ID Task Name Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Busunju Poultry structures 44 days
2
3 Site Handover 1 day 1 day Site Handover
4
5 Site Preparations 4 days
6 Site Clearance 2 days 2 days Site Clearance
7 Site set up 2 days 2 days Site set up
8 Setting out 1 day 1 day Setting out
9
10 Framing 14 days
11 Column Bases excavation 2 days 2 days Column Bases excavation
12 Steel work column stubs & Bases 3 days 3 days Steel work column stubs & Bases
13 Prefabs for Formwork Boxes - Stubs 3 days 3 days Prefabs for Formwork Boxes - Stubs
14 Casting column bases 1 day 1 day Casting column bases
15 Fixing Formwork Stubs & Casting stub columns 4 days 4 days Fixing Formwork Stubs & Casting stub columns
16 Placing steel F.work & Casting columns 4 days 4 days Placing steel F.work & Casting columns
17 Steel work beam 4 days 4 days Steel work beam
18 Formwork Ring beam 4 days 4 days Formwork Ring beam
19 Casting Ring beam 4 days 4 days Casting Ring beam
20
21 Roofing 21 days
22 Forming Roof trusses on Ground 12 days 12 days Forming Roof trusses on Ground
23 Lifting & Aligning Roof Trusses 3 days 3 days Lifting & Aligning Roof Trusses
24 Iron sheets laying 3 days 3 days Iron sheets laying
25
26 Exacation srip foundation 3 days 3 days Exacation srip foundation
27 Strip concrete 3 days 3 days Strip concrete
28 Plinth walling 3 days 3 days Plinth walling
29 Slab lining 4 days 4 days Slab lining
30 Walling Below beam 4 days 4 days Walling Below beam
31 walling above beams 4 days 4 days walling above beams
32 Splash exvavation, concrete & Brickwork + Backfill 6 days 6 days Splash exvavation,concrete & Brickwork + Backfill
33 fabrication of door & windows 11 days 11 days fabrication of door & windows
34 Fixing doors & windows 4 days 4 days Fixing doors & windows
35 Plaster & Render 6 days 6 days Plaster & Render
36
37 Slab & Associated works 8 days
38 Murrum backfill & Compaction 4 days 4 days Murrum backfill & Compaction
39 Hardcore placement & Blinding 4 days 4 days Hardcore placement & Blinding
40 Slab Casting 4 days 4 days Slab Casting
41
42 Mechanical Installations 32 days
43 Tank stand fabrication 12 days 12 days Tank stand fabrication
44 tank placement & Piping 3 days 3 days tank placement & Piping
45 Electrical Installation 3 days 3 days Electrical Installation
46
47 painting and clean Up 6 days 6 days painting and clean
48 Site handover 1 day 1 day Site Handover

Project: Project1 Task Progress Summary External Tasks Deadline


Date: Thu 1/27/22 Split Milestone Project Summary External Milestone