BUILDING :B
SUBJECT : ADDITIONAL WORKS FOR MAIN LOBBY INSTALLATION
DATE : July 11, 2022
MATERIALS LABOR
Item No. Description UNIT QTY TOTAL
Unit Cost Amount Unit Cost Amount
I. ELECTRICAL WORKS
A. GROUND FLOOR MAIN LOBBY ADDITIONAL ELECTRICAL WORKS
Roughing Ins
1 20mmØ PVC Pipe lth 420.00 170.00 71,400.00 55.24 23,200.80 94,600.80
2 20mmØ PVC A & L pcs 120.00 20.28 2,433.60 7.89 946.80 3,380.40
3 15mmØ Bushing pcs 60.00 12.00 720.00 5.02 57.68 189.68
4 Octagonal Box pcs 60.00 52.00 3,120.00 21.53 1,291.80 4,411.80
5 Octagonal Box Cover pcs 60.00 30.00 1,800.00 10.89 653.40 2,453.40
6 20mmØ Flexible Metal conduit lm 88.00 83.00 7,304.00 65.63 5,775.44 13,079.44
7 20mmØ Angle connector pcs 48.00 120.00 5,760.00 56.82 2,727.36 8,487.36
8 20mmØ Straight connector pcs 48.00 37.62 1,805.76 56.82 2,727.36 4,533.12
9 Chipping Works lot 1.00 335.00 1,340.00 603.00 938.00 2,278.00
Bistay bag/s
Cement bag/s
10 Consumables lot 1.00 27,602.90 27,602.90 12,421.30 12,421.30 40,024.20
SUB TOTAL FOR A 123,286.26 50,739.95 173,438.21
Prepared By Checked By
MATERIALS LABOR
Item No. Description UNIT QTY TOTAL
Unit Cost Amount Unit Cost Amount
I. ELECTRICAL WORKS
A. GROUND FLOOR MAIN LOBBY ADDITIONAL ELECTRICAL WORKS
Roughing Ins
1 20mmØ PVC Pipe lth 420.00 170.00 71,400.00 55.24 23,200.80 94,600.80
2 20mmØ PVC A & L pcs 120.00 20.28 2,433.60 7.89 946.80 3,380.40
3 15mmØ Bushing pcs 60.00 12.00 720.00 5.02 57.68 189.68
4 Octagonal Box pcs 60.00 52.00 3,120.00 21.53 1,291.80 4,411.80
5 Octagonal Box Cover pcs 60.00 30.00 1,800.00 10.89 653.40 2,453.40
6 20mmØ Flexible Metal conduit lm 88.00 83.00 7,304.00 65.63 5,775.44 13,079.44
7 20mmØ Angle connector pcs 48.00 120.00 5,760.00 56.82 2,727.36 8,487.36
8 20mmØ Straight connector pcs 48.00 37.62 1,805.76 56.82 2,727.36 4,533.12
9 Chipping Works lot 1.00 335.00 1,340.00 603.00 938.00 2,278.00
Bistay bag/s
Cement bag/s
10 Consumables lot 1.00 27,602.90 27,602.90 12,421.30 12,421.30 40,024.20
SUB TOTAL FOR A 123,286.26 50,739.95 173,438.21
Prepared By Checked By
MATERIALS LABOR
Item No. Description UNIT QTY TOTAL
Unit Cost Amount Unit Cost Amount
I. ELECTRICAL WORKS
A. GROUND FLOOR MAIN LOBBY ADDITIONAL ELECTRICAL WORKS
Roughing Ins
1 20mmØ PVC Pipe lth 420.00 170.00 71,400.00 55.24 23,200.80 94,600.80
2 20mmØ PVC A & L pcs 120.00 20.28 2,433.60 7.89 946.80 3,380.40
3 15mmØ Bushing pcs 60.00 12.00 720.00 5.02 57.68 189.68
4 Octagonal Box pcs 60.00 52.00 3,120.00 21.53 1,291.80 4,411.80
5 Octagonal Box Cover pcs 60.00 30.00 1,800.00 10.89 653.40 2,453.40
6 20mmØ Flexible Metal conduit lm 88.00 83.00 7,304.00 65.63 5,775.44 13,079.44
7 20mmØ Angle connector pcs 48.00 120.00 5,760.00 56.82 2,727.36 8,487.36
8 20mmØ Straight connector pcs 48.00 37.62 1,805.76 56.82 2,727.36 4,533.12
9 Chipping Works lot 1.00 335.00 1,340.00 603.00 938.00 2,278.00
Bistay bag/s
Cement bag/s
10 Consumables lot 1.00 27,602.90 27,602.90 12,421.30 12,421.30 40,024.20
SUB TOTAL FOR A 123,286.26 50,739.95 173,438.21
Prepared By Checked By
MATERIALS LABOR
Item No. Description UNIT QTY TOTAL
Unit Cost Amount Unit Cost Amount
I. ELECTRICAL WORKS
A. GROUND FLOOR MAIN LOBBY ADDITIONAL ELECTRICAL WORKS
Roughing Ins
1 20mmØ PVC Pipe lth 420.00 170.00 71,400.00 55.24 23,200.80 94,600.80
2 20mmØ PVC A & L pcs 120.00 20.28 2,433.60 7.89 946.80 3,380.40
3 15mmØ Bushing pcs 60.00 12.00 720.00 5.02 57.68 189.68
4 Octagonal Box pcs 60.00 52.00 3,120.00 21.53 1,291.80 4,411.80
5 Octagonal Box Cover pcs 60.00 30.00 1,800.00 10.89 653.40 2,453.40
6 20mmØ Flexible Metal conduit lm 88.00 83.00 7,304.00 65.63 5,775.44 13,079.44
7 20mmØ Angle connector pcs 48.00 120.00 5,760.00 56.82 2,727.36 8,487.36
8 20mmØ Straight connector pcs 48.00 37.62 1,805.76 56.82 2,727.36 4,533.12
9 Chipping Works lot 1.00 335.00 1,340.00 603.00 938.00 2,278.00
Bistay bag/s
Cement bag/s
10 Consumables lot 1.00 27,602.90 27,602.90 12,421.30 12,421.30 40,024.20
SUB TOTAL FOR A 123,286.26 50,739.95 173,438.21
Prepared By Checked By