REQUEST FOR QUOTATION

Customer Name: Dela Salle University Date: December 15, 2021


Address: 2401 Taft Avenue, 0922 Manila, Philippines
Civil and Sanitary
Attention: Engr. Anthony Y. Dorde Designation:
Works Office

Subject:
Proposed EMRSC Exterior Wall Repainting, Waterproofing and Sealing of
Earthquake Cracks

Actual Computed
Front Elevation 2279.5925 2621.531375
Rear Elevation 2048.55 2355.8325
Right Elevation 2349.077 2701.43855
Left Elevation 3045.355 3502.15825

Total Area of Polytech: 11180.96068 sqm


Area for CSM: 11180.96068 sqm

Unit Qty Description Unit Price Total


776 pails Poly Tech White 7,390.00 5,734,640.00
20 rolls CSM #230 18,000.00 360,000.00
300 sets Epoxy 3,840.00 1,152,000.00
1200 pcs Packer 285.00 342,000.00
4 pcs Nozzle 455.00 1,820.00
500 tubes Sikaflex - concrete 1,100.00 550,000.00
285 tubes Sika Hyflex - glass 1,350.00 384,750.00
1000 pcs Backer Rods (3.5 m/pc) 150.00 150,000.00
30 sacks Patching Compound 1,150.00 34,500.00
50 pcs GI Pipe size 3/4 dia 1,970.00 98,500.00
30 pcs Clamp 120.00 3,600.00
10 kls GI wire #16 340.00 3,400.00
1 roll Lambat / Mesh (8'x90m) 10,227.27 10,227.27

Total 8,825,437.27
Legend: To be Fill Up

metal poly tech csm masonry putty


#REF! 776.1007 83.8219 225.6192
#REF! 776.00 84.00 226.00
Manpower Days Labor Head Cost Amount
Actual Labor Cost 15 180 600 1,620,000.00 PHP

Labor Cost: (40% of Material Cost) 3,530,174.91 PHP


Contractor Labor Cost
w/ safety officer: x 2 - PHP
(Kuya Medel)

Item Description Amount

A. Labor and Material


1 Labor Cost 3,530,174.91
2 Material Cost 8,825,437.27

Sub Total A 12,355,612.18

B. Miscellaneous
1 Mob / Demob 20,000.00
2 Bonds and CARI 86,489.29
3 Tools and Equipment 30,000.00
4 Permit 20,000.00
5 Gondula 800,000.00
6 Hauling 15,000.00
7 Safety Officer 160,000.00
8 Contengency 404,613.04

Sub Total B 1,536,102.33

Total Cost 13,891,714.51


12% VAT 1,667,005.74

Actual Area 9,722.57


Cost per Square Meter 1,600.27
Total Project Cost 15,558,720.25
13,487,101.46
REQUEST FOR QUOTATION

Customer Name: Dela Salle University Date: December 15, 2021


Address: 2401 Taft Avenue, 0922 Manila, Philippines
Civil and Sanitary
Attention: Engr. Anthony Y. Dorde Designation:
Works Office

Subject:
Proposed EMRSC Exterior Wall Repainting, Waterproofing and Sealing of
Earthquake Cracks

Actual Computed
Front Elevation 2279.5925 2621.531375
Rear Elevation 2048.55 2355.8325
Right Elevation 2349.077 2701.43855
Left Elevation 3045.355 3502.15825

Total Area of Polytech: 11180.96068 sqm


Area for CSM: 11180.96068 sqm

Unit Qty Description Unit Price Total


776 pails Poly Tech White 2,600.00 2,017,600.00
20 rolls CSM #230 6,336.00 126,720.00
300 sets Epoxy 1,352.00 405,600.00
1200 pcs Packer 100.00 120,000.00
4 pcs Nozzle 160.00 640.00
1000 tubes Sikaflex - concrete 387.00 387,000.00
285 tubes Sika Hyflex - glass 475.00 135,375.00
1500 pcs Backer Rods (3.5 m/pc) 53.00 79,500.00
30 sacks Patching Compound 405.00 12,150.00
100 pcs GI Pipe size 3/4 dia 693.00 69,300.00
50 pcs Clamp 42.00 2,100.00
10 kls GI wire #16 120.00 1,200.00
1 roll Lambat / Mesh (8'x90m) 3,600.00 3,600.00

Total 3,360,785.00
Legend: To be Fill Up

metal poly tech csm masonry putty


#REF! 776.1007 83.8219 225.6192
#REF! 776.00 84.00 226.00
Manpower Days Labor Head Cost Amount
Actual Labor Cost 15 180 600 1,620,000.00 PHP

Labor Cost: (40% of Material Cost) 1,344,314.00 PHP


Contractor Labor Cost
w/ safety officer: x 2 - PHP
(Kuya Medel)

Item Description Amount

A. Labor and Material


1 Labor Cost 1,620,000.00
2 Material Cost 3,360,785.00

Sub Total A 4,980,785.00

B. Miscellaneous
1 Mob / Demob 20,000.00
2 Bonds and CARI 39,846.28
3 Tools and Equipment 30,000.00
4 Permit 20,000.00
5 Gondula 800,000.00
6 Hauling 15,000.00
7 Safety Officer 160,000.00
8 Contengency 303,281.56

Sub Total B 1,388,127.84

Total Cost 6,368,912.84


12% VAT 764,269.54

Actual Area 9,722.57


Cost per Square Meter 733.67
Total Project Cost 7,133,182.39
6,065,631.28
Actual Cost for Quotation

Customer Name: Dela Salle University Date: February 10, 2022


Address: 2401 Taft Avenue, 0922 Manila, Philippines
Civil and Sanitary
Attention: Engr. Anthony Y. Dorde Designation:
Works Office

Subject:
Proposed EMRSC Exterior Wall Repainting, Waterproofing and Sealing of
Earthquake Cracks

Actual Computed
Front Elevation 2279.5925 2621.531375
Rear Elevation 2048.55 2355.8325
Right Elevation 2349.077 2701.43855
Left Elevation 3045.355 3502.15825
Window Metal Frame 1278.52 1470.298

Total Area of Polytech: 11180.96068 sqm


Area for CSM: 11180.96068 sqm
Total Area of Metal: 1470.298

Unit Qty Description Unit Price Total


776 pails Poly Tech White 2,600.00 2,017,600.00
20 rolls CSM #230 6,336.00 126,720.00
300 sets Epoxy 1,400.00 420,000.00
1200 pcs Packer 100.00 120,000.00
4 pcs Nozzle 160.00 640.00
500 tubes Sikaflex - concrete 387.00 193,500.00
1000 tubes Sika Hyflex - glass 475.00 475,000.00
1000 pcs Backer Rods (3.5 m/pc) 53.00 53,000.00
30 sacks Patching Compound 405.00 12,150.00
50 pcs GI Pipe size 3/4 dia 693.00 34,650.00
30 pcs Clamp 42.00 1,260.00
10 kls GI wire #16 120.00 1,200.00
1 roll Lambat / Mesh (8'x90m) 3,600.00 3,600.00
212 gals Boysen QDE 705.00 149,460.00

Total 3,608,780.00
Legend: To be Fill Up

metal poly tech csm masonry putty


212.0426 776.1007 83.8219 225.6192
212.00 776.00 84.00 226.00
Manpower Days Labor Head Cost Amount
Actual Labor Cost 15 180 600 1,620,000.00 PHP

Labor Cost: (40% of Material Cost) 1,443,512.00 PHP


Contractor Labor Cost: 11,001.09 x 306.72 3,374,255.71 PHP

Item Description Amount

A. Labor and Material


1 Labor Cost 3,374,255.71
2 Material Cost 3,608,780.00

Sub Total A 6,983,035.71

B. Miscellaneous
1 Mob / Demob 20,000.00
2 Bonds and CARI 83,796.43
3 Tools and Equipment 20,000.00
4 Permit 20,000.00
5 Gondula (Contractor)
6 Hauling 10,000.00
7 Safety Officer - 2 (Contractor)
8 Contengency 142,736.64

Sub Total B 296,533.07

Total Cost 7,279,568.78


12% VAT 873,548.25

Actual Area 11,001.09


Cost per Square Meter 741.12
Total Project Cost 8,153,117.03
7,136,832.13