COMMISSIONING OF DEPARTMENTAL STORES IN CANADA

ID Task Name Duration Start Finish Predecessors


January February March April May
E B M E B M E B M E B M E
1 COMMISSIONING OF 60 days Tue 1/2/11 Tue 26/4/11
CHAIN OF
DEPARTMENTAL STORES
IN CANADA
2 Preliminary 5 days Tue 1/2/11 Tue 8/2/11
3 Reasearch Failed & 2 days Tue 1/2/11 Thu 3/2/11
Successful Franchise
in Target Location
4 Visit Successful 3 days Thu 3/2/11 Tue 8/2/11 3
franchise to get first
hand info.
5 Business Analysis 9.88 days Tue 8/2/11 Mon 21/2/11 2
6 Research on Failed & 9 days Tue 8/2/11 Mon 21/2/11 4
Successful Stores in
Target Loaction
7 SWOT Analysis of 9 days Wed 9/2/11 Mon 21/2/11 4
Store Model
8 Determine Range of 9 days Wed 9/2/11 Mon 21/2/11 4
Product & Services
9 Determine Store 9 days Wed 9/2/11 Mon 21/2/11 4
Policies
10 Determine Supplier 9 days Wed 9/2/11 Mon 21/2/11 4
and Vendor Channels

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Store Commissioning Summary Manual Summary Rollup Progress
Date: Sun 31/3/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
COMMISSIONING OF DEPARTMENTAL STORES IN CANADA
ID Task Name Duration Start Finish Predecessors
January February March April May
E B M E B M E B M E B M E
11 Establish Vendor & 9 days Wed 9/2/11 Mon 21/2/11 4
Supplier Relationships

12 Devise Marketing 9 days Wed 9/2/11 Mon 21/2/11 4


Strategy
13 Devise Adertising 9 days Wed 9/2/11 Mon 21/2/11 4
Strategy
14 Research and Know 9 days Wed 9/2/11 Mon 21/2/11 4
Canadian Laws
Regarding Store
Operations
15 Financial Plan 6 days Tue 22/2/11 Tue 1/3/11 5
16 Estimate CAPEX 6 days Tue 22/2/11 Tue 1/3/11 14
17 Estimate OPEX 6 days Tue 22/2/11 Tue 1/3/11 14
18 Estimate Profitability 4 days Tue 22/2/11 Fri 25/2/11 14

19 Work on Sales 2 days Tue 22/2/11 Wed 23/2/11 14


Forecast
20 Determine how to file 2 days Tue 22/2/11 Wed 23/2/11 14
tax return
21 Estimate expected 2 days Tue 22/2/11 Wed 23/2/11 14
Break Even Point
22 Legal 5 days Wed 2/3/11 Tue 8/3/11 15
23 Choose a Unique Legal 1 day Wed 2/3/11 Wed 2/3/11 21
Name in Canada

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Store Commissioning Summary Manual Summary Rollup Progress
Date: Sun 31/3/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
COMMISSIONING OF DEPARTMENTAL STORES IN CANADA
ID Task Name Duration Start Finish Predecessors
January February March April May
E B M E B M E B M E B M E
24 Choose a Legal 1 day Wed 2/3/11 Wed 2/3/11 21
Structure
25 Registration 2 days Wed 2/3/11 Thu 3/3/11 21
26 Registration of Legal 2 days Wed 2/3/11 Thu 3/3/11 21
Entity in Canada
27 Formalization of all 5 days Wed 2/3/11 Tue 8/3/11 21
Legal Process
28 Acquistion of Property 5 days Wed 9/3/11 Tue 15/3/11 15

29 Negotiate with 5 days Wed 9/3/11 Tue 15/3/11 27


Property Owner for 30
yrs lease
30 Negotiate with 4 days Thu 10/3/11 Tue 15/3/11 27
Contractor for
Renovation on Leased
Property
31 Sign Deeds of Lease 5 days Wed 9/3/11 Tue 15/3/11 27
32 Pay For Lease 5 days Wed 9/3/11 Tue 15/3/11 27
33 Preparation for Opening 20 days Wed Tue 12/4/11 28
16/3/11
34 Renovate Leased 20 days Wed Tue 12/4/11 32
Property 16/3/11
35 Install Security, 19 days Thu 17/3/11 Tue 12/4/11 32
Payment and
Communication
System

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Store Commissioning Summary Manual Summary Rollup Progress
Date: Sun 31/3/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
COMMISSIONING OF DEPARTMENTAL STORES IN CANADA
ID Task Name Duration Start Finish Predecessors
January February March April May
E B M E B M E B M E B M E
36 Purchase of Utility 10 days Wed Tue 12/4/11 32
Vechicles 30/3/11
37 Conduct Employment 15 days Wed Tue 12/4/11 32
Process 23/3/11
38 Employ the Best 15 days Wed Tue 12/4/11 32
Hands 23/3/11
39 Placing of orders for 20 days Wed Tue 12/4/11 32
Suppliers 16/3/11
40 Finishing Preparation 19.88 days Wed Tue 12/4/11 32
For Store Furniture 16/3/11
and Accessories

41 Opening of Stores 20 days Wed 13/4/11Tue 10/5/11 33


42 Opening of 7 Stores in 20 days Wed Tue 10/5/11 40
Alberta 13/4/11

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Store Commissioning Summary Manual Summary Rollup Progress
Date: Sun 31/3/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4