Professional Documents
Culture Documents
PROJECT:
OWNER/
MONDE NISSIN,
CLIENT:
SUBJECT:
DATE:
GENERAL REQUIREMENT
#1 1 Lot(s) Mobilization/Demobilization 25,000.00
1 labor ,tools & equipment 32,400.00
DISTMANTLING OF EXISTING SUPPLY AND RETURN DUCT OF
AHU
Dismantling of 52.73 sq.m. Return duct including deteriorated Angle bar
and c channel supports.
#2 1 Lot(s)
CLADDING WORKS
#4 1 Lot(s)
85.08 sq.m aluminum cladding works for return and supply duct
SUB-TOTAL #REF!
TOTAL AMOUNT
#REF!
(VAT INCL.)
GOODHOUSE INDUSTRIES INC.
BAGUMBAYAN, TAGUIG CITY
PROJECT:
OWNER/CLIENT:
SUBJECT:
DATE:
GA. 22, GI. PLAIN SHEET(ducting for supply and return ) pcs 33.00 775.00 25,575.00
1''PE INSULATION FOAM roll 2.00 9,830.00 19,660.00
RUGBY gal. 3.00 620.00 1,860.00
1''X1''X1/4thk.angle bar pcs 10.00 480.00 4,800.00
CLADDING WORKS
GA. 22, g.i PLAIN SHEET(cladding ) pcs 33.00 1,620.00 53,460.00 1,060.00
BLIND RIVETS 1/8 X 3/4 box 3.00 190.00 570.00
BLIND RIVETS 1/2 X 1/8 box 3.00 220.00 660.00
SUB-TOTAL 54,690.00
GENERAL REQUIREMENTS
MOBILIZATION/DEMOBILIZATION 25,000.00
LABOR COST
MANPOWER: NUMBER RATE/DAY NUMBER OF DAYS
SAFETY OFFICER 1 1,200.00 2.00 2,400.00
PROJECT INCHARGE/ENGINEER 1 1,500.00 2.00 3,000.00
FOREMAN 1 1,000.00 3.00 3,000.00
INSTALLER(SKILLED) 2 850.00 3.00 2,550.00
LABORER 2 750.00 3.00 2,250.00
SUB-TOTAL 13,200.00
TOOLS AND EQUIPMENT
DELIVERY VEHICLE back and forth 8,000.00 2.00 16,000.00
H-FRAMES SET 800.00 2.00 1,600.00
SET OF TOOLS SET 800.00 2.00 1,600.00
SUB-TOTAL 19,200.00
SUB-TOTAL 217,285.00
TOTAL COST