PROVISION OF FACILITY AS-BUILT SERVICES

FOR EBOCHA OIL CENTER AND OGBAINBIRI FLOWSTATION


PROPOSED PROJECT SCHEDULE

ID Task Name Duration Start February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023
1 1 PROVISION OF FACILITY AS-BUILT SERVICES FOR EBOCHA OIL 123 days Wed 01/03/23
CENTER AND OGBAINBIRI FLOWSTATION

2 1.1 PROJECT MANAGEMENT 41 days Wed 01/03/23

3 1.1.1 Contract Award 1 day Wed 01/03/23

4 1.1.2 Administrative kick-off meeting 1 day Thu 02/03/23

5 1.1.3 Master Document Register (MDR) 2 days Fri 03/03/23

6 1.1.4 Desktop Review of Existing P&IDs 6 days Tue 07/03/23

7 1.1.5 Report of Desktop Review of Existing P&IDs 5 days Wed 15/03/23

8 1.1.6 Site Visit for Data Acquisition (Ogbainbiri Flow Station and 21 days Wed 22/03/23
Ebocha Oil Center)

9 1.1.7 Prepare and Issue Data Acquisition Report (Ogbainbiri Flow 5 days Thu 20/04/23
Station and Ebocha Oil Center)

10 1.1.8 Monthly / Weekly Progress Report 0 days Wed 01/03/23 01/03

11 1.2 AS-BUILT CAMPAIGN FOR OGBAIBIRI FLOW STATION AND 79 days Thu 27/04/23
EBOCHA OIL CENTER

12 1.2.1 ISSUE FOR REVIEW 60 days Thu 27/04/23

13 1.2.1.1 Updating of P&IDs to As-built Status 60 days Thu 27/04/23

14 1.2.1.2 Line List and piping classes 4 days Mon 08/05/23

15 1.2.1.3 Equipment List 3 days Mon 08/05/23

16 1.2.2 ISSUE FOR APPROVAL (IFA) 14 days Thu 20/07/23

17 1.2.2.1 Issue all deliverables for Approval 14 days Thu 20/07/23

18 1.2.3 APPROVED FOR AS-BUILT (AS-BUILT) 5 days Wed 09/08/23

19 1.2.3.1 Issue all deliverables for As-Built 5 days Wed 09/08/23

20 1.3 PROJECT CLOSE - OUT 3 days Wed 16/08/23

21 1.3.1 Prepare/Issue Project Close Out Report 3 days Wed 16/08/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Progress

Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks