You are on page 1of 2

PROJECT : COST GUIDELINES

LOCATION :
SUBJECT : Mechanical Works

INHOUSE
Unit Cost (Php)
Item DESCRIPTION Qty Unit Total Cost (Php)
Material Labor Total

AIR CONDITIONING WORKS (2F)

1 PRELIMINARIES

1.1 Mobilization/Demobilization 1.00 lot 90,000.00 90,000.00


1.2 Testing & Commissioning 1.00 lot 15,000.00 15,000.00
1.3 As built & Shopdrawings 1.00 lot 15,000.00 15,000.00
1.4 Site Management 1.00 lot 60,000.00 60,000.00
1.5 Hauling & Liftings 1.00 lot 20,000.00 20,000.00

TOTAL - PRELIMINARIES 200,000.00

2 DUCTING WORKS

2.1 GI Sheet
a. #24 1.00 sqm 380.00 266.00 646.00 646.00
b. #22 1.00 sqm 400.00 280.00 680.00 680.00
c. #20 1.00 sqm 450.00 315.00 765.00 765.00
d. #18 1.00 sqm 480.00 336.00 816.00 816.00
2.2 Flexible Duct 300mm dia 1.00 m 700.00 490.00 1,190.00 1,190.00
2.3 Hangers & Supports 1.00 lot 1,843.65 1,290.56 3,134.21 3,134.21
2.4 Insulation 4.00 sqm 245.00 171.50 416.50 1,666.00
2.5 Misclleanous and Consumable Materials 1.00 lot 890.00 623.00 1,513.00 1,513.00
2.6 Diffusers (300X300) 1.00 pc/s 1,500.00 1,050.00 2,550.00 2,550.00
2.8 Return Grill 1.00 pc/s 20,000.00 12,831.52 32,831.52 32,831.52
2.9 Duct repair 1.00 lot 10,000.00 7,000.00 17,000.00 17,000.00

TOTAL - AIRCONDITIONING WORKS 62,791.73

SUM FOR AIR CONDITIONING WORKS (2F) 262,791.73

AIR CONDITIONING WORKS (1F)

5 AIRCONDITIONING EQUIPMENT

5.1 Everest Cassette Type Inverter 3TR, 220V, 1PH 1.00 pc/s 17,500.00 17,500.00 17,500.00
5.2 Midea Cassette Type Inverter 5TR, 220V, 3PH 1.00 pc/s 150,000.00 18,000.00 168,000.00 168,000.00
5.3 1.00 pc/s
FCU Ceiling Cassette Type 3TR, 220V, 1PH 1.00 pc/s 66,000.00
FCU Wall Mounted Type 1HP, 220V, 1PH 1.00 pc/s 11,000.00

TOTAL - AIRCONDITIONING EQUIPMENT 185,500.00

6 REFRIGERANT PIPING SYSTEM

6.1 Copper Piping, Hard Drawn Type L


a. 3/4" Ø 1.00 m 350.00 175.00 525.00 525.00
b. 1/2" Ø 1.00 m 250.00 125.00 375.00 375.00
c. 5/8" Ø 1.00 m 267.00 133.50 400.50 400.50
d. 3/8" Ø 1.00 m 155.00 77.50 232.50 232.50
6.2 Fittings (Elbow, Tee's & Coupling) 1.00 lot 63.30 31.65 94.95 94.95
6.3 Rubber Insulation 1"Thick
a. 3/4" Ø 1.00 m 170.00 85.00 255.00 255.00
b. 1/2" Ø 1.00 m 130.00 65.00 195.00 195.00
c. 5/8" Ø 1.00 m 150.00 105.00 255.00 255.00
d. 3/8" Ø 1.00 m 95.00 66.50 161.50 161.50
6.4 Miscellaneous and Consumable Materials 1.00 lot 94.95 66.47 161.42 161.42
6.5 Hanger and Supports 1.00 lot 175.59 7,866.84 8,042.43 8,042.43

TOTAL - REFRIGERANT PIPING SYSTEM 9,798.29


PROJECT : COST GUIDELINES
LOCATION :
SUBJECT : Mechanical Works

INHOUSE
Unit Cost (Php)
Item DESCRIPTION Qty Unit Total Cost (Php)
Material Labor Total

7 ELECTRICAL SYSTEM

7.2 Communication Cable 1.00 m 65.00 45.50 110.50 110.50


2
7.3 THHN Stranded Wire #10 1.00 m 45.00 31.50 76.50 76.50
7.4 Liquid Tight Conduit 1.00 m 175.00 122.50 297.50 297.50
7.5 Miscellaneous and Consumable Materials 1.00 lot 48.45 33.92 82.37 82.37

TOTAL - ELECTRICAL SYSTEM 566.87

8 CONDENSATE DRAIN LINE SYSTEM

8.1 PVC pipe 1" 1.00 m 150.00 105.00 255.00 255.00


8.2 Rubber Insulation 1.00 m 105.00 73.50 178.50 178.50
8.3 Hanger and Supports 1.00 lot 43.35 30.35 73.70 73.70
8.4 Miscellaneous and Consumable Materials 1.00 lot 50.72 35.50 86.22 86.22

TOTAL - CONDENSATE DRAIN LINE SYSTEM 593.42

SUM FOR AIR CONDITIONING WORKS (1F) #REF!

FIRE PROTECTION WORKS (Overall)

9 PRELIMINARIES

9.1 Mobilization/Demobilization 1.00 lot 45,000.00 45,000.00


9.2 Permits & Licenses 1.00 lot 20,000.00 20,000.00
9.3 Testing & Commissioning 1.00 lot 25,000.00 25,000.00
9.4 As built & Shopdrawings 1.00 lot 15,000.00 15,000.00
9.5 Site Management 1.00 lot 50,000.00 50,000.00

TOTAL - PRELIMINARIES 155,000.00

10 FIRE SPRINKLER SYSTEM

10.1 BI Pipes
a. 1" Ø 790.00 m 295.00 177.00 472.00 372,880.00
10.2 Hangers & Supports 1.00 lot 37,288.00 22,380.00 59,668.00 59,668.00
10.3 Pipe Fittings 1.00 lot 44,745.60 26,850.00 71,595.60 71,595.60
10.4 Pipe Sealant 1.00 lot 24,794.00 14,880.00 39,674.00 39,674.00
10.5 Painting Works 1.00 lot 18,644.00 13,076.40 31,720.40 31,720.40

TOTAL - FIRE PROTECTION SYSTEM 958,462.00

SUM FOR FIRE PROTECTION WORKS (OVERALL) 1,113,462.00

SUMMARY
AIR CONDITIONING WORKS (2F) 262,791.73

SUBTOTAL #REF!

FIRE PROTECTION WORKS (OVERALL) 1,113,462.00

SUBTOTAL 1,113,462.00

Grand Total #REF!

Prepared by; Noted by; Approved by;

JERICO F. TECSON IAN FRANCIS A. DIZON ARIES M. VICENTE


Mechanical Engineer Production Head Operations Head

You might also like