ID Task Name Duration Start Apr 30, '23 May 7, '23 May 14, '23 May 21, '23

S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 MOBILISATION SCHEDULE 20 days Tue 5/2/23

2 Obtain legal documentation describing site boundary 1 day Tue 5/2/23 5/2 5/2

3 Preparation of Site Layout from Gen Layout 2 days Wed 5/3/23 5/3 5/4

4 Construct/ Set up temporary facilities 4 days Fri 5/5/23 5/5 5/9

5 Procure office facilities 3 days Wed 5/10/23 5/10 5/12

6 Resources deployment 5 days Sat 5/13/23

7 Perosonnel;Site Admin and other Site staff not deployed 2 days Sat 5/13/23 5/13 5/15

8 Equipment; Excavator,Tippers, Concrete Mixer 2 days Sat 5/13/23 5/13 5/15

9 Materials 5 days Sat 5/13/23 5/13 5/18

10 Preparation of Master Work Schedule 2 days Tue 5/16/23 5/16 5/17

11 Design Review and agree on final design with Employer 5 days Tue 5/16/23 5/16 5/20

12 Preconstruction Material Testing 5 days Fri 5/19/23 5/19 5/24

13 Identify Suppliers 1 day Tue 5/16/23 5/16 5/16

14 Notify local Authority intention to commence works 2 days Mon 5/22/23 5/22 5/23

Task Rolled Up Baseline

Progress Rolled Up Baseline Milestone

Baseline Rolled Up Progress

Milestone Split
Project: MOBILISATION SCHEDULE -KUYIANA
Baseline Milestone Baseline Split
WATER DAM Date: Sun 4/2/23
Summary External Tasks

Rolled Up Task Project Summary

Rolled Up Milestone Group By Summary

Baseline Summary Deadline

Page 1