ID Task Name Duration Month 1 Month 2 Month 3 Month 4 Month 5 Month 6

W-3 W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25
1 RENOVATION OF GEIDAM LOCAL GOVERNMENT LODGE, 119 days
GEIDAM LGA, YOBE STATE
2 MOBILISATION TO SITE 3 days
3 SITE SETTING OUT 4 days
4 BLOCK 1 85 days
5 DEMOLITION AND ALTERATION 10 days
6 MASONRY RETROFIT (Concrete and Blockwork) 21 days
7 BLOCKWORK AND CONCRETE WORK 21 days
8 ROOF CARCASS AND COVERING 19 days
9 STRUCTURAL CARCASSING 10 days
10 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
11 CEILING 7 days
12 DOORS/WINDOWS INSTALLATION 12 days
13 FINISHES 14 days
14 FLOOR 12 days
15 ELECTRICAL INSTALLATION 10 days
16 PLUMBING SERVICES INSTALLATION 12 days
17 PAINTING 10 days
18 BLOCK 2 85 days
19 DEMOLITION AND ALTERATION 10 days
20 MASONRY RETROFIT (Concrete and Blockwork) 21 days
21 BLOCKWORK AND CONCRETE WORK 21 days
22 ROOF CARCASS AND COVERING 19 days
23 STRUCTURAL CARCASSING 10 days
24 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
25 CEILING 7 days
26 DOORS/WINDOWS INSTALLATION 12 days
27 FINISHES 14 days
28 FLOOR 12 days
29 ELECTRICAL INSTALLATION 10 days
30 PLUMBING SERVICES INSTALLATION 12 days
31 PAINTING 10 days
32 BLOCK 3 85 days
33 DEMOLITION AND ALTERATION 10 days
34 MASONRY RETROFIT (Concrete and Blockwork) 21 days
35 BLOCKWORK AND CONCRETE WORK 21 days
36 ROOF CARCASS AND COVERING 19 days
37 STRUCTURAL CARCASSING 10 days
38 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
39 CEILING 7 days
40 DOORS/WINDOWS INSTALLATION 12 days
41 FINISHES 14 days
42 FLOOR 12 days
43 ELECTRICAL INSTALLATION 10 days
44 PLUMBING SERVICES INSTALLATION 12 days
45 PAINTING 10 days
46 BLOCK 4 85 days
47 DEMOLITION AND ALTERATION 10 days
48 MASONRY RETROFIT (Concrete and Blockwork) 21 days
49 BLOCKWORK AND CONCRETE WORK 21 days
50 ROOF CARCASS AND COVERING 19 days
51 STRUCTURAL CARCASSING 10 days
52 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
53 CEILING 7 days
54 DOORS/WINDOWS INSTALLATION 12 days
55 FINISHES 14 days
56 FLOOR 12 days
57 ELECTRICAL INSTALLATION 10 days
58 PLUMBING SERVICES INSTALLATION 12 days
59 PAINTING 10 days
60 BLOCK 5 95 days
61 DEMOLITION AND ALTERATION 10 days
62 MASONRY RETROFIT (Concrete and Blockwork) 21 days
63 BLOCKWORK AND CONCRETE WORK 21 days
64 ROOF CARCASS AND COVERING 19 days
65 STRUCTURAL CARCASSING 10 days
66 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
67 CEILING 7 days
68 DOORS/WINDOWS INSTALLATION 12 days
69 FINISHES 14 days
70 FLOOR 12 days
71 ELECTRICAL INSTALLATION 10 days
72 PLUMBING SERVICES INSTALLATION 12 days
73 PAINTING 10 days
74 BLOCK 6 95 days
75 DEMOLITION AND ALTERATION 10 days
76 MASONRY RETROFIT (Concrete and Blockwork) 21 days
77 BLOCKWORK AND CONCRETE WORK 21 days
78 ROOF CARCASS AND COVERING 19 days
79 STRUCTURAL CARCASSING 10 days
80 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
81 CEILING 7 days
82 DOORS/WINDOWS INSTALLATION 12 days
83 FINISHES 14 days
84 FLOOR 12 days
85 ELECTRICAL INSTALLATION 10 days
86 PLUMBING SERVICES INSTALLATION 12 days
87 PAINTING 10 days
88 BLOCK 7 95 days
89 DEMOLITION AND ALTERATION 10 days
90 MASONRY RETROFIT (Concrete and Blockwork) 21 days
91 BLOCKWORK AND CONCRETE WORK 21 days
92 ROOF CARCASS AND COVERING 19 days
93 STRUCTURAL CARCASSING 10 days
94 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
95 CEILING 7 days
96 DOORS/WINDOWS INSTALLATION 12 days
97 FINISHES 14 days
98 FLOOR 12 days
99 ELECTRICAL INSTALLATION 10 days
100 PLUMBING SERVICES INSTALLATION 12 days
101 PAINTING 10 days
102 BLOCK 8 95 days
103 DEMOLITION AND ALTERATION 10 days
104 MASONRY RETROFIT (Concrete and Blockwork) 21 days
105 BLOCKWORK AND CONCRETE WORK 21 days
106 ROOF CARCASS AND COVERING 19 days
107 STRUCTURAL CARCASSING 10 days
108 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
109 CEILING 7 days
110 DOORS/WINDOWS INSTALLATION 12 days
111 FINISHES 14 days
112 FLOOR 12 days
113 ELECTRICAL INSTALLATION 10 days
114 PLUMBING SERVICES INSTALLATION 12 days
115 PAINTING 10 days
116 RECEPTION 95 days
117 DEMOLITION AND ALTERATION 10 days
118 MASONRY RETROFIT (Concrete and Blockwork) 21 days
119 BLOCKWORK AND CONCRETE WORK 21 days
120 ROOF CARCASS AND COVERING 19 days
121 STRUCTURAL CARCASSING 10 days
122 ROOF COVERING/ REPAIR OF ROOF LEAKAGES 9 days
123 CEILING 7 days
124 DOORS/WINDOWS INSTALLATION 12 days
125 FINISHES 14 days
126 FLOOR 12 days
127 ELECTRICAL INSTALLATION 10 days
128 PLUMBING SERVICES INSTALLATION 12 days
129 PAINTING 10 days
130 GATE HOUSE 7 days
131 DEMOLITION AND ALTERATION 1 day
132 MASONRY RETROFIT 3 days
133 ROOF CARCASS AND COVERING 1 day
134 WINDOWS AND DOORS 1 day
135 FINISHES 1 day
136 ELECTRICAL INSTALLATION 1 day
137 PAINTING 1 day
138 GENERATOR HOUSE 7 days
139 DEMOLITION AND ALTERATION 1 day
140 MASONRY RETROFIT 3 days
141 ROOF CARCASS AND COVERING 1 day
142 WINDOWS AND DOORS 1 day
143 FINISHES 1 day
144 PAINTING 1 day
145 ELECTRICAL INSTALLATION 1 day
146 SITE CLEANING 2 days
147 SITE HAND OVER 1 day

Project: NLCB LOT 035 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline