You are on page 1of 1

ID Task Name Duration Month 2 Month 3 Month 4

W-3 W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11


1 CONSTRUCTION OF 9 SILOS 63 days
BUNKERS
2 Site Handover 1 day Site Handover

3 Mobilisation 3 days Mobilisation

4 Site Setup 3 days Site Setup

5 Foundation Excavation 7 days Foundation Excavation

6 Steel Work fixing 20 days Steel Work fixing

7 formwork base 4 days formwork base

8 casting base 4 days casting base

9 Formwork Concrete walls 7 days Formwork Concrete walls

10 Casting Concrete Walls 4 days Casting Concrete Walls

11 Stripping Formwork 3 days Stripping Formwork

12 Waterproofing 3 days Waterproofing

13 Pavers Works 10 days Pavers Works

14 painting 5 days painting

15 Site Cleaning 3 days Site Cleaning

16 Site Handover 1 day Site Handover