Professional Documents
Culture Documents
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.No. Description of Works Total Amount Remarks
1 Civil Works 42,460,599.83
2 Electrical Works 2,212,423.35
3 Sanitary Works 1,792,992.65
Total Cost of Building : 46,466,015.83
VAT @ 13% : 6,040,582.06
Grand Total Cost : 52,506,597.88
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
A Civil Works
1 EARTHWORK
1.01 Clearing and grubbing the site for construction by
removing 150mm thick top soil including bushes, small trees,
leveling of undulated ground, shorting and stacking/storing
selected top soil for reuse in landscaping works, disposing
unsuitable materials from site, etc., all complete as per
drawings, specifications and instructions of the Engineer.
sq.m. 2370.00
1.02 Earthwork in Excavation in foundations in all type of soils
for foundation, trenches, footing, pits etc. to the required
depth including dewatering by manual or mechanical means
etc. as per specifications with all contractor’s own machinery
and equipment's, providing crossing of track, shoring,
strutting, timbering and buttressing with appropriate
materials and all such measures necessary to retain in
position the sides of the foundation pit and including refilling
the excavated material with watering, ramming, leveling the
site and disposing off the surplus/unusable earth to outside
the construction premises, etc. all complete as per drawings,
specifications and instructions of the Engineer.
cu.m. 482.41
1.03 Earthwork in Back filling in foundation and sides of
foundation with approved soil obtained from the excavation
at site and stacked at site or brought from outside in layer not
exceeding 15 cm thick (compacted thickness) including
transportation of soil, spreading in required line and level,
sprinkling water, ramming, compacting with mechanical
rammers, testing, etc., all complete as per drawing,
specification and instructions of the Engineer.
cu.m. 1034.58
1.04 Providing, laying Second class chimney made dry flat brick
soling with sand blending inperfect line & level including
proper compaction all complete sq.m. 1590.83
2 CONCRETE WORKS
2.01 Lean Concrete
a) Providing and laying machine mixed Plain Cement
Concrete of M15 grade for leveling course in foundations
and under floor of building, etc. in all level with broken stone
aggregate of size not more than 25 mm of approved quality
including formwork wherever necessary, dewatering,
batching, mixing, transporting, placing, compacting, curing,
including all lead and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
cu.m. 119.31
2.02 PCC for RCC Works (M20)
a)
Providing, laying , compacting & curing plain cement
Concrete M20 for RCC footings, Raft foundation ,slab,
columns, beams, tie beam, retaining walls and all kinds of
R.C.C. works with cement, sand & stone ballast 40mm down
finishings to approved level, lines & dimensions all complete
as per drawings, specifications & instructions of site
engineer.
b)Sub & Super-structure works cu.m. 466.12
2.03 Formworks
Centering and shuttering with steel or water proof 19mm-
12mm plywood material for all kinds of work including all
necessary propping, scaffolding, staging, supporting etc. all
complete as per drawing, specification, and instruction of site
engineer.
a)Beam,,lintels/Sills. sq.m. 1847.34
b)Column sq.m. 352.16
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
2.04 Reinforcement
a) Providing and fixing in position TMT Fe500 steel
reinforcement of various diameter confirming to relevant IS
code in R.C.C. works including straightening, cutting,
bending, binding with 20 SWG annealed wire for tying the
reinforcement bars at each junctions (binding wire shall not
be measured separately) including all waste and cut pieces,
provision for adequate numbers of spacers, chairs, providing
and placing cement mortar (1:1) cover blocks to keep the
bars in intended position at all levels all complete as per
drawings, specifications and instructions of the Engineer.
(Lap length to be considered for bar length exceeding 10
meter in length).
a) TMT Bars MT 116.53
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
EXHIBITION HALL at GPZ , Simara
Bill of Quantities (BOQ) -Part A - Civil Works
Rate (NPR)
SN Description Unit Quantity Amount Remarks
In Figure In words
3 MASONRY WORK
3.1 Providing & laying local chimney made brick masonry work
in cement, sand mortar (1:5) in superstructure finished in
perfect line & level including wetting the bricks, packing the
joints & curing the work complete in all thickness of walls as
per drawings,
a) For Foundation and superstructure cu.m. 356.54
4 DOORS/WINDOWS WORKS
4.01 Providing, fabricating & fixing Windows and ventilation of
Upvc frame using Upvc section with 5mm clear float glass,
U-shaped both side plastic gasket, steel hook locks and
screws all accessories as per drawing all complete.
a)Upvc Sliding Window - Section (50x80)mm white color
and 5 mm Glass witn net sq.m. 410.08
4.02 Providing, fabricating and fixing in position Upvc swing door
of anodized Chinese section (100x60)mm using and 5mm
clear glass with handle, standard lock, door stopper and all
other accessories as per design drawings, specifications &
instructions of the site engineer.
sq.m. 78.38
5 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing average 38mm
mm thick screed with 1:2:4 cement sand mortar in perfect
lines & level in whole flooring as per design, specification
and instruction of the site engineer. sq.m. 2630.52
5.02 Providing & laying, 6 mm thick non skid 300 x 300 mm or
600 x 600 mm tiles of Somany,Johnson, cotto or equivalent
with same quality of borderof approved colour , texture &
quality 0ver 38 mm thick screeding with cement sand mortar
(1:3) with grinding and polishing , joint sealing, maintaining
propr slope . level, in perfect line & level all complete as per
design, drawing, pattern, specification & instructionof site
engineer.
8 MISCELLANEOUS WORKS
8.01
Providing, fabrication and fixing in position 32" high 18
gauge stainless steel hand rail (2" dia.) for stair case 4 rows
of 18 gauge 1 inch stainless steel between handrail and floor
with 2 inch dia SS pipe for vertical post at 1.6 m c/c
including welding,cutting all complete as per specifications,
drawings and instruction of the site engineer r.m. 45.00
8.02 Water Tank Stand -(2 x 1000 ltr.) capacity- 2 nos. kg. 500.00
8.03 Spiral Staircase no. 1.00
Total Amount (Excludimg VAT) for Civil Works:
SPECIAL ECONOMIC ZONE AUTHORITY
Tripureshwor, Kathmandu
Cost Estimate of EXHIBITION HALL at GPZ , Simara
S.N. Description of Works Unit Rate Quantity Amount Remarks
1.00 EARTHWORK
1.01 Clearing and grubbing the site for construction by removing 150mm thick top soil
including bushes, small trees, leveling of undulated ground, shorting and stacking/storing
selected top soil for reuse in landscaping works, disposing unsuitable materials from site, etc.,
all complete as per drawings, specifications and instructions of the Engineer.
sq.m. 6.90 2,370.00 16,353.00
1.02 Earthwork in Excavation in foundations in all type of soils for foundation, trenches,
footing, pits etc. to the required depth including dewatering by manual or mechanical means
etc. as per specifications with all contractor’s own machinery and equipment's, providing
crossing of track, shoring, strutting, timbering and buttressing with appropriate materials and
all such measures necessary to retain in position the sides of the foundation pit and including
refilling the excavated material with watering, ramming, leveling the site and disposing off
the surplus/unusable earth to outside the construction premises, etc. all complete as per
drawings, specifications and instructions of the Engineer.
a
Providing, laying , compacting & curing plain cement Concrete M20 for RCC footings, Raft
foundation ,slab, columns, beams, tie beam, retaining walls and all kinds of R.C.C. works
with cement, sand & stone ballast 40mm down finishings to approved level, lines &
dimensions all complete as per drawings, specifications & instructions of site engineer.
a) Sub & Super-structure works cu.m. 14,031.20 466.12 6,540,233.27
2.03 Formworks
Centering and shuttering with steel or water proof 19mm-12mm plywood material for all
kinds of work including all necessary propping, scaffolding, staging, supporting etc. all
complete as per drawing, specification, and instruction of site engineer.
a) Beam,,lintels/Sills, Slab. sq.m. 828.35 1,847.34 1,530,241.36
b) Column sq.m. 828.35 352.16 291,711.74
2.04 Reinforcement
Providing and fixing in position TMT Fe500 steel reinforcement of various diameter
confirming to relevant IS code in R.C.C. works including straightening, cutting, bending,
binding with 20 SWG annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all waste and cut pieces, provision
for adequate numbers of spacers, chairs, providing and placing cement mortar (1:1) cover
blocks to keep the bars in intended position at all levels all complete as per drawings,
specifications and instructions of the Engineer. (Lap length to be considered for bar length
exceeding 10 meter in length).
a)Upvc Sliding Window - Section (50x80)mm white color and 5 mm Glass witn net sq.m. 8,875.70 410.08 3,639,724.87
4.02 Providing, fabricating and fixing in position Upvc swing door of anodized Chinese section
(100x60)mm using and 5mm clear glass with handle, standard lock, door stopper and all
other accessories as per design drawings, specifications & instructions of the site engineer.
sq.m. 9,509.35 78.38 745,295.31
5.00 FLOOR FINISHINGS
5.01 a)Providing, laying, compacting and curing average 38mm mm thick screed with 1:2:4
cement sand mortar in perfect lines & level in whole flooring as per design, specification and
instruction of the site engineer. sq.m. 629.88 2,630.52 1,656,911.94
5.02 Providing & laying, 6 mm thick non skid 300 x 300 mm or 600 x 600 mm tiles of
Somany,Johnson, cotto or equivalent with same quality of borderof approved colour , texture
& quality 0ver 38 mm thick screeding with cement sand mortar (1:3) with grinding and
polishing , joint sealing, maintaining propr slope . level, in perfect line & level all complete
as per design, drawing, pattern, specification & instructionof site engineer.
6.02
Providing, laying & curing 12.5 mm thick cement sand (1:3) plastering in ceiling, beams
and column surfaces including chipping & wetting the concrete surfaces finished in perfect
plumb, lines and level as per drawings, specifications and instructions of the site engineer. sq.m. 401.66 1,511.61 607,151.26
Isolated footing
F1 4 1.600 1.600 2.00 20.48 Cu.m.
F2 4 2.200 2.200 2.00 38.72 Cu.m.
F3 8 2.200 2.200 2.00 77.44 Cu.m.
F4 8 2.850 2.850 2.00 129.96 Cu.m.
b) Toe wall
Grid 1-1/2-2/3-3/4-4 4 41.875 0.350 0.075 8.794 Cu.m.
c) Toe wall
Grid A-A/B-B/C-C/D-D/E-E/F-F 6 24.800 0.350 0.075 7.812 Cu.m.
b) Isolated footing
F1 4 Volume = 0.806 3.224 Cu.m.
F2 4 Volume = 1.844 7.375 Cu.m.
F3 8 Volume = 1.854 14.832 Cu.m.
F4 8 Volume = 4.267 34.137 Cu.m.
3 Top terrace
3.1 4" Thick Brick Wall
Internal Wall 1 45.00 0.10 1.20 8.64 Cu.m.
1 27.00 0.10 1.20 3.24 Cu.m.
Total 11.88 Cu.m.
C. Water proofing
On Terrace 1 Area= 1323.03 1323.03 Sq.m.
Toilet Floor 1 Area= 54.00 54.00 Sq.m.
Toilet wall 1 Area= 140.70 140.70 Sq.m.
Deduction of ventilation -9 Area= 1.35 -12.15 Sq.m.
Total 1505.58 Sqm.