Date: January 8, 2020

Reference Number: CVIBAL CONSTRUCTION


General Construction | Renovation | Fit-Out | Design & Consultancy

CLIENT : 41 Reyes 57 Sierra Madre Circle, Suburban Heights Subd. Cainta Rizal

LOCATION: Pleasant Hills Subd. San Jose del Monte Bulacan Contact Nos: 0928-8458674 / 0928-8458670

Material Other/
Item Description Qty Unit Extended Cost
Cost Labor Cost

1 GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization 1.00 lot 15,000.00
1.2 Hauling and Disposal 1.00 lot 3,500.00
1.3 Site Praparation & Protective Coverings 1.00 lot 5,000.00
1.4 Final Cleaning And Sanitation 1.00 lot 3,750.00
Sub-Total 27,250.00
2 CEILING WORKS
2.10 Foyer, Bedrooms, Family room, Living room. Dining room
2.11 Using 12mm THK Ordinary Gypsum Board (Knauf/Boral/Gyproc)
a Supply and Install of Gypsum board for ceiling in metal framing 234.16 sqm 570.00 280.00 199,036.00
Toilet & Bath
2.12 Using 12mm THK Moisture Resistant Gypsum Board (Knauf/Boral/Gyproc)
a Supply and Install of Gypsum board for ceiling in metal framing 33.19 sqm 820.00 280.00 36,509.00
Kitchen
2.13 Using 12mm THK Fire Retardant Gypsum Board (Knauf/Boral/Gyproc)
a Supply and Install of Gypsum board for ceiling in metal framing 25.32 sqm 820.00 280.00 27,852.00
Sub-Total 263,397.00
3 PAINTING WORKS
3.10 Exterior
3.11 Using Titan Superflex Elastomeric Paint-firewall (Boysen) ; Semigloss Latex-non firewall (Boysen)
a Firewall 120.66 sqm 300.00 200.00 60,330.00
b Non Firewall 188.13 sqm 250.00 150.00 75,252.00
Interior
3.12 Using Semigloss Latex-wall (Boysen); Flat Latex-ceiling (Boysen)
a Wall 371.33 sqm 250.00 150.00 148,532.00
b Ceiling 301.43 sqm 200.00 150.00 105,500.50
Sub-Total 389,614.50

TOTAL PROJECT COST (EXCLUSIVE OF TAX) 680,261.50

*** TERMS AND CONDITIONS


50% Downpayment shall be paid upon signing of contract 340,130.75
15% Progress Billing 102,039.23
15% Progress Billing 102,039.23
15% Progress Billing 102,039.23
5% Final Billing upon accomplishment 34,013.08
Any variation/additional works and change order must be approved by both party 680,261.50

** EXCLUDED
Painting of Perimeter Fence Wall/Parapet Wall
Ceiling Eaves (exterior) - boards and paint