ID Task Task Name Duration Start Finish August 2023 September 2023
Mode 4 7 10 13 16 19 22 25 28 31 3 6 9 12
1 Zimre Lift A Installation 23 days Mon 7/8/23 Wed 6/9/23 0%
2 Platform Installation 2 days Mon 7/8/23 Tue 8/8/23 0%
3 Machine Installation 2 days Wed 9/8/23 Thu 10/8/23 0%
4 Counter Weight Installation
2 days Fri 11/8/23 Mon 14/8/23 0%
5 Roping 2 days Tue 15/8/23 Wed 16/8/23 0%
6 Machine Auto Tune 1 day Thu 17/8/23 Thu 17/8/23 0%
7 Demolitions 2 days Fri 18/8/23 Mon 21/8/23 0%
8 Landing Doors Installation
5 days Fri 18/8/23 Thu 24/8/23 0%
9 Builders Work 2 days Fri 25/8/23 Mon 28/8/23 0%
10 Car Door Installation 1 day Tue 29/8/23 Tue 29/8/23 0%
11 Doors Auto Tuning 1 day Wed 30/8/23Wed 30/8/23 0%
12 Wiring 2 days Wed 30/8/23Thu 31/8/23 0%
13 Speed Run and Testing 2 days Fri 1/9/23 Mon 4/9/23 0%
14 Inspection & Commissioning
2 days Tue 5/9/23 Wed 6/9/23 0%

Critical Finish-only Manual Summary

Critical Split Duration-only Project Summary

Critical Progress Baseline External Tasks

Task Baseline Split External Milestone

Split Baseline Milestone Inactive Task

Task Progress Milestone Inactive Milestone

Manual Task Summary Progress Inactive Summary

Start-only Summary Deadline

Page 1

You might also like