ID Task Task Name Duration Start Finish Predecessors May '23 Jun '23

Mode 01 08 15 22 29 05 12 19 26
1 Soil Investigation 1 day Thu 11-05-23Thu 11-05-23
2 Cleaning of site 2 days Fri 12-05-23 Mon 15-05-231
3 Excavation 5 days Tue 16-05-23 Mon 22-05-232
4 Formwork 6 days Tue 23-05-23 Tue 30-05-23 3
5 Anti termite 5 days Wed 31-05-23Tue 06-06-23 4
6 Bar Bending 3 days Wed 07-06-23Fri 09-06-23 5
7 Erection of bar 1 day Mon 12-06-23Mon 12-06-236
8 Concreting 6 days Tue 13-06-23 Tue 20-06-23 7
9 Removal of formwork2 days Wed 21-06-23Thu 22-06-238
10 Curing 12 days Fri 23-06-23 Mon 10-07-239
11 soil filling 2 days Tue 11-07-23 Wed 12-07-2310
12 Plinth 5 days Thu 13-07-23Wed 19-07-2311
13 Column upto slab 2 days Thu 20-07-23Fri 21-07-23 12
14 Beam formwork 4 days Mon 24-07-23Thu 27-07-2313
15 Slab 6 days Fri 28-07-23 Fri 04-08-23 14
16 Beam Casting 5 days Mon 07-08-23Fri 11-08-23 15
17 Brick work 9 days Mon 14-08-23Thu 24-08-2316
18 Mortal preparation 10 days Fri 25-08-23 Thu 07-09-2317
19 Plastering 8 days Fri 08-09-23 Tue 19-09-23 18
20 Flooring 12 days Wed 20-09-23Thu 05-10-2319
21 Painting 14 days Fri 06-10-23 Wed 25-10-2320
22 M.E.P. 16 days Thu 26-10-23Thu 16-11-2321

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Thu 11-05-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Jul '23 Aug '23 Sep '23 Oct '23 Nov '23
26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Thu 11-05-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

You might also like