CROWN ENGINEERING NATIONAL PAINT

ID Task Task Name Duration Start Finish % Complete June 2023


Mode 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25
1 FABRICATION & INSTALLATION OF MEZZANINE 261.1m2 30 days Mon 5/15/23 Fri 6/23/23 80%
2 Purchases 5 days Mon 5/15/23 Fri 5/19/23 90%
3 - Purchase of steel materials 5 days Mon 5/15/23 Fri 5/19/23 90%
4 Preparation of site 1 day Mon 5/15/23 Mon 5/15/23 100%
5 - Mobilisation to site and preparation 1 day Mon 5/15/23 Mon 5/15/23 100%
6 Cutting 6 days Tue 5/16/23 Tue 5/23/23 100%
7 - Cutting of Poles and base plates 3 days Tue 5/16/23 Thu 5/18/23 100%
8 - Cutting of Beams (Longitudinal and Tranverse beams) 3 days Fri 5/19/23 Tue 5/23/23 100%
9 Welding 3 days Wed 5/24/23 Fri 5/26/23 90%
10 - Welding of assorted cut peaces (base plates, Gussets, beams & Poles) 3 days Wed 5/24/23 Fri 5/26/23 90%
11 Elevation of structure 13 days Mon 5/29/23 Wed 6/14/23 94%
12 - Erection of Longitudinal frames 4 days Mon 5/29/23 Thu 6/1/23 100%
13 - Erection of Transverse frames 5 days Fri 6/2/23 Thu 6/8/23 100%
14 - Linking and welding of the entire structure 4 days Fri 6/9/23 Wed 6/14/23 80%
15 Wooden Installation 25 days Mon 5/22/23 Fri 6/23/23 54%
16 - Machining 2 days Mon 5/22/23 Tue 5/23/23 70%
17 - Flooring 7 days Thu 6/15/23 Fri 6/23/23 50%
18 Surface Treatment 6 days Thu 6/15/23 Thu 6/22/23 50%
19 - Buffering 3 days Thu 6/15/23 Mon 6/19/23 80%
20 - Painting 3 days Tue 6/20/23 Thu 6/22/23 20%

Task Project Summary Manual Task Start-only Deadline

Project: Project Planning - Mazz Split Inactive Task Duration-only Finish-only Progress
Date: Tue 6/13/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

DONE BY: HANS ASONGWE Page 1 NOTE: WORKING DAYS ONLY