TECHNICAL

TENDER
FORM X

PROGRAMME

CLIENT:
ADDAX PETROLEUM DEVELOPMENT (NIGERIA) LIMITED
CALL OFF CONTRACT FOR FABRICATION OF PLATFORM DECKS, TOPSIDES, 
JACKETS AND ASSOCIATED STRUCTURES
 TB‐2909 
ID Task Name Duration Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 TIPICAL PLATFORM FABRICATION 195.58 days?
2 MOBILIZATION 125 days
3 MOBILIZATION 7 days
4 Kick-off Meeting 1 day
5 Pre-Mob Inspection of Project Equipment: Land, Marine and other ancill 3 days
6 Mobilization of test Crew (Hydrotest, NDT etc…) 3 days
7 Tests and Certification of Additional Welders 4 days
8 Engineering & Project Documentation 153 days
9 Engineering & Project Documentation 10 days
10 Engineering & Project Documentation 10 days
11 Receive Client Drawing 2 days
12 Prepare Shop drawings and prepare weld map 14 days
13 Review Drawings for Constructibility 3 days
14 Provide WPS /PQR and Qualify Welders 10 days
15 Prepare & Issue Project Procedures and documentation to Addax 14 days
16 Receive comments from Addax 14 days
17 Finailse Project Procedures and documentation 14 days
18 PROCUREMENT 13 days
19 PROCUREMENT 10 days
20 PROCUREMENT 10 days
21 Procurement of additional Consumables 7 days
22 Procurement of additional Safety equipment 7 days
23 STRUCTURAL FABRICTION 129.58 days
24 Hand Rails,Escape Ladder,Cages & walk way 129.58 days
25 Cutting and edging 7 days
26 Fit up and tack weld in position 14 days

Task Summary External Milestone


Project: CALL OFF CONTRACT FOR
Split Project Summary Progress
Date: Fri 4/27/12
Milestone External Tasks Deadline

Page 1
CALL OFF CONTRACT FOR FABRICATION OF PLATFORM DECKS, TOPSIDES, 
JACKETS AND ASSOCIATED STRUCTURES
 TB‐2909 
ID Task Name Duration Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
27 Weld in place 9 days
28 Dimensional control 14 days
29 Carry out NDT 2 days
30 Blasting and Painting 6 days
31 VALVE ACCESS PLATFORM 24 days
32 Cutting and edging of main Beams/minor beams 5 days
33 Fit ups and Tack-welding of main beams/Minor beams 6 days
34 Welding of Main Beams/Minor beams 14 days
35 Dimensional control of beams 7 days
36 Carry out NDT 2 days
37 Blasting and Painting of Structural frameworks 8 days
38 LAUNCHER DECK 19 days
39 Cutting and edging of main Beams/minor beams 6 days
40 Fit ups and Tack-welding of main beams/Minor beams 7 days
41 Welding of Main Beams/Minor beams 14 days
42 Dimensional control of beams 13 days
43 Carry out NDT on all welded structure 2 days
44 Blasting and Painting of Structural frameworks 3 days
45 DECK LEGS, DECK SUPPORTS AND BRACINGS 25 days
46 Preparation of temporary construction aids 3 days
47 Cutting and edging of deck legs 4 days
48 Fit up and tack weld in position 8 days
49 Weld in place 8 days
50 Dimensional control 11 days
51 Carry out NDT on all welded structure 2 days
52 Blasting and Painting 9 days

Task Summary External Milestone


Project: CALL OFF CONTRACT FOR
Split Project Summary Progress
Date: Fri 4/27/12
Milestone External Tasks Deadline

Page 2
CALL OFF CONTRACT FOR FABRICATION OF PLATFORM DECKS, TOPSIDES, 
JACKETS AND ASSOCIATED STRUCTURES
 TB‐2909 
ID Task Name Duration Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
53 MAIN DECK 37 days 9/17
54 Cutting and edging of main Beams/minor beams 6 days
55 Fit ups and Tack-welding of main beams/minor beams 10 days
56 Welding of Main Beams and Minor beams 16 days
57 Dimensional control of beams 11 days
58 Carry out NDT 2 days
59 Blasting and Painting of Structural frameworks 9 days
60 CAISSON INSTALLATION GUIDE FRAMES/stabbing guides/installa 20 days
61 Cutting and edging of Installation guide frame 6 days
62 Fit ups and Tack-welding of Installation guide frame 9 days
63 Welding of Installation guide frame 11 days
64 Dimensional control of beams 10 days
65 Carry out NDT 2 days
66 Blasting and Painting of Installation guide frame 7 days
67 BOAT LANDING LADDERS, ESCAPE LADDER 30 days
68 Cutting and edging 2 days
69 Fit up and tack weld in position 4 days
70 Weld in in place 5 days
71 Dimensional control of beams 6 days
72 Carry out NDT 1 day
73 Blasting and Painting of Installation guide frame 4 days
74 BOAT LANDING 32 days
75 Cutting and edging 4 days
76 Fit up and tack weld in position 7 days
77 Weld in in place 9 days
78 Carry out NDT 1 day

Task Summary External Milestone


Project: CALL OFF CONTRACT FOR
Split Project Summary Progress
Date: Fri 4/27/12
Milestone External Tasks Deadline

Page 3
CALL OFF CONTRACT FOR FABRICATION OF PLATFORM DECKS, TOPSIDES, 
JACKETS AND ASSOCIATED STRUCTURES
 TB‐2909 
ID Task Name Duration Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
79 Install gratings 2 days
80 Blasting & painting 4 days
81 ANODE CLAMP 14 days
82 Cutting and edging 3 days
83 Rolling and machining of components (clamps, Hinge plates etc) 4 days
84 Fitting & Tacking 3 days
85 Assemble Clamps 4 days
86 Install Padeye 2 days
87 INTEGRATION OF DECK (ERECTION) 186 days?
88 Preparation of Deck integration Areas. 2 days
89 Installation of deck grillages and deck temporary supports. 3 days
90 Integration of Luncher deck on the legs 4 days
91 Welding of Luncher deck on the legs 6 days
92 Integration of main deck on the legs 5 days
93 Welding of main deck on the legs 6 days
94 Integration of the valve access platform on the legs 2 days
95 Welding of the valve access platforms on the legs 5 days
96 Installation of valve access supports and bracings 6 days
97 NDE of all weldings 3 days
98 PIPING PREFABRICATION 100 days
99 PREFABRICATION OF PIPING SYSTEM 60 days?
100 NDE of all weldings 60 days
101 HYDROTEST OF SPOOLS 15 days
102 BLASTING AND COATING OF PIPING 15 days
103 INTEGRATION OF PIPES 39 days
104 Installation of pipe Supports 9 days

Task Summary External Milestone


Project: CALL OFF CONTRACT FOR
Split Project Summary Progress
Date: Fri 4/27/12
Milestone External Tasks Deadline

Page 4
CALL OFF CONTRACT FOR FABRICATION OF PLATFORM DECKS, TOPSIDES, 
JACKETS AND ASSOCIATED STRUCTURES
 TB‐2909 
ID Task Name Duration Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
105 Installation of prefabricated piping spools 18 days
106 Installation of equipments(Chemical Injection skid, test separators, instru 12 days
107 installation of Pig launcher and Pig receiver 3 days
108 Installation of manifold 2 days
109 Installation of instrumentatin lines 9 days
110 Complete Painitng Touchups of the unit 9 days
111 WEIGHING OF PLATFORM 4 days
112 Touch up painting & clean up of fabrication area/Load Out 24 days
113 Package loose fabricated items 8 days
114 Prepare packing list/Load out 7 days
115 Cleanup of Fabrication Area 4 days
116 LOAD OUT 40 days
117 Complete Preparation and company approval of load out design 8 days
118 Final Loadout of Deck 4 days
119 As build Documentation 10 days

Task Summary External Milestone


Project: CALL OFF CONTRACT FOR
Split Project Summary Progress
Date: Fri 4/27/12
Milestone External Tasks Deadline