DRAFT SCHEDULE ROOF MATERIAL ORDER AND FABRICATION

Sep-18 Oct-18 Nov-18


No Item Of Work Duration
29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Submmision Quotation 1 Day


ANNUAL SHUTDOWN JOB
2 Client Processed 2 Day PO
3 Site Visit and Measurement Check 3 Day
4 Po Received 1 Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Material
Onsite
5 Raw Material Order 30 days
6 Fabrication 2 days
Upper Pulp Machine
7 Material Delivery 2 days ( upper ceiling area )
8 Installation 30 days
Others area continuous until 30 days
9 Roof Ventilator Order 21 days
10 Fabrication Flasing 10 Days