Dear Sir,
We are pleased to submit below our best price for your requirement.
EQUALBID19-1Q025
MATERIAL LABOR Total Unit
ITEM NO. QTY UOM ITEM DESCRIPTION
Unit Cost Unit Cost Cost
GLASS WALLING/DOOR
Tempered Glass, 12 mm Thick with 2-side
0.9mX0.9m Door Openning with Stainless Steel
1 lot Handle & Lock, Aluminum Framing & Bracket. 263,819.83 79,145.95 342,965.78
Special Discount, 7%
NET PROJECT COST
Scope of Works:
1.0 Supply labor and materials for installation of inspector test valve connector .
2.0 Supply tools and equipment.
3.0 Testing and Commissioning
4.0 Asbuilt Plan
PROJECT COST:
TERMS: 50% Down payment, balance by progress billing
Excluding relocation and existing items inside
DURATION: As per agreement
VALIDITY: 30 days
WARRANTY: N/A
OTHERS: Written Notice is required for any ADDITONAL or CHANGE OF ORDER
Thank You so Much for giving us the opportunity to submit this quotation.
Conforme :
ALLAN M. ALAGOS, PME
General Manager Client/Representative
11/25/2020
Total Amount
342,965.78
133,120.00
316.37
15,210.00
15,858.96
36,504.00
543,975.11
65,277.01
609,252.12
42,647.65
566,604.47