ID Task Task Name Duration Start Finish Predecessors March 2022 April 2022 May 2022 June 2022

tart Finish Predecessors March 2022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19
1 Orchid International School 141.5 days 16-03-22 09-08-22
2 Sub Structure 34 days 16-03-22 20-04-22
3 Cleaning & Marking 2 days 16-03-22 17-03-22
4 Excavation Phase 1 6 days 17-03-22 23-03-22 3FS-1 day
5 Excavation Phase 2 5 days 27-03-22 01-04-22
6 Ant termite Treatment Phase 1 1 day 23-03-22 24-03-22 4
7 Ant termite Treatment Phase 2 1 day 27-03-22 28-03-22 4FS+4 days
8 Ant termite Treatment Phase 2 1 day 01-04-22 02-04-22 5
9 PCC Phase 1 2 days 22-03-22 24-03-22 6FS-2 days
10 PCC Phase 2 1.75 days 28-03-22 30-03-22 7
11 PCC Phase 2 0.75 days 02-04-22 02-04-22 8
12 Footing & Column marking Phase 1 1.13 days 23-03-22 24-03-22 9FS-1 day
13 Footing & Column marking Phase 2 1 day 29-03-22 30-03-22 10FS-1 day
14 Footing & Column marking Phase 2 0.88 days 03-04-22 03-04-22 11
15 Steel Reinforcement-Mat/Col pedestal till Plinth Phase 51 days 22-03-22 27-03-22 12FS-2 days
16 Steel Reinforcement-Mat/Col pedestal till Plinth Phase 42 days 29-03-22 02-04-22 13FS-1 day
17 Steel Reinforcement Phase 2 5 days 04-04-22 09-04-22 14
18 Shuttering Phase 1 5 days 25-03-22 30-03-22 15FS-2 days
19 Shuttering Phase 2 3 days 31-03-22 03-04-22 16FS-2 days
20 Shuttering Phase 2 2 days 08-04-22 09-04-22 17
21 Footing Concrete Phase 1 5 days 28-03-22 02-04-22 18FS-2 days
22 Footing Concrete Phase 2 3 days 01-04-22 04-04-22 19FS-2 days
23 Footing Concrete Phase 2 1.13 days 10-04-22 10-04-22 20
24 Marking for Column Pedestal & Shuttering phase 1 1 day 02-04-22 03-04-22 21
25 Starter for columns 1.13 days 02-04-22 03-04-22 24FS-1 day
26 Marking for Column Pedestal & Shuttering Phase 2 1 day 11-04-22 11-04-22 23
27 Shuttering for Column Pedestal Phase 1 1 day 04-04-22 04-04-22 25
28 Shuttering for Column Pedestal Phase 2 2 days 12-04-22 13-04-22 26
29 Concreting for Column Pedestal Phase 1 1 day 05-04-22 05-04-22 27
30 Concreting for Column Pedestal Phase 2 1 day 14-04-22 14-04-22 28
31 Pedestal Concrete Phase 2 1 day 15-04-22 15-04-22 30
32 Marking for Column Pedestal & Shuttering phase 2 1 day 06-04-22 06-04-22 29
33 Shuttering for Column Pedestal Phase 2 1 day 07-04-22 07-04-22 32
34 1 Lift Deshuttering & refixing of Phase 2 1 day 16-04-22 16-04-22 31
35 Concreting for Column Pedastal Phase 1 & Phase 2 2 days 08-04-22 09-04-22 33
Strap beam
36 Concreting for Column Pedastal Phase 2 1.13 days 17-04-22 17-04-22 34
37 2 nd lift Deshuttering & refixing of Phase 2 1.13 days 18-04-22 19-04-22 36
38 Concreting for Column Pedastal Phase 2 1 day 19-04-22 20-04-22 37
39 Random Rubble Masonry 4 days 08-04-22 12-04-22 35FS-2 days
40 Shuttering for Plinth beam 4 days 10-04-22 14-04-22 39FS-2 days

Task Project Summary Manual Task Start-only Deadline

Project: Orchid schedule option Split Inactive Task Duration-only Finish-only Progress
Date: 17-03-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors March 2022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19
41 Column lapping -TMT 2 days 13-04-22 15-04-22 40FS-1 day
42 Steel Reinforcement for Plinth beam 3 days 14-04-22 17-04-22 41FS-1 day
43 Concreting for Plinth beam 0.75 days 17-04-22 18-04-22 42
44 Refilling Compaction & Consolidation & PCC 4 days 16-04-22 20-04-22 43FS-2 days
45 Super Structure 107.5 days 20-04-22 09-08-22
46 Column starter marking 1 day 20-04-22 21-04-22 44
47 Column Shuttering 1 day 21-04-22 22-04-22 46
48 Column concreting 2 days 22-04-22 24-04-22 47
49 Shuttering work GF Roof slab & Staircase 5 days 24-04-22 29-04-22 48
50 Reinforcement for beam & slab & Staircase 4 days 28-04-22 02-05-22 49FS-1 day
51 Electrical Conduiting 1 day 02-05-22 03-05-22 50
52 GF Staircase Roof Concreting beam & slab 0.5 days 03-05-22 04-05-22 51
53 Starter for columns 1 day 04-05-22 05-05-22 52
54 Column Shuttering on FF 1 day 05-05-22 06-05-22 53
55 Column concreting 2 days 06-05-22 08-05-22 54
56 Shuttering work FF Roof slab & Staircase 5 days 08-05-22 13-05-22 55
57 Reinforcement for beam & slab 4 days 12-05-22 16-05-22 56FS-1 day
58 Electrical Conduiting 1 day 15-05-22 16-05-22 57FS-1 day
59 FF Staircase Roof Concreting beam & slab 0.5 days 16-05-22 17-05-22 58
60 Starter for columns 1 day 17-05-22 18-05-22 59
61 Column Shuttering 1 day 18-05-22 19-05-22 60
62 Column concreting 2 days 19-05-22 21-05-22 61
63 Shuttering work Roof slab 5 days 20-05-22 25-05-22 62FS-1 day
64 Reinforcement for beam & slab 4 days 24-05-22 28-05-22 63FS-1 day
65 Electrical Conduiting 1 day 28-05-22 29-05-22 64
66 SF Staircase, Roof Concreting beam & slab 0.5 days 29-05-22 30-05-22 65
67 Starter for columns 1 day 30-05-22 31-05-22 66
68 Column Shuttering 1 day 31-05-22 01-06-22 67
69 Column concreting 2 days 01-06-22 03-06-22 68
70 Shuttering work Roof slab 5 days 03-06-22 08-06-22 69
71 Reinforcement for beam & slab 4 days 07-06-22 11-06-22 70FS-1 day
72 Electrical Conduiting 1 day 11-06-22 12-06-22 71
73 TF Staircase Roof Concreting beam & slab 1 day 12-06-22 13-06-22 72
74 Curing of slab by making bunds 1 day 13-06-22 14-06-22 73
75 Starter for columns 1 day 14-06-22 15-06-22 74
76 Column Shuttering 1 day 15-06-22 16-06-22 75
77 Column concreting 2 days 16-06-22 18-06-22 76
78 Shuttering work Roof slab 2 days 18-06-22 20-06-22 77
79 Reinforcement for beam & slab 1 day 21-06-22 21-06-22 78
80 Electrical Conduiting 1 day 22-06-22 22-06-22 79
81 TF Staircase Head Room Roof Concreting beam & slab1 day 23-06-22 23-06-22 80

Task Project Summary Manual Task Start-only Deadline

Project: Orchid schedule option Split Inactive Task Duration-only Finish-only Progress
Date: 17-03-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Predecessors March 2022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19
82 Curing of slab by making bunds 1 day 24-06-22 24-06-22 81
83 GF Floor detailing
84 Block Masonry upto sil level 4 days 24-05-22 28-05-22 59FS+7 days
85 Upto Lintel level 4 days 28-05-22 01-06-22 84
86 Lintel Shuttering 2 days 01-06-22 03-06-22 85
87 Reinforcement Lintel 2 days 03-06-22 05-06-22 86
88 Concreting Lintel 1 day 06-06-22 06-06-22 87
89 3rd lift till beam & slab bottom 1 day 07-06-22 07-06-22 88
90 Window Grills, Door frame & Ventilators grills 4 days 08-06-22 11-06-22 89
91 Water proofing in toilets 2 days 01-06-22 03-06-22 85
92 Plastering
93 Internal walls 10 days 06-06-22 16-06-22 89FS-2 days
94 Rough plastering -Toilets 4 days 14-06-22 18-06-22 93FS-2 days
95 Tiling Work
96 Daddoing 4 days 18-06-22 22-06-22 94
97 Anti skid 4 days 22-06-22 26-06-22 96
98 Vitrified 7 days 24-06-22 01-07-22 97FS-2 days
99 Skirting 4 days 01-07-22 05-07-22 98
100 Painting
101 Putty 4 days 16-06-22 20-06-22 93
102 1st coat Internal painting 4 days 20-06-22 24-06-22 101
103 2nd coat internal painting 3 days 24-06-22 27-06-22 102
104 UPVC Windows & Ventilators 3 days 24-06-22 27-06-22 102
105 Wooden shutters 5.75 days 27-06-22 03-07-22 103
106 FF Floor detailing
107 Block Masonry upto sil level 4 days 06-06-22 10-06-22 68FS+5 days
108 Upto Lintel level 4 days 09-06-22 13-06-22 107FS-1 day
109 Lintel Shuttering 2 days 12-06-22 14-06-22 108FS-1 day
110 Reinforcement Lintel 2 days 14-06-22 16-06-22 109
111 Concreting Lintel 1 day 16-06-22 17-06-22 110
112 3rd lift till beam & slab bottom 1 day 17-06-22 18-06-22 111
113 Window Grills, Door frame & Ventilators grills 4 days 18-06-22 22-06-22 112
114 Water proofing in toilets 2 days 18-06-22 20-06-22 112
115 Plastering
116 Internal walls 8 days 20-06-22 28-06-22 114FS-1 day
117 Rough plastering -Toilets 4 days 28-06-22 02-07-22 116
118 Tiling Work
119 Daddoing 4 days 02-07-22 06-07-22 117
120 Anti skid 4 days 06-07-22 10-07-22 119
121 Vitrified 6 days 05-07-22 11-07-22 119FS-1 day
122 Skirting 4 days 10-07-22 14-07-22 120

Task Project Summary Manual Task Start-only Deadline

Project: Orchid schedule option Split Inactive Task Duration-only Finish-only Progress
Date: 17-03-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
ID Task Task Name Duration Start Finish Predecessors March 2022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19
123 Painting
124 Putty 4 days 21-06-22 24-06-22 114
125 1st coat Internal painting 4 days 25-06-22 29-06-22 124
126 2nd coat internal painting 3 days 29-06-22 02-07-22 125
127 UPVC Windows & Ventilators 3 days 21-06-22 23-06-22 114
128 Wooden shutters 5 days 25-06-22 30-06-22 124
129 SF Floor detailing
130 Block Masonry upto sil level 4 days 18-06-22 22-06-22 73FS+5 days
131 Upto Lintel level 4 days 23-06-22 27-06-22 130
132 Lintel Shuttering 2 days 27-06-22 29-06-22 131
133 Reinforcement Lintel 2 days 29-06-22 01-07-22 132
134 Concreting Lintel 1 day 01-07-22 02-07-22 133
135 3rd lift till beam & slab bottom 1 day 02-07-22 03-07-22 134
136 Window Grills, Door frame & Ventilators grills 4 days 03-07-22 07-07-22 135
137 Water proofing in toilets 2 days 07-07-22 09-07-22 136
138 Plastering
139 Internal walls & Ceiling 10 days 01-07-22 11-07-22 135FS-2 days
140 Rough plastering -Toilets 4 days 03-07-22 07-07-22 135
141 Tiling Work
142 Daddoing 4 days 10-07-22 14-07-22 139FS-1 day
143 Anti skid 4 days 14-07-22 18-07-22 142
144 Vitrified 7 days 11-07-22 18-07-22 139
145 Skirting 4 days 19-07-22 22-07-22 144
146 Painting
147 Putty 4 days 10-07-22 14-07-22 139FS-1 day
148 1st coat Internal painting 4 days 14-07-22 18-07-22 147
149 2nd coat internal painting 3 days 19-07-22 21-07-22 148
150 UPVC Windows & Ventilators 3 days 19-07-22 21-07-22 148
151 Wooden shutters 5.75 days 19-07-22 24-07-22 148
152 TF Terrace Head Room
153 Block Masonry upto sil level +Parapet Wall 3 days 10-07-22 13-07-22 82FS+15 days
154 Upto Lintel level for Staircase Head room 3 days 13-07-22 16-07-22 153
155 Lintel Shuttering 2 days 16-07-22 18-07-22 154
156 Reinforcement Lintel 2 days 19-07-22 20-07-22 155
157 Concreting Lintel 1 day 21-07-22 21-07-22 156
158 3rd lift till beam & slab bottom 1 day 22-07-22 22-07-22 157
159 Window Door & Ventilators 2 days 23-07-22 25-07-22 158
160 Water proofing 2 days 19-07-22 20-07-22 155
161 Plastering
162 Internal walls & Ceiling 7 days 21-07-22 28-07-22 157FS-1 day
163 Rough plastering 3 days 28-07-22 31-07-22 162

Task Project Summary Manual Task Start-only Deadline

Project: Orchid schedule option Split Inactive Task Duration-only Finish-only Progress
Date: 17-03-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
ID Task Task Name Duration Start Finish Predecessors March 2022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19
164 Tiling Work
165 Daddoing 4 days 26-07-22 30-07-22 162FS-2 days
166 Anti skid 2 days 30-07-22 01-08-22 163FS-1 day
167 Vitrified 5 days 29-07-22 03-08-22 163FS-2 days
168 Skirting 3 days 01-08-22 04-08-22 167FS-2 days
169 Painting
170 Putty 3 days 27-07-22 30-07-22 162FS-1 day
171 1st coat Internal painting 4 days 29-07-22 02-08-22 170FS-1 day
172 2nd coat internal painting 2 days 02-08-22 04-08-22 171
173 Outside Plastering
174 TF+SF+FF+GF 10 days 12-07-22 22-07-22 153FS-1 day
175 Ouside Painting
176 TF+SF+FF+GF 6 days 21-07-22 27-07-22 174FS-2 days
177 HO & TO 5 days 04-08-22 09-08-22 172
178 * Note:- We have taken Deshuttering of Slab/Beam on
21st day [For spans more than 6m -21days removal of
props].
179 Considering the start date as 16.03.2022.

Task Project Summary Manual Task Start-only Deadline

Project: Orchid schedule option Split Inactive Task Duration-only Finish-only Progress
Date: 17-03-22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone