/5/21
10 Executing 52 days Sun 4/4/21 Mon 6/14/21
11 Delivery 50 days Sun 4/4/21 Thu 6/10/21
12 Replacement 2 switch only 2 days Sun 6/13/21 Mon 6/14/21
13 Monitoring and Control 53 days Thu 4/1/21 Mon 6/14/21
14 Status Report 53 days Thu 4/1/21 Mon 6/14/21
15 Review Meeting 53 days Thu 4/1/21 Mon 6/14/21
16 Monitor Schedule 53 days Thu 4/1/21 Mon 6/14/21
17 Monitor Risk 53 days Thu 4/1/21 Mon 6/14/21
18 Closing 3 days Tue 6/15/21 Thu 6/17/21
19 Knowledge Transfer 3 days Tue 6/15/21 Thu 6/17/21
20 Handover Document 3 days Tue 6/15/21 Thu 6/17/21

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page

You might also like