WORK SCHEDULE

TENDER FOR DESIGN FABRICATION TESTING AND COMMISSIONING OF LIFTING BEAN AT TANA POWER STATION

ID Task Task Name Duration Start Finish


Mode

1 PROJECT TIMELINE 15 days 0


2 EXECUTION PROCEDURES 11 days 1
3 Offsite Works 3 days 0
4 Fabrication of parts from 10mm plate 2days 0
5 Mobilization to site 1 days 2
6 Onsite Works 8 days 3
7 Site meeting and set-up 1 days 0
8 Fitting of stifners plates and welding 2 days 1
9 fitting of stiffners beam and welding 2 days 2
10 fitting hooks stoppers and wheels 1 days 1
11 cleaning and paintworks 2 days
12 PROJECT TERMINATION 4 days 1
13 Inspection of works with client 1 days 0
14 Attendance to snaglist 1 days 1
15 testing and commissioning 1 days 3
16 Clear from site 1 days 2

Labour input 1 welder 1 fitter 2 helpers and painter.


WORK SCHEDULE

TENDER FOR PENSTOCK AND POWERHOUSE ACCESS ANCHORAGE AND CONSTRUCTION OF SENTRY HOUSES AT
KIAMBELE POWER STATION.

ID Task Task Name Duration Start Finish


Mode

1 PROJECT TIMELINE 114 days 21/6/23 24/11/23 156


2 PRELIMINARIES 12 days 21/6/23 6/7/23 15
3 Contractual Matters 12 days 21/6/23 6/7/23 15
4 Tender Evaluation and Award 3 days 21/6/23 24/6/23 3
5 Processing and presentation of performance bond 6 days 24/6/23 30/6/23 6
6 Signing of contract 1 days 1/7/23 2/7/23 1
7 Publication of procurement contract 1 days 3/7/23 4/7/23 1
8 Site handover meeting 1 days 5/7/23 6/7/23 1
9 EXECUTION PROCEDURES 95 days 6/7/23 14/11/23 131
10 Offsite activities 27 days 6/7/23 8/8/23 33
11 Presentation of Method statement, Work plan and project for approval. 1 days 6/7/23 8/7/23 2
12 Presentation of equipment licences and inspection certificates 1 days 9/7/23 11/7/23 2
13 Presentation of material samples for approval by the engineer. 2 days 11/7/23 13/7/23 2
14 Supply of prefabricated duct parts and accessories. 10 days 14/7/23 24/7/23 10
15 Supply of new stainless steel anchor and their associated materials 2 days 25/7/23 27/7/23 1
16 Supply of prefabricated windows and doors 5 days 27/7/23 2/8/23 2
17 Supply of electrical components and equipment 1 days 2/8/23 3/8/23 1
18 Mobilization of resources. 5 days 3/8/23 8/8/23 1
19 ONSITE-WORK ACTIVITIES 68 days 9/8/23 14/11/23 3
20 SITE SET-UP. 6 days 9/8/23 17/8/23 1
21 Site take over and planning meeting 1 days 9/8/23 10/8/23 2
22 Approval of work methodology and work plan 1 days 11/8/23 12/8/23 1
23 Hoarding of the site. 2 days 12/8/23 14/8/23 1
24 Setting up of site office and store. 2 days 15/8/23 17/8/23 8
25 ROCK ANCHORAGE WORKS. 20 days 17/8/23 17/9/23 1
26 Setting up of the scaffolding and access point to higher levels. 2 days 17/8/23 19/8/23 1
27 Clearing of vegetations,shrubs and loose rocks around the area. 4 days 20/8/23 24/8/23 1
28 Drilling of holes not less than 1.5m on the rock. 3 days 25/8/23 28/8/23 1
29 Installation of rock anchors, fasteners and accessories. 3 days 1/9/23 4/9/23 3
30 Installation of hexagonal woven wire mesh as specified by the client. 3 days 4/9/23 7/9/23 1
31 Pumping of concrete slurry on the vertical section of the wall. 2 days 9/9/23 11/9/23 8
32 Carry out the curing process of the pumped concrete to avoid cracking and
1 days 12/9/23 13/9/23 2
increase its strength and durability.
33 Removal of scaffoldings and other demolitions. 3 days 13/9/23 17/9/23 1
34 CONSTRUCTION ON SENTRY HOUSE 26 days 17/9/23 23/10/23 1
35 Setting out levels and lines for excavation. 1 days 18/9/23 19/9/23 2
36 Removal of topmost vegetation soil and cart way to designated area. 1 days 19/9/23 20/9/23 4
37 Excavation works upon the required depth as specified by the engineer. 2 days 22/9/23 22/9/23 3
38 Carry out blinding works to level the excavated trenches. 2 days 22/9/23 24/9/23 1
39 Setting up of sub-structural wall using quarry natural stones. 2 days 24/9/23 26/9/23 1
40 Backfilling of the trenches and compacting in layers using hardcore. 1 days 26/9/23 27/9/23 1
41 Carrying out anti-termite treatment as approved by professional pest
1 days 28/9/23 29/9/23 1
control specialist.
42 Laying of gauge 1000 damp proof polythene membrane. 1 days 30/9/23 1/10/23 1
43 Laying of the BRC wire on the prepared floor. 1 days 2/10/23 3/10/23 1
44 Setting up of super structural wall using 200mm thick machine cut stones. 4 days 3/10/23 7/10/23 3
45 Casting of the reinforced concrete rig beam. 1 days 8/10/23 9/10/23
46 Electing of the previously fabricated trusses. 1 days 10/10/23 11/10/23
47 Putting up of steel purlins 100mm by 50 mm embedded in masonry wall. 2 days 12/10/23 14/10/23
48 Installation of roofing sheets facial boards windows and doors. 2 days 15/10/23 17/10/23
49 Carrying out internal finishes, plasters and paint works. 3 days 18/10/23 21/10/23
50 Inspection of works with the engineer. 1 days 22/10/23 23/10/23
51 DUCT ANCHORAGE AND REPAIRS. 16days 23/10/23 14/11/23
52 Removal of damaged ducting materials from the existing system 3 days 23/10/23 26/10/23
53 Carting away of the removed damaged ducts as directed by the client. 1 days 27/10/23 28/10/23
54 Replacing the removed ducting materials with the newly supplied materials. 3 days 28/10/23 1/11/23
55 Re-anchoring of the entire existing ducting system. 4 days 2/11/23 6/11/23
56 Removal of the old existing fans with their corresponding silencers. 2 days 7/11/23 9/11/23
57 Installation of new fans and silencers of similar rating as existing ones. 2 days 10/11/23 12/11/23
58 Inspection of works with the engineer. 1 days 13/11/23 14/11/23
59 PROJECT TERMINATION 7days 14/11/23 24/11/23 1
60 Inspection of works with client 1 days 14/11/23 15/11/23
61 Attendance to snaglist 2 days 16/11/23 18/11/23 2
62 Handing over works to client 1 days 19/11/23 20/11/23 1
63 Prepare and present As-built Drawings 2 days 21/11/23 23/11/23
64 Clear from site 1 days 23/11/23 24/11/23

Project: TENDER FOR PENSTOCK AND Automatically Scheduled


POWERHOUSE ACCESS
ANCHORAGE AND CONSTRUCTION
OF SENTRY HOUSES AT KIAMBELE
POWER STATION.
Manually Scheduled

Date: 21/06/2023
WORK SCHEDULE
REMAINING WORKS FOR PROPOSED ERECTION OF CAR SHED AT EASA
1D Task Name Duration Start Finish
PROJECT TIMELINE 90days 11/10/22 09/01/23 90
A EXECUTION PROCEDURE
1 Offsite Works 39days 11/10/22 19/11/22
2 Procurement of materials 8days 11/10/22 19/10/22 8
3 Fabrication of stanchions on base plates and stiffened as per
Engineer's detailing 6days 19/10/22 25/10/22
6
4 Fabrication of canopy shed structure 8days 25/10/22 02/11/22 8
5 Surface preparation of structural steel prior paint works 10days 02/11/22 12/11/22 10
6 Paint Works in the approved DFT and color 12days 03/11/22 15/11/22 12
7 Inspection of works 1day 15/11/22 16/11/22 1
8 Mobilization of resources to site 3days 16/11/22 19/11/22 3
9 Onsite Works 43days 20/11/22 02/01/23
10 Welding and assembly of cantilever trusses on column 3days 20/11/22 23/11/22 3
11 Erection of trusses & columns and securing them on RC stub 4days 23/11/22 27/11/22 4
12 column
Reassembly, fitting and welding of the canopy members to form
the canopy shed structure 7days 27/11/22 04/12/22
7
13 Lifting & fitting of canopies and assembly on the erect column-
truss structure 6days 04/12/22 10/12/22
6
14 Welding of the car shed structure to rigidity as approved by the 3days 10/12/22 13/12/22
Engineer 3
15 Surface Preparation: Wire brushing and chipping out of slugs on 2days 13/12/22 15/12/22
welds 2
16 Paint work touch ups on welded joints 3days 15/12/22 18/12/22 3
17 Car shed fabric netting as approved 14days 18/12/22 01/01/23 14
18 Inspection of Works 1day 01/01/23 02/01/23 1
B PROJECT TERMINATION 7days 02/01/23 09/01/23
19 Inspection of works with the Client 1day 02/01/23 03/01/23 1
20 Attendance to snaglist 2days 02/01/23 04/01/23 2
21 Handover works 1day 04/01/23 05/01/23 1
22 Prepare as-built drawings 3days 05/01/23 08/01/23 3
23 Clear from Site 1day 08/01/23 09/01/23 1
WORK SCHEDULE

TENDER FOR SUPPLY &DELIVARY OF 20"SPIRAL WELDED STEEL PIPES FOR BARINGO SILALI GEOTHERMAL
PROJECT. ITT NO. GDC/INFRA/OT/062/2022:2023

ID Task Mode Task Name Duration Start Finish

1 PROJECT TIMELINE 106 days 27/6/23 23/10/23 106


2 PRELIMINARIES 101 days 27/6/23 18/10/23 12
3 Contractual Matters 12 days 27/6/23 13/7/23 12
4 Tender Evaluation and Award 3 days 27/6/23 30/6/23 3
5 Processing and presentation of performance bond 6 days 1/7/23 7/7/23 6
6 Signing of contract 1 days 8/7/23 9/7/23 1
7 Publication of procurement contract 1 days 10/7/23 11/7/23 1
8 Site handover meeting 1 days 12/7/23 13/7/23 1
9 EXECUTION PROCEDURES 89 days 13/7/23 4/2/24 89
10 Offsite Works 89 days 13/7/23 18/10/23 89
11 Presentation of Work plan and project drawings for approval. 2 days 13/7/23 15/7/23 2
12 Presentation of equipment licences and inspection certificates 2 days 16/7/23 18/7/23 2
13 Presentation of pipe sample to the client. 3 days 19/7/23 22/7/23 3
14 Presentation of test sample results to the client. 1 days 23/7/23 24/7/23 1
15 Procurement of fabrication material 1 days 25/7/23 26/7/23 1
16 Fabrication of spiral pipes. 60 days 27/7/23 25/9/23 60
17 Surface preparation and paintworks 7 days 26/9/23 3/10/23 7
18 Mobilization of resources to site. 3 days 3/10/23 6/10/23 3
19 Supply of the steel welded spiral pipes to site 10 days 7/10/23 18/10/23 10
20 PROJECT TERMINATION 5 days 18/10/23 23/10/23 5
21 Inspection of works with client 1 days 18/10/23 19/10/23 1
22 Handing over works to client 1 days 20/10/23 21/10/23 1
23 Prepare and present As-built Drawings 2 days 20/10/23 22/10/23 2
24 Clear from site 1 days 22/10/23 23/10/23 1

TENDER FOR SUPPLY


&DELIVARY OF 20"SPIRAL
Project: WELDED STEEL PIPES Automatically Scheduled

Manually Scheduled
Date: 27/06/23
WORK SCHEDULE

TENDER FOR INSTALLATION AND COMMISIONING OF 20T EOT CRANE


SNSC/061/2022-2023

ID TASK NAME DURATION START


1 Pre-assembly. 3 DAYS
Barricading of the working area
Assessment of the individual components
Identification of disassembly of parts.
Sorting out components for various color codes
Greasing and servicing of the moving parts and motors
2 Equipment and components. 8 DAYS
Mobilization of working equipment and human labour
Sandblasting of the garders, the two halves for each side
Sandblasting of the two end carriages
Sandblasting of the wire rope drums and shelves
Sandblasting of the grab frame and grabbing teeth
Painting the cleaned components
3 Assembling 8 DAYS
Trial assembly of the girders to the end controllers
Greasing of the main gantry moving rail.
Assembly of the hydraulic power pack
Assembly of the grab teeth to the power pack
Lifting of the individual components
4 Electrical connection 3 DAYS
5 Testing and commissioning 2 DAYS
6 Removal of the scrap materials and general site clean-up. 2DAYS
FINISH
3
1
1
2
1
1
8
1
1
1
1
1
3
8
2
1
1
2
4
3
2
2
TENDER FOR SUPPLY AND DELIVARY OF ASSORTED KITCHEN EQUIPMENT FOR EASA TENDER(ITT) NO.KCAA/031/2022-2023
ID NAMES DURATION START DATE FINAL DATE
PROJECT TIMELINE 90 3-Jan-23 04-Mar-23
CONTRACTUAL MATTERS 12 3-Jan-23 15-Jan-23
Tender evaluation and award
Processing and presentation of performance bond
Signing of contract
Publication of procument contract
EQUIPMENTS 78 15-Jan-23 04-Mar-23
1 Electric industial 4 decker oven 1810*1130*2270mm
2 20 Ltrs double well-deep flier
3 Bone cutter 1650mm
4 20Kg potato peeler
5 Chips cutter with 4 blade
6 Plate warmer 450*485*770
7 Kitchen trolleys 3 tier flat shelves stainless steel
8 Meat micer 150kg/h
9 Deep freezer 80Ltrs
10 Water dispenser
11 Salad displaycounter with hood
12 Dish waser hood type 50*50 backets 1000 plates per hour
13 Dough mixer 22 ltrs
14 Coffee maker machine
15 Bein marie complete with sneeze guard 2200*700*850
16 Dough sheeter
17 Stainless ateel worktable
18 Replacement of the kitchen burners/boiler
19 Single trolley 64 trays proofer cabinet fermentation room dough prover
20 Dual compartment refrigerated juice dispenser
21 Table top electric oven commercial
22 Commercial microwaves
23 Fridge single door and double door 420L
24 Commercial charcoal jiko
25 Commercial charcoal grill
26 Medium sufurials
27 Commercial toaster
28 Measuring scale
29 Lamp chandeliers
30 Wooden menu stand
31 Table menu stand
32 Pest control appliances
33 Commercial waffie crepe machine
34 Modern chafing dishes 10ltrs electric chef set chafing dish heater with glass
35 Plastic inserts
36 Kitchen racks 4 tier
WORK SCHEDULE

TENDER FOR CONSTRUCTION OF THR PROPOSED STAFF CAR PARKING AND PEDESTRIAN SHADE IN THE UNHCR
COMPOUND-KAKUMA; TURKANA COUNTY REF NO. RFP/SC/KAK/2022/010/SL

ID Task Task Name Duration Start Finish


Mode

1 PROJECT TIMELINE 60 days 12/8/22 12/2/23 60


2 PRELIMINARIES 12 days 28/11/22 13/12/22 12
3 Contractual Matters 12 days 28/11/22 13/12/22 12
4 Tender Evaluation and Award 2 days 28/11/22 30/11/22 2
5 Processing and presentation of performance bond 6 days 1/12/22 7/12/22 6
6 Signing of contract 1 days 8/12/22 9/12/22 1
7 Publication of procurement contract 1 days 10/12/22 11/12/22 1
8 Site handover meeting 1 days 12/12/22 13/12/22 1
9 EXECUTION PROCEDURES 40 days 13/12/22 6/2/23 40
10 Offsite Works 22 days 13/12/22 4/1/23 22
11 Presentation of Method Statement and Work Program for approval by the 2 days 13/12/22 15/12/22 2
Engineer
12 Presentation of Job safety analysis for Engineer’s approval. 2 days 13/12/22 15/12/22 2
13 Presentation of material samples for approval. 1 days 16/12/22 17/12/22 1
14 Procurement of materials. 1 days 17/12/22 18/12/22 1
15 Fabrication of steel columns, trusses purlins and gutter 5 days 17/12/22 22/12/22 5
16 Carry out surface preparation prior paint works 7 days 27/12/22 3/1/23 7
17 Carry out paintworks in the required DFT and layers and ensure finish in 7 days 27/12/22 3/1/23 7
uniform application.
18 Mobilization of resources to site i.e. labour, material, tools and machinery. 2 days 2/1/23 4/1/23 2
19 Onsite Works 33 days 4/1/23 6/2/23 33
20 Site setup 4 days 4/1/23 8/1/23 4
21 Site take over and planning meeting 2 days 4/1/23 6/1/23 2
22 Approval of work methodology and work plan 2 days 4/1/23 6/1/23 2
23 Hoarding of the site & Installation of warning boards. 2 days 5/1/23 7/1/23 2
24 Setting up a site office 1 days 7/1/23 8/1/23 1
25 Civil works 19 days 5/1/23 24/1/23 19
26
Clearing and sripping of surface 3 days 5/1/23 8/1/23 3
27 Excavation works 7 days 8/1/23 15/1/23 7
28 Fabrication and installation of reiforcing steel for colums 7 days 8/1/23 15/1/23 7
29 colum footing and setting of studs 4 days 13/1/23 17/1/23 4
30 columns formwork and casting 3 days 16/1/23 19/1/23 3
31 Backfilling and compacting 4 days 19/1/23 23/1/23 4
32 Inspection of works. 1 days 23/1/23 24/1/23 1
33 Super-structural works 13 days 24/1/23 6/2/23 13
34 Installation of steel colums 4 days 24/1/23 28/1/23 4
35 Installation of prefabricated truss 3 days 28/1/23 31/1/23 3
36 Instalation of prefabricated purlin and brazings 1 days 31/1/23 1/2/23 1
37 Gutter installations 1 days 1/2/23 2/2/23 1
38 Install weldon gutter end caps 2 days 2/2/23 4/2/23 2
39 Cut on gutters and Install drop outlets. 1 days 2/2/23 3/2/23 1
40 Install downpipes 1 days 3/2/23 4/2/23 1
41 Cleaning of surface and final paint work 2 days 3/2/23 5/2/23 2
42 Inspection of works 1 days 5/2/23 6/2/23 1
43 PROJECT TERMINATION 6 days 6/2/23 12/2/23 6
44 Inspection of works with client 1 days 6/2/23 7/2/23 1
45 Attendance to snaglist 3 days 6/2/23 9/2/23 3
46 Handing over works to client 1 days 9/2/23 10/2/23 1
47 Prepare and present As-built Drawings 2 days 9/2/23 11/2/23 2
48 Clear from site 1 days 11/2/23 12/2/23 1

Project: TENDER FOR CONSTRUCTION OF THR PROPOSED STAFF CAR Automatically Scheduled
PARKING AND PEDESTRIAN SHADE IN THE UNHCR COMPOUND-
KAKUMA; TURKANA COUNTY REF NO. RFP/SC/KAK/2022/010/SL
Date: 01/08/23
BOREHOLE EQUIPING AND CONSTRUCTION OF GALVANIZED STEEL OVERHEAD TANK ON 18M TOWER AT EXPORT
PROCESSING ZONES AUTHORITY ATHIRIVER MACHAKOS COUNTY

ID TASK NAME DURATION START


Err:502
WORK SCHEDULE

TENDER FOR CONSTRUCTION OF THR PROPOSED STAFF CAR PARKING AND PEDESTRIAN SHADE IN THE UNHCR
COMPOUND-KAKUMA; TURKANA COUNTY REF NO. RFP/SC/KAK/2022/010/SL

ID Task Task Name Duration Start Finish


Mode

1 PROJECT TIMELINE 73 days 23/11/22 4/2/23 73


2 PRELIMINARIES 16 days 23/11/22 9/12/22 16
3 Contractual Matters 16 days 23/11/22 9/12/22 16
4 Tender Evaluation and Award 3 days 23/11/22 26/11/22 3
5 Processing and presentation of performance bond 6 days 27/11/22 3/12/22 6
6 Signing of contract 1 days 4/12/22 5/12/22 1
7 Publication of procurement contract 1 days 6/12/22 7/12/22 1
8 Site handover meeting 1 days 8/12/22 9/12/22 1
9 EXECUTION PROCEDURES 50 days 9/12/22 28/1/23 50
10 Offsite Works 11 days 9/12/22 20/12/22 11
11 Presentation of Method statement, Work plan and project for approval. 2 days 9/12/22 11/12/22 2
12 Presentation of equipment licences and inspection certificates 2 days 12/12/22 14/12/22 2
13 Mobilization of resources to site 3 days 17/12/22 20/12/22 3
14 Onsite Works 26 days 2/1/23 28/1/23 26
15 Site setup 5 days 2/1/23 7/1/23 5
16 Site take over and planning meeting 1 days 2/1/23 3/1/23 1
17 Approval of work methodology and work plan 2 days 3/1/23 5/1/23 2
18 Hoarding of the site 1 days 5/1/23 6/1/23 1
19 Setting up a site office 1 days 6/1/23 7/1/23 1
20 Pre-assembly 3days 5/1/23 8/1/23 3
21 Assessment of the individual components 1days 5/1/23 6/1/23 1
22 Identification of disassembly of parts. 2days 5/1/23 7/1/23 2
23 Sorting out components in various color codes 1days 6/1/23 7/1/23 1
24 Greasing and servicing of the moving parts and motors 1days 7/1/23 8/1/23 1
25 Surface Preparation & PaintWorks 8 days 9/1/23 17/1/23 8
26 Sandblasting of the garders, the two halves for each side 1 days 9/1/23 10/1/23 1
27 Sandblasting of the two end carriages 1 days 10/1/23 11/1/23 1
28 Sandblasting of the wire rope drums and shelves 1 days 12/1/23 13/1/23 1
29 Sandblasting of the grab frame and grabbing teeth 1 days 14/1/23 15/1/23 1
30 Painting the cleaned components 3 days 13/1/23 16/1/23 3
31 Inspection Works 1 days 16/1/23 17/1/23 1
32 Assembly Works 8 days 17/1/23 25/1/23 8
33 Trial assembly of the girders to the end controllers 2 days 17/1/23 19/1/23 2
34 Greasing of the main gantry moving rail. 1 days 18/1/23 19/1/23 1
35 Assembly of the hydraulic power pack 1 days 19/1/23 20/1/23 1
36 Assembly of the grab teeth to the power pack 2 days 20/1/23 22/1/23 2
37 Lifting of the individual components 4 days 21/1/23 25/1/23 4
38 Electrical Works 3 days 25/1/23 28/1/23 3
39 Layout electrical cables for power pack 1 days 25/1/23 26/1/23 1
40 Install limit switches & terminate to remote control pads and control boxes 1 days 26/1/23 27/1/23 1
41 Inspection of Works 1 days 27/1/23 28/1/23 1
42 Testing and commissioning 1 days 27/1/23 28/1/23 1
43 PROJECT TERMINATION 6 days 29/1/23 4/2/23 6
44 Inspection of works with client 1 days 29/1/23 30/1/23 1
45 Attendance to snaglist 3 days 29/1/23 1/2/23 3
46 Handing over works to client 1 days 1/2/23 2/2/23 1
47 Prepare and present As-built Drawings 2 days 1/2/23 3/2/23 2
48 Clear from site 1 days 3/2/23 4/2/23 1

Project: INSTALLATION AND Automatically Scheduled


COMMISSIONING OF 20T
EOT CRANE
Manually Scheduled
Date: 14/11/22
WORK PROGRAM

BOREHOLE EQUIPING AND CONSTRUCTION OF GALVANIZED STEEL OVERHEAD TANK ON 18M TOWER AT
EXPORT PROCESSING ZONES AUTHORITY ATHIRIVER MACHAKOS COUNTY

ID TASK NAME DURATION START


1 PROJECT TIMELINE 113 Days 16/2/2023
PRELIMINARIES 8 Days 16/2/2023
Contractual matters 8 Days 24/2/2023
Tender evaluation and award 3 Days 24/2/2023
Processing and presentation of performance bond 4 Days 25/2/2023
signing of contract 1 Days 26/2/2023
Publication of procurement contract 1 Days 27/2/2023
EXECUTION PROCEDURE 101 Days 28/2/2023
OFFSITE WORKS 30 Days 28/2/2023
Presentation of method statement workplan and JSA 2 Days 1/3/2023
Project drawings for approval 1 Days 3/3/2023
Presentation of lift machinary inspection certificates
and operators licence 2 Days 4/3/2023
Project design works 3 Days 4/3/2023
Presentation of project drawings and materials
equipments sample 1 Days 5/3/2023
Procurement of materials and work equipments 3 Days 6/3/2023
Fabrication tank tower 15 Days 9/3/2023
Fabrication of tank panels 15 Days 24/3/2023
Surface preparations and paintworks 11 Days 5/4/2023
Galvanization of tank panels brackets and brazings 13 days 16/4/2023
Inspection of works 1 Days 18/4/2023
Mobilization of resources 5 Days 19/4/2023
Onsite Works 85 Days 24/4/2023
Site set up 5 Days 25/4/2023
Site takeover and meetings 2 Days 26/4/2023
Approval of workplan methodology and JSA 2 Days 26/4/2023
Hoading over the site under works setting up office 2 Days 27/4/2023
Establish a location with approval for storing damping
or disposal of waste materials
1 Days 28/4/2023
Borehole equipping 17 Days 29/4/2023
Installation of pipework and fittings 7 Days 1/5/2023
Installation of control valves and meter 3 Days 8/5/2023
Construction of borehole chamber 7 Days 11/5/2023
Construction of pump house 7 Days 18/5/2023
Tank works 41 Days 19/5/2023
excavation works 4 Days 20/5/2023
Civil works 14 Days 24/5/2023
Erection of columns 3 Days 8/6/2023
Installation of brazings 5 Days 11/6/2023
Installation of access ladders 2 Days 16/6/2023
Install beam bearers and joists 2 Days 18/6/2023
Install deck chequered plates and handrail 2 Days 20/6/2023
Hoist and assembly of tank panels 10 Days 22/6/2023
Assembly stay and ties 2 Days 2/7/2023
Install roof and vents 4 Days 4/7/2023
Install tank access ladder 2 Days 8/7/2023
Carry out pipe works 2 Days 10/7/2023
Paintworks touch-ups 2 Days 12/7/2023
Inspection of works 1 Days 12/7/2023
PROJECT TERMINATION 6 Days 12/7/2023
Inspection of works 1 Days 13/7/2023
Attendance to snaglist 2 Days 14/7/2023
Handing over the works 1 Days 14/7/2023
Prepare and present as built drawings 2 Days 16/7/2023
Clear from site 2 Days 18/7/2023