ID Task Name Duration Start Finish 30 Jan '22 06 Feb '22

T F S S M T W T F S S M
1 Modular Construction 46 days Thu 27-01-22 Thu 31-03-22
2 Substructure 36 days Thu 27-01-22 Thu 17-03-22
3 Site Clearance 2 days Thu 27-01-22 Fri 28-01-22
4 Lining and Marking 3 days Mon 31-01-22 Wed 02-02-22
5 Excavation 1 day Thu 03-02-22 Thu 03-02-22
6 PCC 1 day Fri 04-02-22 Fri 04-02-22
7 Footings 14 days Mon 07-02-22 Thu 24-02-22
8 Filling 1 day Fri 25-02-22 Fri 25-02-22
9 Plinth Beam 14 days Mon 28-02-22 Thu 17-03-22
10 Module Preparation in Industry16 days Mon 31-01-22 Mon 21-02-22
11 Beams 14 days Mon 31-01-22 Thu 17-02-22
12 Columns 14 days Mon 31-01-22 Thu 17-02-22
13 Slabs 14 days Mon 31-01-22 Thu 17-02-22
14 Walls 14 days Mon 31-01-22 Thu 17-02-22
15 Module alignment 2 days Fri 18-02-22 Mon 21-02-22
16 Module Transportation & Alignment
21 days Tue 22-02-22 Tue 22-03-22
17 Interior Finishing 1 day Tue 22-02-22 Tue 22-02-22
18 Transporting Modules 2 days Fri 18-03-22 Mon 21-03-22
19 Module placement onsite 1 day Tue 22-03-22 Tue 22-03-22
20 After Module Placement 7 days Wed 23-03-22 Thu 31-03-22
21 Flooring 1 day Wed 23-03-22 Wed 23-03-22
22 painting 4 days Wed 23-03-22 Mon 28-03-22
23 HVAC 2 days Tue 29-03-22 Wed 30-03-22
24 Plumbing& Electrical 3 days Wed 23-03-22 Fri 25-03-22
25 Finish works 4 days Mon 28-03-22 Thu 31-03-22
Task Inactive Task Start-only
Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Thu 27-01-22 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 1
06 Feb '22 13 Feb '22 20 Feb '22 27 Feb '22
M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Thu 27-01-22 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 2
06 Mar '22 13 Mar '22 20 Mar '22 27 Mar '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Thu 27-01-22 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 3