ID Task Name Duration Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24

19 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12
0 Activity schedule and work plan 135 days
1 1 PRELIMINARIES 15 days
2 1.1 Contract signing 1 day
3 1.2 Site mobilisation 14 days
4 1.3 Site Preparations 14 days
5 2 SOURCE 26 days
6 2.1 Site clearance 3 days
7 2.2 Earthworks 3 days
8 2.3 Retaining wall 10 days
9 2.4 Reservoir / sump at pump station 10 days
10 2.4.1 Concrete works 2 days
11 2.4.2 Formwork 3 days
12 2.4.3 Reinforcement 3 days
13 2.4.4 Catchment protection 2 days
14 3 SUMP 23 days
15 3.1 Site clearance 3 days
16 3.2 Earthworks 2 days
17 3.3 Retaining wall 10 days
18 3.4 Reservoir / sump at pump station 8 days
19 3.4.1 Concrete works 2 days
20 3.4.2 Formwork 3 days
21 3.4.3 Reinforcement 3 days
22 4 PUMP STATION 30 days
23 4.1 Site clearance 3 days
24 4.2 Earthworks 2 days
25 4.3 Construction of Guard and pump house 3 wks
26 4.4 Walkways 5 days
27 4.5 Fence 1 wk
28 4.6 Gate 2 days
29 4.7 Site landscapping 3 days
30 5 TRANSMISSION MAINS 38 days
31 5.1 Site clearance 5 days
32 5.2 Earthworks 4 wks
33 5.3 Pipes 5 days
34 5.4 Pipework-Fittings & Valves 10 days
35 5.5 Pipework-Manholes & Pipework ancillaries 3 days
36 5.6 Road Reinstatement 3 days
37 5.7 Other pipework Ancillries 5 days
38 5.8 Marker posts 1 day
39 6 RESERVOIR 33 days
40 6.1 Site Clearance 2 days
41 6.2 Earthworks 3 days
42 6.3 Insitu Concrete 3 days
43 6.4 Pipework-Fittings & Valves 3 days
44 6.5 Pipework-Supports & Protections 3 days
45 6.6 Supply and instalation of elevated tank 1 mon
46 6.7 Walk ways 3 days
47 6.8 Fence 3 days
48 6.9 Compound levelling 1 day
49 7 DISTRIBUTION NETWORK 37 days
50 7.1 Demolition & Site clearance 3 days
51 7.2 Excavation, pipelaying and back filling 6 wks
52 7.3 Service connections 5 days
53 7.4 Public stand posts 2 days
54 7.5 Pipework fittings 2 wks
55 7.6 Valves and penstocks 2 days
56 7.7 Pipework-Manholes & Pipework ancillaries 2 days
57 7.8 Road Reinstatement 3 days
58 7.9 Other pipework Ancillries 2 days
59 7.10 Marker posts 1 day
60 8 ELECTRO-MECHANICAL INSTALLATIONS 11 days
61 8.1 Installation of pump and Photovaltaic 4 days
equipment & Accessories
62 8.2 Wiring 2 days
63 8.3 Construction of solar panel farm 1 wk
64 8.4 Earthing and Lightning protection 2 days
65 8.5 Installation of Alarm protection system 2 days
66 9 PROJECT CLOSURE 1 day
67 9.1 Commissioning 1 day
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Activity schedule and w
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 07/03/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Activity schedule and w
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 07/03/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress