SPECIAL ECONOMIC ZONE AUTHORITY

Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.No. Description of Works Total Amount Remarks
1 Civil Works 42,460,599.83
2 Electrical Works 2,212,423.35
3 Sanitary Works 1,792,992.65
Total Cost of Building : 46,466,015.83
VAT @ 13% : 6,040,582.06
Grand Total Cost : 52,506,597.88
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
A Civil Works
1 EARTHWORK
1.01 Clearing and grubbing the site for construction by
removing 150mm thick top soil including bushes, small trees,
leveling of undulated ground, shorting and stacking/storing
selected top soil for reuse in landscaping works, disposing
unsuitable materials from site, etc., all complete as per
drawings, specifications and instructions of the Engineer.
sq.m. 2370.00
1.02 Earthwork in Excavation in foundations in all type of soils
for foundation, trenches, footing, pits etc. to the required
depth including dewatering by manual or mechanical means
etc. as per specifications with all contractor’s own machinery
and equipment's, providing crossing of track, shoring,
strutting, timbering and buttressing with appropriate
materials and all such measures necessary to retain in
position the sides of the foundation pit and including refilling
the excavated material with watering, ramming, leveling the
site and disposing off the surplus/unusable earth to outside
the construction premises, etc. all complete as per drawings,
specifications and instructions of the Engineer.

cu.m. 482.41
1.03 Earthwork in Back filling in foundation and sides of
foundation with approved soil obtained from the excavation
at site and stacked at site or brought from outside in layer not
exceeding 15 cm thick (compacted thickness) including
transportation of soil, spreading in required line and level,
sprinkling water, ramming, compacting with mechanical
rammers, testing, etc., all complete as per drawing,
specification and instructions of the Engineer.
cu.m. 1034.58
1.04 Providing, laying Second class chimney made dry flat brick
soling with sand blending inperfect line & level including
proper compaction all complete sq.m. 1590.83
2 CONCRETE WORKS
2.01 Lean Concrete
a) Providing and laying machine mixed Plain Cement
Concrete of M15 grade for leveling course in foundations
and under floor of building, etc. in all level with broken stone
aggregate of size not more than 25 mm of approved quality
including formwork wherever necessary, dewatering,
batching, mixing, transporting, placing, compacting, curing,
including all lead and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.

cu.m. 119.31
2.02 PCC for RCC Works (M20)
a)
Providing, laying , compacting & curing plain cement
Concrete M20 for RCC footings, Raft foundation ,slab,
columns, beams, tie beam, retaining walls and all kinds of
R.C.C. works with cement, sand & stone ballast 40mm down
finishings to approved level, lines & dimensions all complete
as per drawings, specifications & instructions of site
engineer.
b)Sub & Super-structure works cu.m. 466.12
2.03 Formworks
Centering and shuttering with steel or water proof 19mm-
12mm plywood material for all kinds of work including all
necessary propping, scaffolding, staging, supporting etc. all
complete as per drawing, specification, and instruction of site
engineer.
a)Beam,,lintels/Sills. sq.m. 1847.34
b)Column sq.m. 352.16
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
2.04 Reinforcement
a) Providing and fixing in position TMT Fe500 steel
reinforcement of various diameter confirming to relevant IS
code in R.C.C. works including straightening, cutting,
bending, binding with 20 SWG annealed wire for tying the
reinforcement bars at each junctions (binding wire shall not
be measured separately) including all waste and cut pieces,
provision for adequate numbers of spacers, chairs, providing
and placing cement mortar (1:1) cover blocks to keep the
bars in intended position at all levels all complete as per
drawings, specifications and instructions of the Engineer.
(Lap length to be considered for bar length exceeding 10
meter in length).
a) TMT Bars MT 116.53
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
3 MASONRY WORK
3.1 Providing & laying local chimney made brick masonry work
in cement, sand mortar (1:5) in superstructure finished in
perfect line & level including wetting the bricks, packing the
joints & curing the work complete in all thickness of walls as
per drawings,
a) For Foundation and superstructure cu.m. 356.54

4 DOORS/WINDOWS WORKS
4.01 Providing, fabricating & fixing Windows and ventilation of
Upvc frame using Upvc section with 5mm clear float glass,
U-shaped both side plastic gasket, steel hook locks and
screws all accessories as per drawing all complete.
a)Upvc Sliding Window - Section (50x80)mm white color
and 5 mm Glass witn net sq.m. 410.08
4.02 Providing, fabricating and fixing in position Upvc swing door
of anodized Chinese section (100x60)mm using and 5mm
clear glass with handle, standard lock, door stopper and all
other accessories as per design drawings, specifications &
instructions of the site engineer.
sq.m. 78.38
5 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing average 38mm
mm thick screed with 1:2:4 cement sand mortar in perfect
lines & level in whole flooring as per design, specification
and instruction of the site engineer. sq.m. 2630.52
5.02 Providing & laying, 6 mm thick non skid 300 x 300 mm or
600 x 600 mm tiles of Somany,Johnson, cotto or equivalent
with same quality of borderof approved colour , texture &
quality 0ver 38 mm thick screeding with cement sand mortar
(1:3) with grinding and polishing , joint sealing, maintaining
propr slope . level, in perfect line & level all complete as per
design, drawing, pattern, specification & instructionof site
engineer.

a) 6mm Tiles Flooring sq.m. 182.55


5.03 Providing, laying, grinding & polishing 18 mm thick marble
of approved colour and quality in floor with 1:3 c/s mortar
over already screed surface in perfect line & level all
complete as per design, patterns, specification and instruction
of site engineer.
a) 18mm Marble Flooring sq.m. 83.63
5.04 Providing, mixing & applying polymer modified
hydraulically setting water proofing coat of approved make
on floor/roof slab/wall as per manufacturer's specification
and instruction of site engineer.
a)Toilet and Terrace Area sq.m. 1505.58
6 PLASTERING/FINISHING WORKS
6.01
Providing, laying & curing cement sand (1:4) Plastering on
internal & external walls to perfect plumb, lines & level
icluding raking the mortar joints and wetting the masonry
surface all complete as per design drawings, specifications
and instrcution of the site engineer all complete:
a) External Wall Surface (20mm thick) sq.m. 1286.93
b) Internal Wall Surface (20mm thick) sq.m. 632.16
6.02
Providing, laying & curing 12.5 mm thick cement sand (1:3)
plastering in ceiling, beams and column surfaces including
chipping & wetting the concrete surfaces finished in perfect
plumb, lines and level as per drawings, specifications and
instructions of the site engineer. sq.m. 1511.61
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
7 PAINTING WORK
7.01 Providing and applying white wall putty (super fine quality)
punning on internal and external surface with minimum two
coats or more to achieve smooth finish surface in line and
level to the entire satisfaction oif owner including scrapping
and hacking the existing finished surfaces scafolding etc,
complete
sq.m. 3430.69
7.02 Providing and applying two coats of plastic emulsion paint
with one coat of primer coat with specified and approved
shadein two coats over wall putty in wall surface and
ceiling inclusuive of surface preparation of providing
puttying sanding surface, watering(if necessary), cleaning as sq.m. 2143.77
per specifications, drawings and instruction all complete.
7.03 Providing and applying over wall putty surface with
specified two Weather Coat paint of approved shadein one
coat inclusuive of primer coat, surface preparation of
providing puttying sanding surface, watering(if necessary),
cleaning as per specifications, drawings and instruction of the
site engineer
sq.m. 1286.93

8 MISCELLANEOUS WORKS
8.01
Providing, fabrication and fixing in position 32" high 18
gauge stainless steel hand rail (2" dia.) for stair case 4 rows
of 18 gauge 1 inch stainless steel between handrail and floor
with 2 inch dia SS pipe for vertical post at 1.6 m c/c
including welding,cutting all complete as per specifications,
drawings and instruction of the site engineer r.m. 45.00
8.02 Water Tank Stand -(2 x 1000 ltr.) capacity- 2 nos. kg. 500.00
8.03 Spiral Staircase no. 1.00
Total Amount (Excludimg VAT) for Civil Works:
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.N. Description of Works Unit Rate Quantity Amount Remarks

1.00 EARTHWORK
1.01 Clearing and grubbing the site for construction by removing 150mm thick top soil
including bushes, small trees, leveling of undulated ground, shorting and stacking/storing
selected top soil for reuse in landscaping works, disposing unsuitable materials from site, etc.,
all complete as per drawings, specifications and instructions of the Engineer.
sq.m. 6.90 2,370.00 16,353.00
1.02 Earthwork in Excavation in foundations in all type of soils for foundation, trenches,
footing, pits etc. to the required depth including dewatering by manual or mechanical means
etc. as per specifications with all contractor’s own machinery and equipment's, providing
crossing of track, shoring, strutting, timbering and buttressing with appropriate materials and
all such measures necessary to retain in position the sides of the foundation pit and including
refilling the excavated material with watering, ramming, leveling the site and disposing off
the surplus/unusable earth to outside the construction premises, etc. all complete as per
drawings, specifications and instructions of the Engineer.

cu.m. 497.49 482.41 239,996.44


1.03 Earthwork in Back filling in foundation and sides of foundation with approved soil obtained
from the excavation at site and stacked at site or brought from outside in layer not exceeding
15 cm thick (compacted thickness) including transportation of soil, spreading in required line
and level, sprinkling water, ramming, compacting with mechanical rammers, testing, etc., all
complete as per drawing, specification and instructions of the Engineer.

cu.m. 345.00 1,034.58 356,928.98


1.04 Providing, laying Second class chimney made dry flat brick soling with sand blending
inperfect line & level including proper compaction all complete sq.m. 828.35 1,590.83 1,317,766.52
2.00 CONCRETE WORKS
2.01 Lean Concrete
a) Providing and laying machine mixed Plain Cement Concrete of M10 grade for leveling
course in foundations and under floor of building, etc. in all level with broken stone aggregate
of size not more than 25 mm of approved quality including formwork wherever necessary,
dewatering, batching, mixing, transporting, placing, compacting, curing, including all lead
and lift, etc. all complete as per drawings, specifications and the instructions of the Engineer.

cu.m. 11,264.82 119.31 1,344,033.55


2.02 PCC for RCC Works (M20)

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.N. Description of Works Unit Rate Quantity Amount Remarks

a
Providing, laying , compacting & curing plain cement Concrete M20 for RCC footings, Raft
foundation ,slab, columns, beams, tie beam, retaining walls and all kinds of R.C.C. works
with cement, sand & stone ballast 40mm down finishings to approved level, lines &
dimensions all complete as per drawings, specifications & instructions of site engineer.
a) Sub & Super-structure works cu.m. 14,031.20 466.12 6,540,233.27
2.03 Formworks
Centering and shuttering with steel or water proof 19mm-12mm plywood material for all
kinds of work including all necessary propping, scaffolding, staging, supporting etc. all
complete as per drawing, specification, and instruction of site engineer.
a) Beam,,lintels/Sills, Slab. sq.m. 828.35 1,847.34 1,530,241.36
b) Column sq.m. 828.35 352.16 291,711.74
2.04 Reinforcement
Providing and fixing in position TMT Fe500 steel reinforcement of various diameter
confirming to relevant IS code in R.C.C. works including straightening, cutting, bending,
binding with 20 SWG annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all waste and cut pieces, provision
for adequate numbers of spacers, chairs, providing and placing cement mortar (1:1) cover
blocks to keep the bars in intended position at all levels all complete as per drawings,
specifications and instructions of the Engineer. (Lap length to be considered for bar length
exceeding 10 meter in length).

a) TMT Bars MT 126,109.00 116.53 14,695,504.97


3.00 MASONRY WORK
3.01
Providing & laying local chimney made brick masonry work in cement, sand mortar (1:4) in
superstructure finished in perfect line & level including wetting the bricks, packing the joints
& curing the work complete in all thickness of walls as per drawings,
a) For Foundation and superstructure cu.m. 13,113.56 356.54 4,675,561.15
-
4.00 DOORS/WINDOWS WORKS -
4.01 Providing, fabricating & fixing Windows and ventilation of Upvc frame using Upvc section
with 5mm clear float glass, U-shaped both side plastic gasket, steel hook locks and screws all
accessories as per drawing all complete.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.N. Description of Works Unit Rate Quantity Amount Remarks

a)Upvc Sliding Window - Section (50x80)mm white color and 5 mm Glass witn net sq.m. 8,875.70 410.08 3,639,724.87
4.02 Providing, fabricating and fixing in position Upvc swing door of anodized Chinese section
(100x60)mm using and 5mm clear glass with handle, standard lock, door stopper and all
other accessories as per design drawings, specifications & instructions of the site engineer.
sq.m. 9,509.35 78.38 745,295.31
5.00 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing average 38mm mm thick screed with 1:2:4
cement sand mortar in perfect lines & level in whole flooring as per design, specification and
instruction of the site engineer. sq.m. 629.88 2,630.52 1,656,911.94
5.02 Providing & laying, 6 mm thick non skid 300 x 300 mm or 600 x 600 mm tiles of
Somany,Johnson, cotto or equivalent with same quality of borderof approved colour , texture
& quality 0ver 38 mm thick screeding with cement sand mortar (1:3) with grinding and
polishing , joint sealing, maintaining propr slope . level, in perfect line & level all complete
as per design, drawing, pattern, specification & instructionof site engineer.

a) 6mm Tiles Flooring sq.m. 4,439.00 182.55 810,339.45


5.03 Providing, laying, grinding & polishing 16 mm thick marble of approved colour and quality
in floor with 1:3 c/s mortar over already screed surface in perfect line & level all complete as
per design, patterns, specification and instruction of site engineer. -
a) 18mm Marble Flooring sq.m. 4,475.21 83.63 374,261.81
5.04 Providing, mixing & applying polymer modified hydraulically setting water proofing coat of
approved make on floor/roof slab/wall as per manufacturer's specification and instruction of
site engineer.
a)Toilet and Terrace Area sq.m. 657.80 1,505.58 990,367.24
6.00 PLASTERING/FINISHING WORKS
6.01
Providing, laying & curing cement sand (1:4) Plastering on internal & external walls to
perfect plumb, lines & level icluding raking the mortar joints and wetting the masonry surface
all complete as per design drawings, specifications and instrcution of the site engineer all
complete:
a) External Wall Surface (12.5mm thick) sq.m. 345.59 1,286.93 444,749.27
b) Internal Wall Surface (12.5mm thick) sq.m. 345.59 632.16 218,469.00

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.N. Description of Works Unit Rate Quantity Amount Remarks

6.02
Providing, laying & curing 12.5 mm thick cement sand (1:3) plastering in ceiling, beams
and column surfaces including chipping & wetting the concrete surfaces finished in perfect
plumb, lines and level as per drawings, specifications and instructions of the site engineer. sq.m. 401.66 1,511.61 607,151.26

7.00 PAINTING WORK


7.01 Providing and applying white wall putty (super fine quality) punning on internal and external
surface with minimum two coats or more to achieve smooth finish surface in line and level to
the entire satisfaction oif owner including scrapping and hacking the existing finished
surfaces scafolding etc, complete
sq.m. 276.20 3,430.69 947,557.92
7.02 Providing and applying two coats of plastic emulsion paint with one coat of primer coat with
specified and approved shadein two coats over wall putty in wall surface and ceiling
inclusuive of surface preparation of providing puttying sanding surface, watering(if
necessary), cleaning as per specifications, drawings and instruction all complete.
sq.m. 281.32 2,143.77 603,084.64
7.03 Providing and applying over wall putty surface with specified two Weather Coat paint of
approved shadein one coat inclusuive of primer coat, surface preparation of providing
puttying sanding surface, watering(if necessary), cleaning as per specifications, drawings and
instruction of the site engineer
sq.m. 226.33 1,286.93 291,270.30

8.00 MISCELLANEOUS WORKS


8.01
Providing, fabrication and fixing in position 32" high 18 gauge stainless steel hand rail (2"
dia.) for stair case 4 rows of 18 gauge 1 inch stainless steel between handrail and floor with
2 inch dia SS pipe for vertical post at 1.6 m c/c including welding,cutting all complete as per
specifications, drawings and instruction of the site engineer r.m. 424.13 45.00 19,085.85
8.02 Water Tank Stand -(2 x 1000 ltr.) capacity- 2 nos. kg. 138.00 500.00 69,000.00
8.03 Spiral Staircase LS 35,000.00 1.00 35,000.00
Total Amount (Civil) 42,460,599.83

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Summary of Civil Works of Exhibitiion Hall
Super-
Sub-Structure Structure Total
SN Description Unit works Remarks
works Quantity
GF
1 Site Clearance sq.m. 2370.00 2370.00
2 Earthwork in excavation cu.m. 482.41 482.41
3 Earthwork in backfilling cu.m. 1034.58 1034.58
4 Disposal cu.m. 552.16 552.16
5 Brick Soling sq.m. 1590.83 1590.83
5 75 mm PCC M10 in foundation cu.m. 119.31 119.31
6 M20 PCC for RCC cu.m. 153.12 313.00 466.12
7 Fe500 Reinforcement Work Mt 116.53 116.53
8 Formwork sq.m.
a)Beam,,lintels/Sills. 1847.34 1847.34
b)Column 352.16 352.16
9 Brick Works
230 mm Brick (9") cu.m. 140.60 215.94 356.54
10 Plaster Works
20 mm Internal Plaster (1:4) sq.m. 632.16 632.16
20mm External Plaster (1:4) sq.m. 1286.93 1286.93
12.5 mm Ceiling Plaster (1:3) sq.m. 1511.61 1511.61
11 Painitng Works
Wall Putty work sq.m. 3430.69 3430.69
Plastic Emulsion Paint sq.m. 2143.77 2143.77
Weathercoat Paint sq.m. 1286.93 1286.93
12 Flooring Works
Screeding 38 mm sq.m. 2630.52 2630.52
3 mm Cement Punning Work sq.m. 2557.43 2557.43
Floor/Wall Tile in Toilet sq.m. 182.55 182.55
18 mm Marble in Lobby & Staircase sq.m. 83.63 83.63
13 Enamel Paint (For metal works) sq.m.
14 Upvc Casement Door sq.m. 78.38 78.38
15 Upvc Sliding Window sq.m. 410.08 410.08
16 Water Proofing in toilet & Terrace sq.m. 1505.58 1505.58
17 Hand Rail at Staircase R.m. 45.00 45.00

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Excavation and Backfilling Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
Site clearance (Taking boundary line from
1 master plan) 1 Area= 2370.000 2370.00
Total 2,370.00 Sqm.
2 Earthwork Excavation

Isolated footing
F1 4 1.600 1.600 2.00 20.48 Cu.m.
F2 4 2.200 2.200 2.00 38.72 Cu.m.
F3 8 2.200 2.200 2.00 77.44 Cu.m.
F4 8 2.850 2.850 2.00 129.96 Cu.m.

Toe wall (Longitudinal Direction)


Grid 2-2/3-3 2 31.400 0.60 1.35 50.87 Cu.m.
Grid 1-1/4-4 2 34.600 0.60 1.35 56.05 Cu.m.

Toe wall (Transverse Direction)


Grid A-A/F-f 2 20.550 0.60 1.35 33.29 Cu.m.
Grid B-B/C-C/D-D/E-E 4 18.650 0.60 1.35 60.43 Cu.m.
Wall 2 3.500 0.600 0.30 1.26 Cu.m.
Steps 2 9.785 0.600 0.30 3.52 Cu.m.
4 7.950 0.600 0.30 5.72 Cu.m.
2 5.775 0.600 0.30 2.08 Cu.m.
2 7.200 0.600 0.30 2.59 Cu.m.
Total 482.41 Cum.

3 Back filling of Earthwork


a) Footing and Toe Wall
Backfilling @33% of Excavation Work 1 Volume = 159.197 159.20 Cu.m.
b) Room Area (as per Ground Floor Plan)
Area is taken
Pannels 10 Area= 64.226 0.55 353.24 Cu.m. from autocad
drawing of tie
Pannels 5 Area= 92.123 0.55 253.34 Cu.m. beam plan
Wall 2 3.500 5.500 0.63 24.26 Cu.m.
Steps 2 6.185 1.800 0.38 8.46 Cu.m.
4 5.550 1.200 0.38 10.12 Cu.m.
2 2.175 1.800 0.38 2.98 Cu.m.
2 3.600 81.500 0.38 222.98 Cu.m.
Total 1,034.58 Cum.

Prepared By: Checked By: Approved BY:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Concrete Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A. Sub Structure Works
1 PCC(M10) Works
a) Isolated footing
F1 4 1.600 1.600 0.075 0.768 Cu.m.
F2 4 2.200 2.200 0.075 1.452 Cu.m.
F3 8 2.200 2.200 0.075 2.904 Cu.m.
F4 8 2.850 2.850 0.075 4.874 Cu.m.

b) Toe wall
Grid 1-1/2-2/3-3/4-4 4 41.875 0.350 0.075 8.794 Cu.m.

c) Toe wall
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 24.800 0.350 0.075 7.812 Cu.m.

d) Room Area (as per Ground Floor Plan)


Pannels 10 Area= 64.226 0.075 48.170 Cu.m.
Pannels 5 Area= 92.123 0.075 34.546 Cu.m.
Wall 2 3.500 0.600 0.075 0.32 Cu.m.
Steps 2 9.785 0.600 0.075 0.88 Cu.m.
4 7.950 0.600 0.075 1.43 Cu.m.
2 5.775 0.600 0.075 0.52 Cu.m.
2 7.200 0.600 0.075 0.65 Cu.m.
Steps 2 6.185 1.800 0.075 1.67 Cu.m.
4 5.550 1.200 0.075 2.00 Cu.m.
2 2.175 1.800 0.075 0.59 Cu.m.
2 7.200 1.800 0.075 1.94 Cu.m.
Total 119.312 Cum.

2 PCC for RCC (M20) Works


a) Foundation Tie beam & Plinth Tie Beam
Longitudinal Direction
Grid 1-1/2-2/3-3/4-4 4 41.875 0.350 0.350 41.038 Cu.m.
Transverse Direction
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 24.800 0.350 0.350 36.456 Cu.m.

b) Isolated footing
F1 4 Volume = 0.806 3.224 Cu.m.
F2 4 Volume = 1.844 7.375 Cu.m.
F3 8 Volume = 1.854 14.832 Cu.m.
F4 8 Volume = 4.267 34.137 Cu.m.

c) Column upto Plinth lvl


C-550X550 12 0.550 0.550 1.900 6.897 Cu.m.
C-600X600 4 0.600 0.600 1.900 2.736 Cu.m.
C-650X650 8 0.650 0.650 1.900 6.422 Cu.m.

Total 153.116 Cum.


B. Super Structure Works
1 Upto Ground floor Slab Lvl.
PCC for RCC(M20) Works
a) Ground Floor Beam
Main Beam

Prepared bY: Checked by: Approved By:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Concrete Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
Grid 1-1/2-2/3-3/4-4 4 43.350 0.400 0.525 36.414 Cu.m.
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 26.000 0.400 0.525 32.760 Cu.m.
Secondary Beam
Grid 1-1 to 4-4 3 43.250 0.230 0.225 6.715 Cu.m.
Grid A-A to F-F 5 25.500 0.230 0.225 6.598 Cu.m.

Lintel 1 175.820 0.230 0.150 6.066 Cu.m.


Sill 2 145.300 0.230 0.100 6.684 Cu.m.

b) Ground floor slab 1 Area= 1323.025 0.125 165.378 Cu.m.


c) Ground floor column
C-550X550 12 0.550 0.550 6.200 22.506 Cu.m.
C-600X600 4 0.600 0.600 6.200 8.928 Cu.m.
C-650X650 8 0.650 0.650 6.200 20.956 Cu.m.

Total 313.004 Cum.

Prepared bY: Checked by: Approved By:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Masonry Wall Works of Exhibition Hall Block
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A. Brick Flat Soling
a. Isolated footing
F1 4 1.600 1.600 10.24 Sq.m.
F2 4 2.200 2.200 19.36 Sq.m.
F3 8 2.200 2.200 38.72 Sq.m.
F4 8 2.850 2.850 64.98 Sq.m.
b. Below Lower Tie Beam
Grid 1-1/2-2/3-3/4-4 4 41.875 0.350 117.250 Sq.m.
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 24.800 0.350 104.160 Sq.m.

c. Room Area (as per Ground Floor Plan)


Pannels 10 Area= 64.226 642.263 Sq.m.
Pannels 5 Area= 92.123 460.613 Sq.m.
Wall 2 3.500 0.600 4.20 Sq.m.
Steps 2 9.785 0.600 11.74 Sq.m.
4 7.950 0.600 19.08 Sq.m.
2 5.775 0.600 6.93 Sq.m.
2 7.200 0.600 8.64 Sq.m.
Steps 2 6.185 1.800 22.27 Sq.m.
4 5.550 1.200 26.64 Sq.m.
2 2.175 1.800 7.83 Sq.m.
2 7.200 1.800 25.92 Sq.m.
Total 1590.83 Sqm.

B. Brick Wall Works


1 Between Foundation and Plinth Tie Beams
Grid 1-1/2-2/3-3/4-4 4 41.875 0.350 1.20 70.350 Cu.m.
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 24.800 0.350 1.20 62.496 Cu.m.

Steps 2 6.185 0.230 0.45 1.280 Cu.m.


4 5.55 0.230 0.45 2.298 Cu.m.
2 2.175 0.230 0.45 0.450 Cu.m.
2 7.2 0.230 0.45 1.490 Cu.m.
Entrance portion 1 7.000 0.800 0.40 2.240 Cu.m.
Total 140.60 Cum.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Masonry Wall Works of Exhibition Hall Block
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
2 Ground Floor Level
2.1 9" Thick Brick Wall
External wall east and west 2 42.25 0.23 4.35 84.542 Cu.m.
External wall north and south 2 24.80 0.23 4.35 49.625 Cu.m.

Internal wall exhibition hall 6 6.00 0.23 3.35 27.738 Cu.m.


6 8.00 0.23 3.35 36.984 Cu.m.
Conference room wall 1 22.75 0.23 4.88 25.508 Cu.m.
1 8.67 0.23 4.88 9.722 Cu.m.
Entrance portion 1 7.00 0.23 4.88 7.849 Cu.m.
Toilet wall 2 17.20 0.23 4.88 38.571 Cu.m.
3 3.00 0.23 4.88 10.091 Cu.m.
8 1.25 0.23 3.35 7.705 Cu.m.
DEDUCTIONS
C.G. -2 3.55 0.23 4.35 -7.104 Cu.m.
D1 -2 1.1 0.23 2.4 -1.214 Cu.m.
MD1 -3 2.4 0.23 3.5 -5.796 Cu.m.
TD -9 0.9 0.23 2.1 -3.912 Cu.m.
Windows -9 4.00 0.23 5.00 -41.400 Cu.m.
Windows -1 4.00 0.23 9.00 -8.280 Cu.m.
Ventilation -9 0.63 0.23 1.50 -1.941 Cu.m.
Lintel Volume -1 Volume= 6.07 -6.066 Cu.m.
Sill Volume -1 Volume= 6.68 -6.684 Cu.m.
Total 215.94 Cum.

3 Top terrace
3.1 4" Thick Brick Wall
Internal Wall 1 45.00 0.10 1.20 8.64 Cu.m.
1 27.00 0.10 1.20 3.24 Cu.m.
Total 11.88 Cu.m.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Flooring Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
1 Ground Floor
A. Screeding 38 mm
Terrace 1 Area= 1323.03 1323.03 Sq.m.
Ground Floor 1 Area= 1234.41 1234.41 Sq.m.
Outside Foyer I 1 Area= 20.00 20.00 Sq.m.
Staircase 2 Area= 4.12 8.24 Sq.m.
2 Area= 3.60 7.20 Sq.m.
2 Area= 6.60 13.20 Sq.m.
2 Area= 6.66 13.32 Sq.m.
1 Area= 11.13 11.13 Sq.m.
Total 2630.52 Sqm.

B. Cement Punning Works (3 mm)


Ground Floor & Terrace 1 Area= 2557.43 2557.43 Sq.m.
Total 2557.43 Sqm.

C. Water proofing
On Terrace 1 Area= 1323.03 1323.03 Sq.m.
Toilet Floor 1 Area= 54.00 54.00 Sq.m.
Toilet wall 1 Area= 140.70 140.70 Sq.m.
Deduction of ventilation -9 Area= 1.35 -12.15 Sq.m.
Total 1505.58 Sqm.

D. 16mm thick Marble Works


Staircase (Tread and Landing) 1 Area= 53.09 53.09 Sq.m.
Riser portion 5 40.72 0.15 30.54 Sq.m.
Total 83.63 Sqm.

6mm glazed Floor Tiles (600mm X


F. 600mm OR 300mm X 300mm)
Toilet Floor 1 Area= 54.00 54.00 Sq.m.
Toilet wall 1 Area= 140.70 140.70 Sq.m.
Deduction of ventilation -9 Area= 1.35 -12.15 Sq.m.
Total 182.55 Sqm.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Flooring Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
1.0 Foundation
Isolated footing
F1 4 1.600 1.600 0.250 2.560 Sqm.
F2 4 2.200 2.200 0.300 5.808 Sqm.
F3 8 2.200 2.200 0.300 11.616 Sqm.
F4 8 2.850 2.850 0.400 25.992 Sqm.

Column Upto Plinth


C-550X550 12 Perimeter= 2.200 1.900 50.160 Sqm.
C-600X600 4 Perimeter= 2.400 1.900 18.240 Sqm.
C-650X650 8 Perimeter= 2.600 1.900 39.520 Sqm.
153.896 Sqm.
2.0 Foundation Beam/Plinth Beam
Grid 1-1/2-2/3-3/4-4 2 41.875 0.350 58.625 Sqm. (x2)
Grid A-A/B-B/C-C/D-D/E-E/F-F 2 24.800 0.350 34.720 Sqm. (x2)
Total 93.345 Sqm.

3.0 Upto Ground floor Slab Lvl


Ground Floor Slab 1 Area = 1323.025 1323.025 Sqm.
Do around 1 150.100 0.125 18.763 Sqm.
Deduction Column area
C-550X550 -12 Area = 0.303 -3.630 Sqm.
C-600X600 -4 Area = 0.360 -1.440 Sqm.
C-650X650 -8 Area = 0.423 -3.380 Sqm.

Main Beam Ground Floor


Grid 1-1/2-2/3-3/4-4 1 43.350 1.050 45.518 Sqm.
Grid A-A/B-B/C-C/D-D/E-E/F-F 1 26.000 1.050 27.300 Sqm.

Secondary Beam Ground Floor


Grid 1-1 to 4-4 3 43.250 0.450 58.388 Sqm.
Grid A-A to F-F 5 25.500 0.450 57.375 Sqm.

Lintel 2 175.820 0.230 80.877 Sqm.


2 175.820 0.150 52.746 Sqm.
Sill 4 145.300 0.230 133.676 Sqm.
4 145.300 0.100 58.120 Sqm.
Total 1847.337 Sqm.
Column
C-550X550 12 Perimeter= 2.200 6.200 163.680 Sqm.
C-600X600 4 Perimeter= 2.400 6.200 59.520 Sqm.
C-650X650 8 Perimeter= 2.600 6.200 128.960 Sqm.
Total 352.160 Sqm.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Plastering Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
Plastering Work
Plaster 1:4 on Wall Surface
1 Ground Floor
a) Internal Surface
Internal wall exhibition hall 6 6.00 3.35 120.600 Sqm.
6 8.00 3.35 160.800 Sqm.
Conference room wall 1 22.75 4.88 110.906 Sqm.
1 8.67 4.88 42.271 Sqm.
Toilet wall 2 17.20 4.88 167.700 Sqm.
3 3.00 4.88 43.875 Sqm.
8 1.25 3.35 33.500 Sqm.
D1 -2 1.1 2.4 (5.280) Sqm.
MD1 -3 2.4 3.5 (25.200) Sqm.
TD -9 0.9 2.1 (17.010) Sqm.
Total 632.162 Sqm.
b) Ceiling portion
Ground Floor Slab 1 Area = 1323.025 1,323.025 Sqm.
Main Beam Ground Floor
Grid 1-1/2-2/3-3/4-4 1 43.350 1.050 45.518 Sqm.
Grid A-A/B-B/C-C/D-D/E-E/F-F 1 26.000 1.050 27.300 Sqm.

Secondary Beam Ground Floor


Grid 1-1 to 4-4 3 43.250 0.450 58.388 Sqm.
Grid A-A to F-F 5 25.500 0.450 57.375 Sqm.

Total 1,511.605 Sqm.


c) External Surface
External Wall 1 145.30 5.00 726.500 Sqm.
Entrance portion 1 7.00 6.75 47.250 Sqm.
Columns
C-550X550 12 Perimeter = 2.200 6.200 163.680 Sqm.
C-600X600 4 Perimeter = 2.400 6.200 59.520 Sqm.
C-650X650 8 Perimeter = 2.600 6.200 128.960 Sqm.
Outer Ceiling 1 Area = 148.50 148.500 Sqm.
Apron 1 193.000 1.65 318.450 Sqm.
Deductions
C.G. -2 3.55 4.35 (30.885) Sqm.
D3 -4 2.40 3.50 (33.600) Sqm.
TD -9 0.90 2.10 (17.010) Sqm.
Windows -9 4.00 5.00 (180.000) Sqm.
Windows -1 4.00 9.00 (36.000) Sqm.
Ventilation -9 0.63 1.50 (8.438) Sqm.
Total 1,286.928 Sqm.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Paint Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
Painting Works
Ground Floor
1 Painting (Wall Surface)
External Total 1,286.93 sqm
Internal Total 632.16 sqm
Ceiling Total 1,511.61 sqm

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Door and Window Works of Exhibition Hall
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
1 Ground Floor
b) Upvc Works
Doors (Upvc)
Door(D1) 2 3.55 4.35 30.885 Sq.m.
Door(D2) 2 1.1 2.4 5.28 Sq.m.
D3 3 2.4 3.5 25.2 Sq.m.
TD 9 0.9 2.1 17.01 Sq.m.

Total 78.38 Sqm.


Windows (Upvc)
WindowsDoors 12 4.00 7.25 348 Sq.m.
Windows 1 4.00 9.00 36 Sq.m.
Windows 2 4.90 1.80 17.64 Sq.m.
Ventilation 9 0.63 1.50 8.4375 Sq.m.
Total 410.08 Sqm.

Prepared by: Checked by: Approved by:


SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Miscellaneous Works of Canteen Block
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
1 Hand Railing

Handrail on staircase 1 Total 45.00 Rm.

2 Water Tank Stand -(2 x 1000 ltr.) capacity


1 Total 250.00 Kg.

Prepared by: Checked by: Approved by: