Professional Documents
Culture Documents
Annexure - B
Page 1 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
A. Civil & Structural Works
1 1,471 CLEARING SITE As AP SOR 3.18 Sqm 4,678
Clearing light Jungle
2 Earth work excavation for foundations and depositing on bank for all lifts
and with an initial lead of 10m including all operational, incidental,
labour charges such as shoring, sheeting, planking, strutting, etc.
complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308).
4 217 Pre construction Anti termite is a process in which chemical toxic to BMT-H. 66 170.42 Sqm 36,981
subterrean termites is apply/ inject into soil during early stage of
building Construction
2. Treatement of soil Beneath the building and around the
foundations conduct and chemical use as per BIS - IS 6313 (Part -2) 2013
code specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or repels
terminates & impervious to tremite entry.
3. Imidacloprid 30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter
of water and apply emulsion/solution @ 7.5 Litres/Square meter (Sqm)
of internal, external vertical surface of the colums , plinth beams (Back
filling) walls and floor junction, external perimeters, along reatining wall @
5.0 Liters/Sqm of the horizontal surface of basement top surface of the
basement filling below flooring bed (Plinth) & @ 2.0 Litres/ Line meter
at expansion joints. The substructure of a depth of 500mm around
coulmns & 300mm deep around plinth beams, basements & floor
filling area including excavation channel along the wall & rodding etc.
cost & Conveyance of all materials to the site, cost of labour for
sparying, rodding etc. complete for furnished item of work as per the
approval of the Engineer-in-charge
5 136 Supply and laying of Soling stone of 150 mm size with initial lead in layers BLD-CSTN-2-9 583.00 Cum 79,288
not exceeding 15 cm thick, consolidating each deposited layer by watering
and ramming including cost and conveyance of water to work site and all
operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
6 91 Providing and laying Plain Cement concrete (1:5:10) using 40mm metal BLD-CSTN-2-7 3,657.47 Cum 3,32,830
with Concrete mixture. The rate shall be including of all materials, lif, lead
and other related works etc to complete.
7 22 Providing and laying CRS Masonry in CM (1:6) including curing, scaffolding BLD-CSTN-4-iv 4,434.67 Cum 97,563
etc. The rate shall be including of all materials, lift, lead and other related
works etc. to complete.
Page 2 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
8 Supply and placing of the Design Mix Concrete (waterproofing Concrete)
M25 By using 380 Kg/Cum (RMC) corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, finishing curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402)with minimum cement content as per IS code from
standard suppliers approved by the department including
pumping, centering, shuttering, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication charges for
finished item of work
8.1 242 For Swimming pool base slab / Toilet Block Footing BLD-CSTN-2-14 (A) 8,925.37 Cum 21,59,940
8.2 150 For Swimming pool wall / Pedestals etc., BLD-CSTN-2-14 (A) 9,487.85 Cum 14,23,178
10 1.51 work including supplying, fabricating, cutting, assembling, hoisting and As AP SOR 1,03,287.94 MT 1,55,965
fixing in position at all heights of all shapes and size with all leads and lifts
as per latest IS 4923, IS 1161, IS 806 for the It should be including necessary
joists, holow pipe, gusset plates, etc., including cutting and welding the
members as per detailed drawing and design. The rate shall include 1 coat
of Zinc chromate primer and 2 coat of Approved Paint to over all the
surfaces of the steel sections. It should also include the cost of Labour
charges for fixing in position and nut-bolt and Anchor fasteners of Hilti or
Fisher as approved by engineer-in-charge. (For Main Entrance MS Gate /
Compound wall / Window / Ventilator Grill work and Miscellaneous
Works)
Page 3 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
11 169 SPECIALISED HIGH PERFORMANCE ACRYLIC POLYMER MODIFIED BMT-H.71 539.67 Sqm 91,204
ELASTOMERIC CEMENTITIOUS WATERPROOF COATING TO THE TERRACE
a). Providing and application of one coat of High performance Acrylate
penetrative water barrier primer – ROOFBOND BCS (Armstrong ) /
ZORIBOND BCS (PMCC) / POWER n PENETRATE (EBT) / WATERSHIELD
CP / DECKGUARD CP (Fosroc) /SIKAGARD 705 L (Sika )diluting with
water at 1 : 0.50 ratio as a primer coat at a consumption of 200ml per
Sqm.
b). Providing and laying of Non woven polyster reinforced fibre mesh
of 40 GSM, with 1 Mtr width and 50mm
overlap on the primed surface. c) Providing and application of one coat of
Two part system of high performance acrylic polymer modified
elastomeric cementitious waterproof coating ROOFBOND RFX
(Armstrong) /POWER n COAT RFX (EBT) / BRUSHBOND RFX
(Fosroc)/ZORIBOND RFX (PMCC) / WATERSHIELD RFX / SIKAGARD 550
U 2K (Sika) mixing of powder and liquid as per packing at 1:2 ratio.
(add the water upto 200ml) at a consumption rate of 300 Grams mix.
d). Providing and application of one coat of Two parts system fibre
Reinforced Acrylic Cementitious Coatings with - ROOFBOND FRC
(Armstrong) ZORIBOND FRC ( PMCC) /
POWER n BOND FRC (EBT)/ WATERSHIELD BOND FR / Fosroc mixing of
powder and liquid as per packing at 1:2 ratio (add the water upto 200ml )
at a consumption rate of 300 Grams mix.
12 1,110 Filling with useful available excavated earth (excluding rock) in trenches, BLD-CSTN- 2-9 32.94 Cum 36,563
sides of foundations and basement with initial lead in layers not exceeding
15 cm thick, consolidating each deposited layer by watering and
ramming including cost and conveyance of water to work site and all
operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
Architectural Works
13 Providing and laying 230mm thk brick work CM 1:6 using common burnt
clay conventional building bricks conforming to IS 1077-1992 having
compressive strength not less than 50 Kg/cm2 in any shape and all depth
including curing, scaffolding etc. complete as directed by engineer-in-
charge in CM 1:6.
Page 4 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
16 External Wall Plastering : Providing and applying Plastering with CM 2
coats 12mm base coat and 8mm thk top coat, (total 20mm thick) for Brick
work, RC walls, RC columns, masonry piers, masonry walls, etc., in cement
mortar 1:4, 20mm thick finishing to line and level with all scaffolding,
curing, etc., complete. with all lead and lift and as directed by Engineer-
Incharge, complete at all levels.
18 928 Internal Wall / Ceiling : Painting to new walls 1-coat primer with 2-coats BLD-CSTN-10-1 144.93 Sqm 1,34,495
of acrylic emulsion paint interior grade having VOC (Volatile Organic
Compound) content less than 50 grams/ liter of approved brand and
shade over a base coat of appropriate primer of approved brand,
making 3 coats in all to give an even shade after thourughly
brushing the surface to remove all dirt and remains of loose
powdered materials, including cost and conveyance of all materials
to work site and all operational, incidental, labour charges etc. complete
for finished item of work as per SS 911.
19 979 External Wall : Painting to External walls 1-coat primer with 2 coats of BLD-CSTN-10-5 252.48 Sqm 2,47,178
acrylic emulsion paint weather proof water-based, modified acrylic with
silicon additives exterior grade having VOC (Volatile Organic Compound )
content less than 50 grams/ liter. shade, in all to give an even shade
after hourughly brushing the surface to remove all dirt and remains of
loose powdered materials, including cost and conveyance of all
materials to work site and all operational, incidental, labour charges etc.
complete for finished item of work as per SS 911.
20 70 Providing and applying enamel paint - of approved make and colour as per BLD-CSTN-10-12- 243.99 Sqm 17,079
the manufacturers specifications, in minimum two coats to get and even viii
finish and shade obtained over one coat of primer, including preparation of
surface, Cleaning after completion, wherever required, etc, complete. Rate
to include all materials, wastages, labour, all in compliance to the drawings
or as specified by the Engineer-Incharge.
21 1,006 Swimming pool floor / wall : Supply of glazed full body porcelain tiles BLD-CSTN-7-5 1,210.01 Sqm 12,17,270
for+C632 external cladding purposes of any size and thickness between 6-
10 mm 1st quality, set over base coat of cement mortar (1:8), 12 mm
thick, including cementitious grout RCC slab / wall, (Tile Grout and Epoxy
grout) including neat cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement paste to full
depth mixed with pigment of matching shade, including cost of all
materials like cement, sand water and tiles etc., complete, including
seigniorage charges, etc., complete for finished item of work
22 34 Office / Coach / Store Room : High polished granite 18 mm thick slabs BLD-CSTN-7-5 3,965.69 Sqm 1,34,833
other than black set over base coat of cement mortar (1:8), 20 mm thick
over CC bed already laid or RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste mixed with pigment of matching shade to full depth,
including cost of allmaterials like cement, sand water and tilesetc.,
complete, including seigniorage charges, labour charges for dressing of
tilesetc., complete for finished item of work, but excluding the cost of
conveyance of all materials
Page 5 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
23 518 Pool Deck (Around Pool Area) : Sadar Ali Granite (double line dressing) BLD-CSTN-7-7 1,871.18 Sqm 9,69,271
20mm thick slabs other than black set over base coat of cement mortar
(1:8), 20 mm thick over CC bed already laid or RCC roof slab, including neat
cement slurry of honey like consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like cement,
sand water and tilesetc., complete, including seigniorage charges, labour
charges for dressing of tilesetc., complete for finished item of work.
24 300 Supply and laying and internal walls to required heigh with glazed full BLD-CSTN-7-18 1,068.52 Sqm 3,20,556
body porcelain wall tiles of size 600 x 1200 mm with any type of design
texture such as marble finish, wooden, bamboo, stone finishes etc.,
scratch less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs and finish in all shades and
designs of any colour and finish in all shades and designs of any colour
and finish in all shades and designs 7.30 mm thick length equal to flooring
stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with pigment of matching
shade to full depth, including cost of all materials like tiles, cement,
sand and water etc., complete for finished. (For Toilet wall / Shower
area etc.,)
25 149 Supply and Layiong of Supply of soluble salt porcelain vitrified tiles BLD-CSTN-7-6 977.76 Sqm 1,45,686
screen printed and polished of size 600 x 600 mm and thickness between 8-
10mm 1st quality conforming in all shades and designs of any colour and
finish in all shades and designs of any colour and finish in all shades and
designs set over base coat of cement mortar (1:8), 12 mm thick over CC bed
already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white
cement paste to full depth mixed with pigment of matching shade,
including cost of all materials like cement, sand water and tiles etc.,
complete for finished item of work. (For Toilet floor)
27 5 Supply & Fixing of Door Shutter made out of solid bond wood block board As AP SOR 13,625.64 Nos 68,128
type with teak ply on both faces.: 35 mm thick conforming to IS:2202
including all hardwares item and as per drawing and stickers indicating
location of the hardware (Tower bolts, Hings, Oxidised aldrop with bolts,
Wind cleats with hings, Heavy duty mortise lock, Door Stoppers, Screws
etc.,) pasted at appropriate places, etc complete.
Page 6 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
28 7 Providing and fixing factory made uPVC white colour fixed glazed BMT-P.79 6,623.75 Sqm 46,366
Windows / Ventilators comprising of uPVC multi-chambered frame
andmullion (where ever required) extruded profiles duly reinforced with
1.60± 0.2 mm thick galvanized mild steel section made from roll
forming process of required length (shape & size according to uPVC
profile),uPVC extruded glazing beads of appropriate dimension,
EPDM gasket,G.I fasteners 100 x 8 mm size for fixing frame to finished wall,
plasticpackers, plastic caps and necessary stainless steel screws etc.
Profileof frame shall be mitred cut and fusion welded at all corners,
mullion (ifrequired) shall be also fusion welded including drilling of
holes for fixinghardware's and drainage of water etc. After fixing
frame the gap betweenframe and adjacent finished wall shall be filled
with weather proof siliconsealant over backer rod of required size
and of approved quality, allcomplete as per approved drawing &
direction of Engineer-in-Charge inclusive of cost of Single / double
29 17 Supply & Fixing SOLID STEEL DOOR door shutter made out of G I Precoated BMT-N.52 1,590.61 Sqm 27,040
Sheet with an average wall thickness of 0.35 mm on both sides. MS Tube
having dimensions of 19 x 19mm is inserted along the hinge side of the
door, core of the door shutter filled with High Density Polyurethane foam
injected with the help of hydraulic injection method, four sides of the
door covered with G I Precoated Sheet and the hardware locations
reinforced with suitable wooden blocks as per drawing and stickers
indicating location of the hardware pasted at appropriate places, etc
complete.
30 4 Supply of material, delivery at site of Swimming Pool Chair (Pool Lounge Quotation 7,000.00 Nos 28,000
Chair), complete for finished item of work, (Material approval by client).
31 60 Supply, delivery of material and fixing at site of Stadium Chair complete for Quotation 1,850.00 Nos 1,11,000
finished item of work, (Material approval by client).
32 12 Supply, delivery of material and fixing at site of Toilet Cubicles (Toilet / Quotation 28,000.00 Nos 3,36,000
Shower area) size 2003 x 900 x 1550 mm (H X W X D), Merino or equalant
complete for finished item of work, (Material approval by client).
Page 7 of 54
Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in
Tirupati
Abstract
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5 6 7
B. Tensile roof
1 1,008 Scope of Work Quotation 4,105.83 Sqm 41,38,677
Providing, Design, Engineering, Supply, Fabrication, Erection and installation of
Fabric Tensile Membrane Structure Roof.
Europian Architecture Membrane
P.V.C. membrane available in range of U.V. Stabilized color , gsm ,Tear
strength30/28 daN and Varnish both side and Maximum operating temperatures -
30* C/+ 70* C . Heat welded at joints.Membrane Joints are heat welded so there is
no waterproofing no maintenance required.
Membrane shall be PVC/ PVDF coated with following Characteristics.
Yarn:High Tenacity Polyester Yarn PES HT 1100 Dtex
Coated fabric Weight:950 g/m²+- 50
Width267 cm
Tensile Strength Warp/ We : 4200/ 4000 N/ 5cm
Tear Strength Warp/ We : 550/ 500 N
Flame Retardancy: Bs2d0 – EN 1350-1
Surface treatment (Top/ Back):PVDF Alloy/ PVDF
Making Up Weldable
Total Thickness:0.72 mm
Micro Organism Resistance Method A, Degree 0 Excellent – ENISO 846-A
Quality Management:ISO 9001
Environmental ManagementISO 14021
Warranty:12 years
Maximum Temperatures sustained by installed membrane: - 30ºC/ + 70 ºC
DESIGN:-
A.IS 875Part III will be used for design Part
B.The en re model will be analyzed in specialized non linear so ware
C.Detailing of membrane & steel includes pa erning & connec on design.
Materials:-
1 STEEL:-
A.All steel members will be CHS/SHS/RHS con rming to IS 1161 / 1239 / 4239 of
min 240 YST.
B.Built up members will be made from plates marked with IS2062. Yst 240/350 as
per design.
C. Foundation bolts will be of 8.8Gr steel.
D. All nut bolts will be 4.8/8.8 gr. Steel hot dip galvanized.
.2 MEMBRANE:-
a.Cables will be 1570Nmm2 galvanized steel core.
b.All corner plates will be pro le cut & in Stainless Steel.
c.Fabric Clamping will be done with aluminum alloy ats & extrusions.
d.Keder will be made of S.s. Wire rope 10/12mm as per requirement.
e.Fabric clamping with 4.8 GI nuts bolts hot dip galvanized.
.3 PAINTING ON ADDITIONAL STEEL:-
a.All steel members will be cleaned with Scrubbing Rap
Page 8 of 54
Proposed Construction of Swimming Pool at Vinayak Sagar Lake, Karkambadi
Road under implementation of the Smart City Mission in Tirupati
MEP WORKS
AMOUNT IN
Sl No DESCRIPTION Remarks
INR
1 MEP Works for Swimming Pool equipments 44,61,567.00
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
A. MEP Works
FILTRATION EQUIPMENT
1 PRESSURE FILTERS
2 TOTALLY ANTI-CORROSIVE Polyester + Quotation 4,55,000.00 Nos 9,10,000.00
Fibre Glass filter 2000mm diameter. Green colour.
Fitted with pressure gauge panel, manual air
bleeder, water drain and emptying plug.
Fitted with collector arms and diffuser made
from unplasticized PVC and polypropelene.
Filtration velocity 40m³/hr/m². Maximum
working pr. : 2.5 kg/cm². Flow rate = 125m³/hr.
Make : Aquanautics
3 FILTER MEDIA
8,900 Silax media 0.5-1 mm and 2mm course and fine Quotation 12.00 Kgs 1,06,800.00
4 RECIRUCLATING PUMP
3 Cast Iron Pumps, 3000 r.p.m. Mechanical Seal in Quotation 1,93,900.00 Nos 5,81,700.00
Stainless steel. IP-54 motor protection.
Stainless Steel Shaft AISI-420 shaft.
With AISI-316 strainer basket. Conn. PN-16.
according to DIN-2501.
Maximum Output : 15 HP. Voltage 230/400V. 3 ph.
Flow rate of 125m³/hr @ 12 m. water head.
(2 working and 1 standby)
Make : Aquanautics
5 DOSING PUMPS
1 Membrane Dosing Pumps aqua model. Quotation 62,000.00 set 62,000.00
Electronic dosing pump to be mounted both on
its base as well as hung on the wall. Pumps
following CE regulations. IP- 65 protection.
Power connections : 220/240V, 50/60 Hz. The
materials in contact with liquid are : Ploypropylene,
Viton, Teflon and PVC. Includes anti-acid plastic
case. Operating panel protection provided by
a transparent polycarbonate
cover. Lubrication not required. Flow 20l/hr @ 5 bar
Make : Edose/EQ
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
8 MAIN DRAIN
2 Main Drains in Stainless Steel grille,polished Quotation 28,000.00 Nos 56,000.00
AISI -304 ,Size : 450mm x 450mm
Make : CP
10 FLOOR INLET
45 White ABS plastic bottom inlet for concrete Quotation 950.00 Nos 42,750.00
with S.S. screws and reg. flow. Flowrate = 6,000l/hr
Make : Aquanautics
12 OVERFLOW GRATING
50 Made in white, U.V. Stabilized PP. Running Length : 100m Quotation 1,450.00 Rmt 72,500.00
Width: 295mm, Height : 25mm
Make : cp
Make : Aquanautics
UNDERWATER ILLUMINATION FOR MAIN POOL
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
Make : Aquanautics
MAINTENANCE ACCESSORIES
22 1 Transparent blue plastic vacuum hose 2" dia Quotation 8,600.00 Nos 8,600.00
30mtrs long including hose cuffs for connection to
suction inlets.
Make : Aquanautics
23 1 Deep bag net made in polypropelene and white Quotation 1,800.00 Nos 1,800.00
polyester netting butterfly nut connection
Make : Aquanautics
24 1 Surface net made in polypropelene and white Quotation 1,450.00 Nos 1,450.00
polyester netting butterfly connection
Make : Aquanautics
25 1 Curved brushes made in polypropelene for pool Quotation 1,350.00 Nos 1,350.00
basins and scum liners
Make : Aquanautics
26 1 Straight brushes made in polypropelene for pool Quotation 1,250.00 Nos 1,250.00
basins and scum liners
Make : Aquanautics
27 1 Algae brushes with stainless steel bristles Quotation 6,550.00 Nos 6,550.00
Make : Aquanautics
28 1 Test kit for free chlorine & pH Quotation 650.00 Nos 650.00
Make : Aquanautics
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
29 PLUMBING WORKS
Providing of Supreme/ Finolex or equivalent PVC pipes of 10kg/cm2 for
frontal Plumbing network & linking joints with Fittings (PN10) & Solution
30 CONTROL PANEL
Supply and fixing Electrical control panel with suitable capacity MCCB as 1,90,000.00
incomer and required Outgoings, indicating RYB with selector switch,
digital volt meter, digital ammeter and with necessary DOL starters for
1 pumps and dosing pump including necessary devices as per the norms of Quotation 1,90,000.00 set
the licensed electrical contractor and cabling, conduting of the filtration
pumps in the plant room as per Project requirement / Engineer Incharge
selection-Additional charges will not allowed for this item
Make: L&T, Schneider, Siemens
31 REGULATING VALVE
Providing of online Regulating Butterfly valves & internal fixtures inclusive 3,60,000.00
1 Quotation 3,60,000.00 Job
of NRV's, flanges gaskets, nuts & bolts etc complete.
Make:supreme/equivalent
32 1 Installation Charges for all above works Quotation 1,55,000.00 Job 1,55,000.00
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
A. Competition Equipment's
1 8.00 Anti wave racing lane with standard 3-colors of length 25 mts Quotation 51,250.00 Nos 4,10,000.00
2 16.00 Stainless Steel Anchor cup as per the standard design Quotation 7,400.00 Nos 1,18,400.00
3 16.00 Stainless steel super Tensioner with steady increase system Quotation 9,800.00 Nos 1,56,800.00
10 2.00 Life Saving Hook with 5mtr Rod Quotation 5,600.00 Nos 11,200.00
11 2.00 First Aid kit A.P SOR 2020-2021 1,221.36 Nos 2,442.72
15 2.00 Stainless Steel Fulcrum for Diving Board Quotation 65,000.00 Nos 1,30,000.00
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
ELECTRICAL WORKS TOILETS , OFFICE AND COACH ROOM
1 POINT WIRING SYSTEM
Wiring for light point/ exhaust fan point with 1.5sq.mm FRLS PVC
insulated copper conductor single core cable in existing surface / recessed
heavy duty PVC conduit, with module type switch, Cover frame, suitable
size Metal GI box and earthing the point with 1.5 sq.mm. FRLS PVC
insulated copper conductor single core cable etc as required. Legrand
Arteor / Schneider Zen celo/ Crabtree Murano/ GM-Zenova- Primary ( I
light/fan controlled by one switch )
a 28 Single light point controlled by a 6A modular switch. A.P SOR 2020-2021 665.46 Nos 18,632.88
1No. 6/16/20A, 3/5pin shuttered type socket outlet located near exhaust
b 12 fan and controlled by 6A modular key type switch located with other A.P SOR 2020-2021 700.43 Nos 8,405.16
switches, inclusive of wiring.
PVC CONDUITS
Supply and Fixing of 25 mm(2.20mm thickness) P.V.C. pipe (ISI MARK)
concealed in wall with all required accessories including masonary work
for light, fan and separate plug point with well seasoned wooden deep
box including all labour charges etc., complete.
Supply and fixing of 12W LED Slim Panel Round / Square suitable for
Recessed / Surface mounting made of diecast alluminium body with
powder coating, acrylic diffuser with Driver as per IS: 15885 (Part 2/ Sec
13) : 2012 , operating voltage range of 150 to 265 Volts AC, P.F > 0.9,
a 25 Surge protection: 2KV,THD<10%, with high power LED's having efficacy of A.P SOR 2020-2021 908.92 Nos 22,723.00
> 90 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc., complete
Makes : Surya /C&S / Syska / Enrich / Stanjo / Polycab/ Ib LED/
Opple/ Luker/ Orbit/Trinic/Lumens/Panasonic /Rhino/ GLO LED/ Vimal
b) LED MAKE : CREE / NICHIA / OSRAM / SAMSUNG / EVERLIGHT
-
Supply and fixing of stepped type Electronic Regulator Makes: GM G
c 3 Home / Gold Medal Olive / Million Zoom / Great white A.P SOR 2020-2021 204.51 Nos 613.53
Omega/Koncept/Vimal opel/ Anchor/Vihan/CPL/ Havells Reo
Supply and Installation of 12" (300mm) Light duty exhaust fan with
metalic blades and wire guard etc complete.
d 12.00 A.P SOR 2020-2021 1,762.64 Nos 21,151.68
Makes: Crompton / Bajaj Bahar WG / Havells Ventil Air-DB / Orient hill
air/Halonix /Polycab/ G.M. (Xenix)
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
Flood Light
Supply, Installation, Testing and Commissioning of 120W LED Flood light
Luminaire made of pressure diecast alluminium housing with powder
coated,having protective toughned glass, Supply Input voltage 120 - 270 V
AC, P.F > 0.90, high power LED's System efficacy >100lm/W and junction
temprature < 70°C, with Ingrees protection IP66, Luminaire performance
complies to IS 10322 (Part 5 / Sec-3), IK05, Driver surge protection 4KV, In
house additional Surge protection 10KV with wide/ Narrow beam optics,
e 4.00 THD<10% at 110 Volts AC, driver efficiency >90%, , CCT: 3000K - 5700K, A.P SOR 2020-2021 13,410.00 Nos 53,640.00
minimum CRI>70, etc., complete
a) LUMINAIRE MAKE : Wipro / Philips/ GE-Venture / Crompton/ Bajaj
/Greenlites / Havells/Capart(Premium) /Halonix/ Polycab
/Keselec/HPL/Jaquar/Eveready / Surya (Lumasmax / O Flood) /
FortuneArrt(Fin)
b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA / OSRAM /
SAMSUNG
TOTAL OF LIGHT FIXTURES : 1,06,221.00
3.0 Distribution Boards
Supplying, installing, testing and commissioning of recess mounted type
with double door DBs complete as per IS 8623; IS 13032; IEC 61439-3 as
listed below.
Makes: Legrand(Ekinox 3) / Schneider-Acti9/Hager -
Novello+/ Seimens/Crabtree Xpro classique-II/L&TNewrange
.
LIGHTING
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
Providing earthling as per IS 3043 with perforated 2.5 mtr long 40 mm dia
B class GI pipe including all accessories like nuts bolts reducer,nipple, wire
meshed funnel and CC finished chamber covered with suitable size CI
a 2 A.P SOR 2020-2021 2,687.82 Nos 5,375.64
cover and Frame and embodying the pipe complete with alternate layers
of salt and coke /charcoal/bentonite powder testing earth resistance as
required etc., complete
Supply and laying of following sizes Earth wire/Strip in horizontal /Vertical
run in Ground/surface/Recess including,
revitting,soldering,saddles,making connection etc as required
b 20.0 25 x 3 mm GI earth flat (Hot dip galvanised) A.P SOR 2020-2021 47.72 Mts 954.40
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
PLUMBING WORKS
1 European Water Closet
Supply, Installation and commissioning approved make Wall Mounted
close coupled EWC suit with wall flush porcelain cistern fixed on EWC
with all internal parts of dual flush cistern, ultra solid seat cover of
approvedmake, complete for finished item of work in all respects: Special
7 A.P SOR 2020-2021 17,412.63 Each 1,21,888.41
Colour - Grade - III
530 x 350 x 375 mm
Clean Rim wall hung EWC with
Duroplast slim soft close seat cover
2 Brand:Basin
Wash CERA /SKU: S1044150/ Kajaria or Equivalent
Supplying & Fixing Indian make Flat Back Wash Hand Basin1st quality
conforming to IS:2556-Part-4:1972 with waste fittings like rubber plug,
chain,32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore
6 A.P SOR 2020-2021 2,375.69 Each 14,254.14
Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/
Senior/ Nice/ Esso or equivalent complete with standard CI brackets
including wooden block: 630 x 450 mm - Single C.P. Pillar cock kajaria /
Hindustan Sanitary ware / CERA / Jaquar.
3 Sensor Faucet for Wash Basins
Supply & Fixing of Jaquar make Sensotronic sensor faucet
6 A.P SOR 2020-2021 14,230.28 Each 85,381.68
for wash basin, Chrome plated with 7 years warranty
4 Urinals
Supplying & Fixing white glazed flat back half stall urinals 1st quality
conforming to IS:2556-1995 with standard C.P. Spreader of overall size 95
4 x 95 x 57 mm conforming to IS:2556-Part6, Sec-6-1974 fixed with screws A.P SOR 2020-2021 3,007.39 Each 12,029.56
complete Indian make : 590 x 375 x 390 mm kajaria / Hindustan Sanitary
ware / CERA / Jaquar.
5 Sensotronic concealed type flushing valve for urinal
Supply & Fixing of Jaquar make Sensotronic sensor faucet
4 A.P SOR 2020-2021 14,230.28 Each 56,921.12
for wash basin, Chrome plated with 7 years warranty
6 GM Ball Valves 25 mm dia
Supplying & Fixing Gunmetal (GM) Ball valve with SS Ball and SS Spindle
10 as per IS - Class - I, Indian make heavy type - 25 mm NB Size Zoloto, Sant A.P SOR 2020-2021 886.20 Each 8,862.00
valves/ JSW
7 GM Ball Valves 32 mm dia
Supplying & Fixing Gunmetal (GM) Ball valve with SS Ball and SS Spindle
2 as per IS - Class - I, Indian make heavy type - 32 mm NB Size Zoloto, Sant A.P SOR 2020-2021 1,600.84 Each 3,201.68
valves/ JSW
8 Bottle Trap
Supply & Fixing of Bottle Trap Jaquar make, Chrome finish with 7 years
10 A.P SOR 2020-2021 1,669.00 Each 16,690.00
warranty
9 Towel Ring
Supply & Fixing of Towel Ring Jaquar make Continental series, Chrome
10 A.P SOR 2020-2021 982.77 Each 9,827.70
finish with 7 years warranty
10 Double coat hook
Supply & Fixing Double coat hook Jaquar make Continental series, Chrome
7 A.P SOR 2020-2021 733.95 Each 5,137.65
finish with 7 years warranty
11 Bibcock cum Health faucet
Supply & Fixing of Bibcock cum Health Faucet with 1m long tube and wall
7 hook of Jaquar Florentine(Quarter turn) series, Chrome Finish with 7 years A.P SOR 2020-2021 3,764.06 Each 26,348.42
warranty
12 shower spray
S & F NP shower spray fancy with NP Flexible pipe-Jaquar
16 A.P SOR 2020-2021 2,154.14 Each 34,466.24
13 CPVC Pipes
Supply and Fixing of Premium make CPVC Pipes and Fittings to meet the
requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes
1/2" ton 2" Ashirvad Flowgurard SDR 11 and SDR 13.5 pipes are made A.P SOR 2020-2021
from idential CPVC compounds having the same physical Properties for
Hot and Cold Water (IS 15778:2007) -Prince/ Finolex /
Sudhakar/Kisan/Supreme
MEP BOQ Page 18 of 54
Proposed Construction of Swimming Pool at Vinayak Sagar Lake, Karkambadi Road under implementation of the Smart City Mission in Tirupati
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
a 136 A.P SOR 2020-2021 69.31 RM 9,426.16
15.9 mm OD Pipe SDR 11
b 85 A.P SOR 2020-2021 105.66 RM 8,981.10
22.20mm ODPipe - SDR 11
c 80 A.P SOR 2020-2021 260.18 RM 20,814.40
34.90mm ODPipe - SDR 11
14 75 mm dia PVC Pipes - 6 kg/sqcm
Supplying 75 mm dia 3 M Single Socket PVC/SWR pipe - 6 Kg/sq.cm -
60 A.P SOR 2020-2021 138.61 RM 8,316.60
Prince/ Finolex / Sudhakar/Kisan/Supreme
15 90 mm dia PVC Pipes - 6 kg/sqcm
Supplying 90 mm dia 3 M single Socket PVC/SWR pipe - 6 Kg/sq.cm -
10 A.P SOR 2020-2021 223.06 RM 2,230.60
Prince/ Finolex / Sudhakar/Kisan/Supreme
16 110 mm dia PVC Pipes - 6 kg/sqcm
Supplying 110 mm dia 3 M Single Socket PVC/SWR pipe - 6 Kg/sq.cm -
146 A.P SOR 2020-2021 265.48 RM 38,760.08
Prince/ Finolex / Sudhakar/Kisan/Supreme
17 75 mm dia plain bend
Supplying 75 mm dia - Plain Bend 87.5 Degree - UPVC/SWR Pipe fittings
5 A.P SOR 2020-2021 47.72 Each 238.60
18 90 mm dia plain bend
Supplying 90 mm dia - Plain Bend 87.5 Degree - UPVC/SWR Pipe fittings
2 A.P SOR 2020-2021 67.03 Each 134.06
19 110 mm dia plain bend
Supplying 110 mm dia - Plain Bend 87.5 Degree - UPVC/SWR Pipe fittings
10 A.P SOR 2020-2021 79.53 Each 795.30
20 75 mm dia 45 degree bend
Supplying 75 mm dia - 45 Degree Bend - UPVC/SWR Pipe fittings
4 A.P SOR 2020-2021 37.00 Each 148.00
21 90 mm dia 45 degree bend
Supplying 90 mm dia - 45 Degree Bend - UPVC/SWR Pipe fittings
1 A.P SOR 2020-2021 52.26 Each 52.26
22 110 mm dia 45 degree bend
Supplying 110 mm dia - 45 Degree Bend - UPVC/SWR Pipe fittings
5 A.P SOR 2020-2021 67.03 Each 335.15
23 75 mm dia single tee
Supplying 75 mm dia - Single Tee - UPVC/SWR Pipe fittings
2 A.P SOR 2020-2021 56.81 Each 113.62
24 90 mm dia single tee
Supplying 90 mm dia - Single Tee - UPVC/SWR Pipe fittings
1 A.P SOR 2020-2021 85.21 Each 85.21
25 110 mm dia single tee
Supplying 110 mm dia - Single Tee - UPVC/SWR Pipe fittings
4 A.P SOR 2020-2021 103.39 Each 413.56
26 75 mm dia coupler
Supplying 75 mm dia - Coupler - UPVC/SWR Pipe fittings
2 A.P SOR 2020-2021 34.08 Each 68.16
27 90 mm dia coupler
Supplying 90 mm dia - Coupler - UPVC/SWR Pipe fittings
1 A.P SOR 2020-2021 48.85 Each 48.85
28 110 mm dia coupler
Supplying110 mm dia - Coupler - UPVC/SWR Pipe fittings
2 A.P SOR 2020-2021 54.54 Each 109.08
29 75 mm dia vent cowl
Supplying 75 mm dia - Vent Cowl - UPVC/SWR Pipe fittings
4 A.P SOR 2020-2021 13.63 Each 54.52
30 110 mm dia vent cowl
Supplying 110 mm dia - Vent Cowl - UPVC/SWR Pipe fittings
4 A.P SOR 2020-2021 18.18 Each 72.72
31 4" dia Multi trap
Supplying 4" (101.6) multi floor trap with out Jalli- UPVC/SWR Pipe
18 A.P SOR 2020-2021 107.93 Each 1,942.74
fittings
32 Labour charges for PVC pipes
Labour charges for laying, fixing and commissioning the PVC pipes
216 including couplers/ bends/ tees etc any diameter including fixing A.P SOR 2020-2021 97.03 RM 20,958.48
necessary fittings like bends, plugs, couplers, junctions, tees, etc with
solvent jointing as per standard practice
33 Masonry Inspection chamber 457.2 x 457.2 mm
BILL OF QUANTITIES-MEP
Sl No. Quantity Description SOR Ref. Rate Unit Amount
1 2 3 4 5.00 6 7.00
Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop.
3 Masonry. Inspection chamber up to 914.4 mm (3'0") and fitted with light A.P SOR 2020-2021 3,678.85 Each 11,036.55
weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame andcover of 20 Kg.
NAME OF WORK :- Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in Tirupati
Est Amt:
Measurements
Sl. No Description of Work Nos. Qnty Rate Per Amount Remarks
L B D
1 CLEARING SITE
Clearing light Jungle Area
site clearing 1 x 1 1,456.42 1,456.42 Auto Cad measurement
Add 1% 14.56
1,470.98
Say 1,471.00 3.18 Sqm 4,677.78 AP SOR 19-2020
2 Earth work excavation
Swimming pool 1 x 1 13.00 22.00 3.25 929.50
Swimming pool 1 x 1 13.00 22.00 2.25 643.50
Balancing tank / Plant Room 1 x 1 13.00 9.00 2.45 286.65
Kids pool 1 x 1 10.00 5.00 1.15 57.50
Toilet Block 1 x 4 1.80 1.80 2.50 32.40
Toilet Block 1 x 6 2.00 2.00 2.50 60.00
Toilet Block 1 x 2 2.20 2.20 2.50 24.20
Toilet Block - PB 1 x 4 10.00 0.45 2.00 36.00
Toilet Block - PB 1 x 3 11.00 0.45 2.00 29.70
Store / Coach room / Office 1 x 6 1.00 1.00 1.50 9.00
Compound wall Footing (126 Rmt) 1 x 36 1.00 1.00 1.50 54.00
Compound wall PB 1 x 1 126.00 0.23 0.45 13.04
Add 2% 43.51
2,219.00
Say 2,220.00
1. By mechanical means 1,554.00 105.76 Cum 1,64,351.04 AP SOR 19-2020
NAME OF WORK :- Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in Tirupati
Est Amt:
Measurements
Sl. No Description of Work Nos. Qnty Rate Per Amount Remarks
L B D
7 Providing and laying CRS Masonry in CM (1:6)
including curing, scaffolding etc. The rate shall
be including of all materials, lift, lead and
other related works etc. to complete.
NAME OF WORK :- Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in Tirupati
Est Amt:
Measurements
Sl. No Description of Work Nos. Qnty Rate Per Amount Remarks
L B D
9 Steel Fe500 bar Co-Eff
For Footing 242.00 60.00 14,520.00
For Pedestals 150.00 120.00 18,000.00
For Plinth beam 24.00 110.00 2,640.00
For RCC Columns 11.00 120.00 1,320.00
For RCC Roof Beam 16.00 110.00 1,760.00
For Roof Slab 53.00 60.00 3,180.00
For OHT, Lintels, Kichen Staircase etc., 1.00 90.00 90.00
497.00 Say 41.51 64,887.19 MT 26,93,467.26 AP SOR 19-2020
10 Miscellaneous Works Co-Eff
Compound wall 126.00 5.00 630.00
Main Gate 700.00
Window Grill etc., 8.64 15.00 129.60
Add 3% 43.79
1,503.39
Say 1.51 1,03,287.94 MT 1,55,964.79 AP SOR 19-2020
11 Roof water proof
Toilet Terrace 1 x 1 13.00 13.00 169.00
169.00
Say 169.00 539.67 Sqm 91,204.23 AP SOR 19-2020
12 Filling with useful available excavated earth
NAME OF WORK :- Proposed Construction of Swimming Pool beside Vinayak Sagar under Implementation of Smart City Mission in Tirupati
Est Amt:
Measurements
Sl. No Description of Work Nos. Qnty Rate Per Amount Remarks
L B D
20 Enamel paint
M.Gate 1 x 2 4.00 3.00 24.00 Item omitted
Window Grill work 1 x 2 7.20 3.00 43.20
Add 3% 2.02
69.22
Say 70.00 243.99 Sqm 17,079.30 AP SOR 19-2020
21 Swimming pool tiles
Floor - Swimming pool 1 x 1 27.00 21.00 567.00 Item omitted
Floor - Kids pool 1 x 1 9.40 5.00 47.00
Kids pool 1 x 1 27.40 0.75 20.55
Swimming pool 1 x 1 92.80 1.85 171.68
Swimming pool 1 x 3 13.00 2.00 78.00
Kids pool 1 x 1 27.00 0.75 20.25
Swimming pool - Open drain 1 x 2 25.00 0.90 45.00
Kids pool - Open drain 1 x 1 9.00 0.90 8.10
Add 5% 47.88
1,005.46
Say 1,006.00 1,210.01 Sqm 12,17,270.06 AP SOR 19-2020
22 Store / Coach room / Office
Flooring with Granit 1 x 1 11.00 3.00 33.00 Auto Cad measurement
Add 3% 0.99
33.99
Say 34.00 3,965.69 Sqm 1,34,833.46 AP SOR 19-2020
23 Flooring with Granit
Deck 1 x 1 21.00 5.00 105.00 Auto Cad measurement
1 x 1 25.00 1.90 47.50
1 x 1 20.00 3.30 66.00
1 x 1 27.00 10.00 270.00
Less Kids pool 1 x -1 9.00 4.50 -40.50
Galary 1 x 3 30.00 0.50 45.00
Add 5% 24.65
517.65
Say 518.00 1,871.18 Sqm 9,69,271.24 AP SOR 19-2020
24 Toilet - Wall Tiles
GF 1 x 1 96.00 2.80 268.80
Shower area 1 x 2 4.00 2.80 22.40
Add 3% 8.74
299.94
Say 300.00 1,068.52 Sqm 3,20,556.00 AP SOR 19-2020
25 Toilet - Floor Tiles
GF 1 x 1 12.00 12.00 144.00 Auto Cad measurement
Add 3% 4.32
148.32
Say 149.00 977.76 Sqm 1,45,686.24 AP SOR 19-2020
26 Door Frame
GF 1 x 3 6.20 18.60
Toilet 1 x 2 6.20 12.40
31.00
Say 31.00 703.28 Rmt 21,801.68 AP SOR 19-2020
27 Door Shutter
GF & FF 1 x 3 3.00
Toilet 1 x 2 2.00
5.00
Say 5.00 13,625.64 Nos 68,128.20 AP SOR 19-2020
28 Upvc Window / V
GF 1 x 3 1.20 1.20 4.32
Toilet / V 1 x 6 0.60 0.60 2.16
6.48
Say 7.00 6,623.75 Sqm 46,366.25 AP SOR 19-2020
29 MS Door
GF 1 x 4 2.00 2.10 16.80
16.80
Say 17.00 1,590.61 Sqm 27,040.37 AP SOR 19-2020
30 Supply of material, delivery at site of Swimming Pool Chair (Pool Lounge Chair)
Floor 1 x 4 1.00 4.00
4.00
Say 4.00 7,000.00 No 28,000.00 Quotation
31 Supply, delivery of material and fixing at site of Stadium Chair
Floor 1 x 60 1.00 60.00
60.00
Say 60.00 1,850.00 No 1,11,000.00 Quotation
32 Supply, delivery of material and fixing at site of Toilet Cubicles
Floor 1 x 12 1.00 12.00
12.00
Say 12.00 28,000.00 No 3,36,000.00 Quotation
1,41,89,786
1,41,89,786
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
MAT-00480 A.1 CLEARING SITE Sqm 1.000 2.80 2.80
Clearing light Jungle
Add for contractor’s profit and overheads @ 13.615 % 13.615% 0.38
Add 25 % additional for Municpal Allowances -
Cost of 1 Sqm 3.18
Say 3.18
BLD-CSTN-2-2 A.2 Ordinary soils-Mechcanical Means-Upto 3 m
depth
Unit = cum
Taking output = 240 cum
a) Labour
Mazdoor Day 8.320 460.00 3,827.20
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.000 2,945.40 17,672.40 HIR-00052
21,499.60
Add for contractor’s profit and overheads @ 13.615 % 13.615% 2,927.17
Add 25 % additional for Municpal Allowances 25% 956.80
Cost of 240 cum 25,383.57
Cost of 1 cum 105.76
Say 105.76
BLD-CSTN-2-1 A.2 Earth work excavation for foundations and depositing on bank for
all lifts and with an initial lead of 10m including all operational,
incidental, labour charges such as shoring ,sheeting, planking,
strutting, etc. complete for finished item of work including
seigniorage excluding dewatering charges etc as per SS - 20 B (APSS
308).
Page 25 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-2-7 A.6 Plain Cement concrete (1:5:10) using 40mm metal with Concrete
mixture. The rate shall be including of all materials, lif, lead and other
related works etc to complete.
Page 26 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-2-14 (A) A.8 Supply and placing of the Design Mix Concrete M25 By using 380
Kg/Cum
PEDESTALS
Detail of cost for 1 cum
A) Material
Stone Aggregate (Single size) : 20 mm nominal size Cum 0.560 1,530.80 857.25
Stone Aggregate (Single size) : 12 mm nominal size Cum 0.080 1,260.80 100.86
Stone Aggregate (Single size) : 10 mm nominal size Cum 0.080 1,095.80 87.66
Stone Aggregate (Single size) : 6 mm nominal size Cum 0.080 910.80 72.86
Fine aggreagte (sand) Cum 0.400 658.30 263.32
Portland Cement Tonne 0.380 3,680.00 1,398.40
Water Kl 1.200 110.00 132.00
B) Machinery
Concrete mixer 600 /
Weigh Batcher Hire charges (Machine mixing) charges hour 1.333 566.10 754.61
400 (diesel)
Needle vibrator 40 mm ( petrol ) hour 1.333 223.00 297.26
C) LABOUR
Mason 1st class Day 0.133 550.00 73.15
Mason 2nd class Day 0.267 500.00 133.50
Mazdoor Day 4.600 460.00 2,116.00
D) Centering charges
HIRE CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 328.00 328.00
LABOUR CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 1,004.00 1,004.00
7,618.88
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,037.31
Add 25% additional for Municpal Allowances 25% 580.66
Add 25 % additional for Municpal Allowances for Centering &
25% 251.00
Scaffolding works Labour componant
Cost of 1cum 9,487.85
Say 9,487.85
BLD-CSTN-2-14 (A) A.8 Supply and placing of the Design Mix Concrete M25 By using 380
Kg/Cum
PLINTH BEAMS
Detail of cost for 1 cum
A) Material
Stone Aggregate (Single size) : 20 mm nominal size Cum 0.560 1,530.80 857.25
Stone Aggregate (Single size) : 12 mm nominal size Cum 0.080 1,260.80 100.86
Stone Aggregate (Single size) : 10 mm nominal size Cum 0.080 1,095.80 87.66
Stone Aggregate (Single size) : 6 mm nominal size Cum 0.080 910.80 72.86
Fine aggreagte (sand) Cum 0.400 658.30 263.32
Portland Cement Tonne 0.380 3,680.00 1,398.40
Water Kl 1.200 110.00 132.00
B) Machinery
Weigh Batcher Hire charges (Machine mixing) Concrete mixer 600 /
hour 1.333 566.10 754.61
charges 400 (diesel)
Needle vibrator 40 mm ( petrol ) hour 1.333 223.00 297.26
C) LABOUR
Mason 1st class Day 0.133 550.00 73.15
Mason 2nd class Day 0.267 500.00 133.50
Mazdoor Day 4.600 460.00 2,116.00
D) Centering charges
HIRE CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 1,390.00 1,390.00
LABOUR CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 1,521.00 1,521.00
9,197.88
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,252.29
Add 25% additional for Municpal Allowances 25% 580.66
Add 25 % additional for Municpal Allowances for Centering &
25% 380.25
Scaffolding works Labour componant
Cost of 1cum 11,411.08
Say 11,411.08
Page 27 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-2-14 (B) A.8 Supply and placing of the Design Mix Concrete M25 By using 380
Kg/Cum
Beams (GF)
Detail of cost for 1 cum
A) Material
Stone Aggregate (Single size) : 20 mm nominal size Cum 0.560 1,530.80 857.25
Stone Aggregate (Single size) : 12 mm nominal size 0.080 1,260.80 100.86
Stone Aggregate (Single size) : 10 mm nominal size 0.080 1,095.80 87.66
Stone Aggregate (Single size) : 6 mm nominal size 0.080 910.80 72.86
Fine aggreagte (sand) Cum 0.400 658.30 263.32
Portland Cement Tonne 0.380 3,680.00 1,398.40
Water Kl 1.200 110.00 132.00
B) Machinery
Concrete mixer 600 /
Concrete mixer 300 / 200 ( diesel) hour 0.308 566.10 174.36
400 (diesel)
Needle vibrator 40 mm ( petrol ) hour 0.308 223.00 68.68
C) LABOUR
Mason 1st class Day 0.067 550.00 36.85
Mason 2nd class Day 0.133 500.00 66.50
Mazdoor Day 3.077 460.00 1,415.42
D) Centering charges
HIRE CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 2,085.00 2,085.00
LABOUR CHARGES FOR CENTERING & SCAFFOLDING Cum 1.000 1,903.00 1,903.00
8,662.17
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,179.35
Add 25% additional for Municpal Allowances 25% 379.69
Add 25% additional for Municpal Allowances for Centering &
25% 475.75
Scaffolding works Labour componant
Cost of 1cum 10,696.97
Say 10,696.97
Page 28 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-2-14 (C) A.8 Supply and placing of the Design Mix Concrete M25 By using 380
Kg/Cum
Roof Slab (GF)
Detail of cost for 1 cum
A) Material
Stone Aggregate (Single size) : 20 mm nominal size Cum 0.560 1,530.80 857.25
Stone Aggregate (Single size) : 12 mm nominal size 0.080 1,260.80 100.86
Stone Aggregate (Single size) : 10 mm nominal size 0.080 1,095.80 87.66
Stone Aggregate (Single size) : 6 mm nominal size 0.080 910.80 72.86
Fine aggreagte (sand) Cum 0.400 658.30 263.32
Portland Cement Tonne 0.380 3,680.00 1,398.40
Water Kl 1.200 110.00 132.00
B) Machinery
Concrete mixer 300 / 200 ( diesel) hour 0.308 566.10 174.36 Concrete mixer 600 /
400 (diesel)
Needle vibrator 40 mm ( petrol ) hour 0.308 223.00 68.68
C) LABOUR
Mason 1st class Day 0.067 550.00 36.85
Mason 2nd class Day 0.133 500.00 66.50
Mazdoor Day 3.077 460.00 1,415.42
D) Centering charges
HIRE CHARGES FOR CENTERING & SCAFFOLDING Sqm 6.667 236.00 1,573.33
LABOUR CHARGES FOR CENTERING & SCAFFOLDING Sqm 6.667 226.00 1,506.67
7,754.17
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,055.73
Add 25 % additional for Municpal Allowances 25% 379.69
Add 25 % additional for Municpal Allowances for Centering &
25% 376.67
Scaffolding works Labour componant
Cost of 1cum 9,566.26
Say 9,566.26
BLD-CSTN-2-20 A.9 Supplying, fitting and placing TMT bar reinforcement in VRCC works
complete as per drawings and technical specifications for Bars below
36 mm dia including over laps and wastage, where they are not
welded. (HYSD) Fe 500D
A) Material
Mild steel, Structural Steel, i.e. Angles, Channels and I - Sections Kg 1.050 41.00 43.05
Painting with one coat of red oxide and two coats of Aluminium paint 0.100 4.31
(on cost of Item 1)
B) LABOUR
MAT-00702 Structural steel fabrication. Kg 1.050 29.00 30.45 MAT-00702
(The rate for structural steel fabrication shall include cost of all
materials (except structural steel), machinery, labour and one coat of
primer painting)
Labour charges for fixing Iron Doors, Iron Windows and Window Kg 1.050 5.00 5.25 BMM-V.15
Grills in position
83.06
Add for contractor’s profit and overheads @ 13.615 % 13.615% 11.31
Add 25% additional for Municpal Allowances 25% 8.93
Cost of 1 Kgs 103.29
Say 103.29 1,03,287.94
WATERPROOFING
Page 29 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BMT-H.71 A.11 SPECIALISED HIGH PERFORMANCE ACRYLIC POLYMER MODIFIED Sqm 1.000 475.00 475.00
ELASTOMERIC CEMENTITIOUS WATERPROOF COATING TO THE
TERRACE
Add for contractor’s profit and overheads @ 13.615 % 13.615% 64.67
Add 25 % additional for Municpal Allowances 25% -
Cost of 1 Sqm 539.67
Say 539.67
BLD-CSTN- 2-9-17 A.12 Filling with useful available excavated earth (excluding rock) in
trenches, sides of foundations and basement with initial lead in layers
not exceeding 15 cm thick, consolidating each deposited layer by
watering and ramming including cost and conveyance of water to
work site and all operational, incidental, labour charges, hire
charges of T & P etc., complete for finished item of work. (APSS
NO. 309 & 310)
Analysis - 6 Cum.
A. Labour
Mazdoor Day 0.310 460.00 142.60
142.60
Add for contractor’s profit and overheads @ 13.615 % 13.615% 19.41
Add 25% additional for Municpal Allowances 25% 35.65
Cost of 6 Cum. 197.66
Cost of 1 Cum. 32.94
Say 32.94
BLD-CSTN-3-1-iv A.13 Providing and laying brick work using common burnt clay conventional
building bricks conforming to IS 1077-1992 having compressive
strength not less than 50 Kg/cm2 in any shape and all depth including
curing, scaffolding etc. complete as directed by engineer-in-charge.
Ground Floor
Super structure plinth for all levels CM 1:6 (1 Cement : 6 coarse Sand)
Page 30 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
Detail of cost for 10 sqm
BLD-CSTN-1-5 CM 1:4 cost
Detail of cost for 1 cum
A) Material
Fine aggreagte (sand) Cum 1.050 753.30 790.97
Portland Cement Tonne 0.360 3,680.00 1,324.80
C) LABOUR
Maszdoor for mortar mixing Day 0.200 460.00 92.00
Add 25 % additional for Municpal Allowances 25% 23.00
Cost of 1 cum 2,230.77
A) Material
CM 1:4 Cum 0.210 2,230.77 468.46
Mason 1st class Day 0.450 550.00 247.50
Mason 2nd class Day 1.050 500.00 525.00
Mazdoor Day 2.800 460.00 1,288.00
D) HIRE CHARGES FOR ACCESS SCAFFOLDING
HIRE CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 1.03 10.30
LABOUR CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 7.95 79.50
2,618.76
Add for contractor’s profit and overheads @ 13.615 % 13.615% 356.54
Add 25% additional for Municpal Allowances 25% 535.00
Cost of 10 sqm 3,510.30
Cost of 1 sqm 351.03
Say 351.03
BLD-CSTN-6-7 A.17 Celing Plastering : Plastering with CM (1:3), 12 mm thick
Detail of cost for 10 sqm
BLD-CSTN-1-4 CM 1:3 cost
Detail of cost for 1 cum
A) Material
Fine aggreagte (sand) Cum 1.050 753.30 790.97
Portland Cement Tonne 0.480 3,680.00 1,766.40
C) LABOUR
Maszdoor for mortar mixing Day 0.200 460.00 92.00
Add 25 % additional for Municpal Allowances 25% 23.00
Cost of 1 cum 2,672.37
A) Material
CM 1:3 Cum 0.150 2,672.37 400.85
Mason 1st class Day 0.450 550.00 247.50
Mason 2nd class Day 1.050 500.00 525.00
Cooli Day 2.800 460.00 1,288.00
D) HIRE CHARGES FOR ACCESS SCAFFOLDING
HIRE CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 2.46 24.60
LABOUR CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 15.91 159.10
2,645.05
Add for contractor’s profit and overheads @ 13.615 % 13.615% 360.12
Add 25% additional for Municpal Allowances 25% 554.90
Cost of 10 sqm 3,560.08
Cost of 1 sqm 356.01
Say 356.01
BLD-CSTN-9-6 Internal Wall : Putty
Detail of cost for 10 sqm
A) Material
Supply of wall putty of White Cement or Polymer or Cement Kg 23.000 27.50 632.50 BMT-J.31
based
C) LABOUR
Pianter Ist class Day 0.273 615.00 167.90
Pianter 2nd class Day 0.637 500.00 318.50
Mazdoor (unskilled) Day 0.910 460.00 418.60
D) HIRE CHARGES FOR ACCESS SCAFFOLDING
HIRE CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 1.03 10.30
LABOUR CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 7.95 79.50
1,627.30
Add for contractor’s profit and overheads @ 13.615 % 13.615% 221.56
Add 25% additional for Municpal Allowances 25% 246.12
Cost of 10 sqm 2,094.97
Cost of 1 sqm 209.50
Say 209.50
BLD-CSTN-10-1 A.18 Internal Wall : Painting to new walls with 1-coat primer 2 coats of
acrylic emulsion paint interior grade having VOC (Volatile Organic
Compound) content less than 50 grams/ liter. of approved brand
and shade over a base coat of appropriate primer of approved
brand, making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and
remains of loose powdered materials, including cost and
conveyance of all materials to work site and all operational,
incidental, labour charges etc. complete for finished item of work as
per SS 911.
Page 31 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
Detail of cost for 10 sqm
A) Material
BLD-CSTN-12-1 Supply of water based Cement Primer of Interior Grade- 1 Kg 0.500 141.00 70.50 BMT-J.01
Supply of acrylic emulsion paint interior grade having VOC Ltr 0.800 168.00 134.40 BMT-J.24
(Volatile Organic Compound) content less than 50 grams/ liter.
C) LABOUR
Painter I st class (Primer) Day 0.080 615.00 49.20
Pianter Iind class(Primer) Day 0.190 500.00 95.00
Painter I st class(Paint) Day 0.360 615.00 221.40
Pianter Iind class(Paint) Day 0.840 500.00 420.00
Sundries including brushes, soaps, putty etc., Ls 0.5% 990.50 4.95
D) HIRE CHARGES FOR ACCESS SCAFFOLDING
HIRE CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 1.03 10.30
LABOUR CHARGES FOR ACCESS SCAFFOLDING Sqm 10.000 7.95 79.50
1,085.25
Add for contractor’s profit and overheads @ 13.615 % 13.615% 147.76
Add 25% additional for Municpal Allowances 25% 216.28
Cost of 10 sqm 1,449.28
Cost of 1 sqm 144.93
Say 144.93
BLD-CSTN-10-5 A.19 Painting to External walls Painting to new walls with 2 coats of water
proof cement paint of apporved brand and shade over a base coat of
approved cement primer grade I making making 3 coats in all to give
an even shade after thourughly brushing the surface to remove all dirt
and remains of loose powdered materials,including cost and
conveyance of all materials to work site and all operational,
incidental, labour charges etc. complete for finished item of work as
per SS 912 for External walls
Page 32 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-10-12-viii A.20 Providing and applying enamel paint - Painting, Priming Coat on Iron /
Wood Work
Page 33 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-7-7 A.22 High polished granite 16 to 18 mm thick slabs other than black set over
base coat of cement mortar (1:8), 20 mm thick over CC bed already laid
or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like cement, sand water and
tilesetc., complete, including seigniorage charges, labour charges for
dressing of tilesetc., complete for finished item of work, but excluding
the cost of conveyance of all materials
B. LABOUR
Mason 1st class Day 3.000 550.00 1,650.00
Mason 2nd class Day 1.000 500.00 500.00
Mazdoor Day 8.000 460.00 3,680.00
Labour for nosing works Rmt 50.500 50.00 2,525.00 BMM-V.13
Add water charges 1% 327.39
33,066.18
Add for contractor’s profit and overheads @ 13.615% 13.615% 4,501.96
Add 25% additional for Municpal Allowances 25% 2,088.75
Cost of 10 m2 39,656.89
Cost of 1 sqm 3,965.69
Say 3,965.69
BLD-CSTN-7-7 A.23 Pool Deck Area : Sadar Ali Granite (double line dressing) 16 to 18 mm
thick slabs other than black set over base coat of cement mortar (1:8),
20 mm thick over CC bed already laid or RCC roof slab, including neat
cement slurry of honey like consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
cement, sand water and tilesetc., complete, including seigniorage
charges, labour charges for dressing of tilesetc., complete for finished
item of work, but
excluding the cost of conveyance of all materials
B. LABOUR
Mason 1st class Day 3.000 550.00 1,650.00
Mason 2nd class Day 1.000 500.00 500.00
Mazdoor Day 8.000 460.00 3,680.00
Add water charges 1% 150.36
15,186.61
Add for contractor’s profit and overheads @ 13.615% 13.615% 2,067.66
Add 25% additional for Municpal Allowances 25% 1,457.50
Cost of 10 m2 18,711.76
Cost of 1 sqm 1,871.18
Say 1,871.18
Page 34 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BLD-CSTN-7-18 A.24 Providing dadooing Providing and internal walls to required heigh
with ceramic tiles Supply of glazed red or white full body ceramic wall
tiles
Detail of cost for 10 sqm
BLD-CSTN-1-4 CM 1:3 cost
Detail of cost for 1 cum
A) Material for cement morter
Fine aggreagte (sand) Cum 1.050 753.30 790.97
Portland Cement mortar Tonne 0.480 3,680.00 1,766.40
B) LABOUR
Mazdoor for mixing mortar Day 0.200 460.00 92.00
Add 25% additional for Municpal Allowances 23.00
Cost of 1 cum 2,672.37
A) Material
Supply of glazed full body porcelain wall tiles of size 600 x 1200 mm
with any type of design texture such as marble finish, wooden,
Sqm 10.500 726.00 7,623.00 BMT-C.28
bamboo, stone finishes etc., scratch less, stain free and
thickness between 6-8 mm 1st quality conforming to IS:13711,
Sand for cm 1:3 base coat Cum 0.120 2,672.37 320.68
Cement for cm 1:3 base coat Kg 57.600 3.68 211.97
Cement for slurry Kg 33.000 3.68 121.44
White cement Kg 6.000 27.00 162.00 BMS-W.68
C) LABOUR
Mason 1st class Day 0.770 550.00 423.50
Mason (2nd class) Day - 500.00 -
Mazdoor (unskiled) Day 0.800 460.00 368.00
Add water charges 1% 1% 0.00
9,230.59
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,256.75
Add 25% additional for Municpal Allowances 25% 197.88
Cost of 10 sqm 10,685.21
Cost of 1 sqm 1,068.52
Say 1,068.52
BLD-CSTN-7-6 A.25 Flooring size 600x600, Supply of Non-skid red or white full body
Ceramic floor tiles of size 300 x 300 mm and thickness between 7-8
mm 1st quality
Detail of cost for 10 sqm
BLD-CSTN-1-8 CM 1:8 cost
Detail of cost for 1 cum
A) Material for cement morter
Fine aggreagte (sand) Cum 1.050 753.30 790.97
Portland Cement mortar Tonne 0.180 3,680.00 662.40
B) LABOUR
Mazdoor for mixing mortar Day 0.200 460.00 92.00
Add 25% additional for Municpal Allowances 23.00
Cost of 1 cum 1,568.37
A) Material
Supply of soluble salt porcelain vitrified tiles screen printed and
polished of size 600 x 600 mm and thickness between 8-10 mm 1st Sqm 10.100 418.00 4,221.80 BMT-C.06
quality conforming
Cement for CM (1:8) for base coat Kg 21.600 3.68 79.49
Cement for slurry Kg 33.000 3.68 121.44
Sand for CM (1:8) Cum 0.120 1,568.37 188.20
White cement Kg 2.000 27.00 54.00
B) LABOUR
Mason 1st class Day 0.960 550.00 528.00
Mason (2nd class) Day 2.240 500.00 1,120.00
Mazdoor (unskilled) Day 3.300 460.00 1,518.00
Add water charges 1% 1% 78.31
7,909.24
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,076.84
Add 25% additional for Municpal Allowances 25% 791.50
Cost of 10 sqm 9,777.58
Cost of 1 sqm 977.76
Say 977.76
BMT-N.80 A.26 DOOR FRAMES Rmt 1.000 619.00 619.00
Supply & Fixing Powder Coated Mild Steel Hallow single rebate door
frames
Add for contractor’s profit and overheads @ 13.615 % 13.615% 84.28
Add 25 % additional for Municpal Allowances -
Cost of 1 Rmt 703.28
Say 703.28
Page 35 of 54
Rate Analysis
BOQ
SOR Ref Description Unit Quantity Rate Amount Remarks
Item Ref
BMT-N.14 A.27 Supply & Fixing of Door Shutter made out of solid bond wood block
11,339.89
Add for contractor’s profit and overheads @ 13.615 % 13.615% 1,543.93
Add 25 % additional for Municpal Allowances 25% 741.83
Cost of 1 Sqm 13,625.64
Say 13,625.64
uPVC white colour fixed glazedwindows / Ventilators
BMT-P.79 A.28 Providing and fixing factory made uPVC white colour fixed Sqm 1.000 5,830.00 5,830.00
glazedwindows / Ventilators
Add for contractor’s profit and overheads @ 13.615 % 13.615% 793.75
Add 25 % additional for Municpal Allowances -
Cost of 1 Sqm 6,623.75
Say 6,623.75
BMT-N.52 A.29 Supply & Fixing SOLID STEEL DOOR door shutter Sqm 1.000 1,400.00 1,400.00
Add for contractor’s profit and overheads @ 13.615 % 13.615% 190.61
Add 25 % additional for Municpal Allowances -
Cost of 1 Sqm 1,590.61
Say 1,590.61
Page 36 of 54
Proposed Construction of Swimming Pool at Vinayak Sagar Lake, Karkambadi Road under implementation of the Smart City Mission in Tirupati
Supply and fixing of ........ LED Slim Panel Round / Square suitable for
Recessed / Surface mounting made of diecast alluminium body with
powder coating, acrylic diffuser with Driver as per IS: 15885 (Part 2/
Sec
13) : 2012 , operating voltage range of 150 to 265 Volts AC, P.F > 0.9,
Surge protection: 2KV,THD<10%, with high power LED's having
efficacy
of > 90 lumins/watt,CCT: 3000K - 5700K, minimum CRI>70, .etc.,
complete
Makes : Surya /C&S / Syska / Enrich / Stanjo / Polycab/ Ib LED/
Opple/ Luker/ Orbit/Trinic/Lumens/Panasonic /Rhino/ GLO LED/
Vimal
b) LED MAKE : CREE / NICHIA / OSRAM / SAMSUNG / EVERLIGHT
a) Material
12W Each 1.00 800.00 800.00 ELEC 3.8.5 449/667
b) Labour charges :
Skilled Electrician Day 0.17 -
Helpers Day 0.17 -
Sub Total 800.00
Overhead & Margin % 13.62% 800.00 108.92
Municipal Labor Allowance @25% on labor % 25% - -
Total 908.92
Bldngs_Elec-9-5
Exhaust Fan
223/317
Supply of 12" (300mm) Light duty exhaust fan with metalic blades
and wire guard etc complete.
Each 1.00 1,450.00 1,450.00 ELEC-5.1.11 Pg 472/667
Makes: Crompton / Bajaj Bahar WG / Havells Ventil Air-DB / Orient
hill air/Halonix /Polycab/ G.M. (Xenix)
Lab0ur
Bldngs_Elec-9-5-
9.7.36 Page Electrician ( Licensed ) day 0.04 575.00 23.96
225/317
Helper (Lineman Electric / Telephone) day 0.04 460.00 19.17
Helper day 0.04 460.00 19.17
Mason day 0.04 500.00 20.83
Sub-Total 1,533.13
Overhead & Margin % 13.62% 1,533.13 208.73
Municipal Labor Allowance @25% on labor % 25% 83.13 20.78
Total 1,762.64
Flood Light
Lab0ur
Electrician ( Licensed ) day 575.00
Helper (Lineman Electric / Telephone) day 460.00
Helper day 460.00
Mason day 500.00
Sub-Total 13,410.00
Overhead & Margin % 13.62% 13,410.00 1,825.77
Municipal Labor Allowance @25% on labor % 25% -
Total 15,235.77
Lighting and Power Distribution Board
Supply of ………………... Protection suitable for
………..S.P. out goings and for 1 No 4 pole Incommer etc
BLD-ELEC-4-4 Page
complete as per IS 8623; IS 13032; IEC 61439-3. .
Item C No.
Makes: Legrand(Ekinox 3) / Schneider-Acti9/Hager -
182/317
Novello+/ Seimens/Crabtree Xpro classique-II/L&TNewrange
.
a) Material
(8 +24) 8 Way TPN DB Horizontal with IP 43, 24 Nos Nos 1.00 4,300.00 4,300.00 ELEC-2.13.4 438/667
63A 4 Pole,100mcb Nos 1.00 1,835.00 1,835.00 ELEC-2.10.1 433/667
6-32A SP MCB Nos 24.00 190.00 4,560.00 ELEC-2.10.1
Copper Busbar and etc Lum 1.00 -
b) Labour charges :
Skilled Electrician Day 0.25 610.00 152.50
Semi Skilled Electrician Day 0.50 500.00 250.00
Helpers Day 0.50 500.00 250.00
Sub Total 11,347.50
Overhead & Margin % 13.62% 11,347.50 1,544.96
Municipal Labor Allowance @25% on labor % 25% 652.00 163.00
Total 13,055.46
SPN DB-8 Way
Supply and fixing of of 8 Way SPN DB with IP 43, 8 NosProtection
suitable for …………. S.P out goings and for 1 No
BLD-ELEC-4-4 Page
Incommer etc complete as per IS 8623; IS 13032; IEC 61439-3.
Item C No. Nos 1.00 1,300.00 1,300.00 ELEC-2.13.1 436 /667
Makes: Legrand(Ekinox 3) / Schneider-Acti9/Hager -Novello+/
182/317
Seimens/Crabtree
Xpro classique-II/L&T-Newrange/Indo Asian-Opti Pro.
6-32A DP MCB Nos 1.00 575.00 575.00 ELEC-2.10.1 433/667
6-32A SP MCB - 6 Nos Nos 8.00 190.00 1,520.00 ELEC-2.10.1 433/667
a) Material
Sub-Total 8,133.70
Overhead & Margin % 13.62% 8,133.70 1,107.40
Municipal Labor Allowance @25% on labor % 25% 1,743.70 435.93
Total 9,677.03
per Meter 96.77
Supply and laying of FRLS-H / HFFR PVC insulated 1100V grade as per
BLD-ELEC-3-
IS : 694 / 1990 specification for Copper cable.
1 -3.1.5 Pg
Makes: Finolex / RR kabel / Havells
169/317
/KEI/Polycab/Gloster/Goldmedal/GM
a) Material
2R 4 Sqmm +1c 1.5 sqmm Mtrs 100.00 74.50 7,450.00 ELEC-1.5.1 415/667
1R of 2.5 sqmm Mtrs 100.00 21.40 2,140.00
Labor
Skilled Electrician Day 1.00 610.00 610.00
Semi Skilled Electrician Day 3.00 500.00 1,500.00
Helpers Day 1.00 500.00 500.00
Sub-Total 12,200.00
Overhead & Margin % 13.62% 12,200.00 1,661.03
Municipal Labor Allowance @25% on labor % 25% 2,610.00 652.50
Total 14,513.53
Per Meter 145.14
Supply and transportation of following XLPE insulated, 1100V grade
Bldngs_Elec-15-4-
armoured alluminium cable as per specification confirming to IS:7098
15.6.2 Pg 277/317
(Part - I)./1554-I
a) Material
50SqmmX 3.5 core Nos 100.00 325.00 32,500.00 ELEC-4.1.1 463/667
Excavation of earth 100 x 0.3 X 0.9 m cum 27.00
Cost of bricks (Civil SSR) 1000 Nos 0.92
Cost of sand (Civil SSR) cum 6.00
Cement (Civil SSR) Kg 25.00
Cost of cable route indicator each 12.00 ELEC-8.1.25 290/526
Transportation charges of bricks and sand Ls
b) Labour charges :
Man Mazdoor for spreading the sand and back filling the excavated
each 2.50
soil.
Electrician ( Licensed ) Day 1.00 610.00 610.00
Lineman Electric / Telephone Day 2.00 500.00 1,000.00
Man Mazdoor for concreting and embedding of cable way indicators Day 2.00
Sundires and Rounding off
Sub Total 34,110.00
Overhead & Margin % 13.62% 34,110.00 4,644.08
Municipal Labor Allowance @25% on labor % 25% 1,610.00 402.50
Rate for 100 Mtrs 39,156.58
Rate per Mtrs 391.57
Supply and transportation of following XLPE insulated,1100V grade
armoured alluminium cable as per specification confirming to IS:7098
(Part - I)./1554-I
a) Material
16SqmmX 4 core Nos 100.00 165.00 16,500.00 ELEC-4.1.1 463/667
Excavation of earth 100 x 0.3 X 0.9 m cum 27.00 -
Cost of bricks (Civil SSR) 1000 Nos 0.92 -
Cost of sand (Civil SSR) cum 6.00 -
Cement (Civil SSR) Kg 25.00 -
Cost of cable route indicator each 12.00 -
Transportation charges of bricks and sand Ls
b) Labour charges :
Man Mazdoor for spreading the sand and back filling the excavated
each 2.50 420.00 -
soil.
Electrician ( Licensed ) Day 1.00 610.00 610.00
Lineman Electric / Telephone Day 2.00 500.00 1,000.00
Man Mazdoor for concreting and embedding of cable way indicators Day 2.00 420.00
Sundires and Rounding off
Sub Total 18,110.00
Overhead & Margin % 13.62% 18,110.00 2,465.68
Municipal Labor Allowance @25% on labor % 25% 1,610.00 402.50
Rate for 100 Mtrs 20,978.18
Rate per Mtrs 209.78
a) Material
3 core 1.5 Sqmm Mtrs 1.00 95.00 95.00 ELEC-4.1.5 Pg 465/667
Labor
Skilled Electrician ( Licensed ) day 610.00 -
Helpers day 500.00 -
Sub-Total 95.00
Overhead & Margin % 13.62% 95.00 12.93
Municipal Labor Allowance @25% on labor % 25% - -
Total 107.93
Supply and making one end termination with heavy duty double
compression brass gland as per BS 6121:2005 ,IP 66 complete,SIBG
type, heavy duty Alluminium lugs duly crimped with crimping tool,
PVC tape etc for following size of
Armoured PVC insulated & PVC sheathed/ XLPE aluminium conductor
cable of
1100 volt grade as required of size. Makes:Dowels/Comet/SMI
a) Material
3.5 coreX50Sqmm No 1.00 350.00 350.00 ELEC-4.1.10 468/667
b) Labour charges :
Skilled Electrician Day -
Helpers Day -
Sub Total 350.00
Overhead & Margin % 13.62% 350.00 47.65
Municipal Labor Allowance @25% on labor % 25% - -
Total 397.65
a) Material
4 coreX16Sqmm No 1.00 230.00 230.00 ELEC-4.1.10 468/667
b) Labour charges :
Skilled Electrician Day -
Helpers Day -
Sub Total 230.00
Overhead & Margin % 13.62% 230.00 31.31
Municipal Labor Allowance @25% on labor % 25% - -
Total 261.31
BLD-ELEC-5-1 -
Earth work excavation of hard gravel soil with small boulders for
5.1.2 page Cum 1.27 -
trench 1st step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
187/317
Earth work hard disintegrated rock and boulders for trench 2nd Step
Cum 1.87 -
of size 1.2 x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
Laying C.C bed in Cement mortar with 1: 2:4 with 20 mm HBG Stone
Cum 0.90 -
Metal (Civil SSR).
Masonary through with brick Masonry with CM 1:3 Cum 0.23 -
Cement plastering inside through with 1:3 Cement mortar, 12 mm
Sqm 2.09 -
thick (Civil SSR).
40mm dia G.I pipe Class 'B' Rmt 2.50 401.00 1,002.50 BMW-F.87 pg 372/667
19mm dia G.I pipe Rmt 0.30 -
G.I Funel covered with wire mesh Each 1.00 80.00 80.00 ELEC-8.1.30 549/667
ELEC-6.7.6 Pg 531/667
25mm x 6mm x 200 mm length G.I Strip (Flat) with 4 Nos. Holes of (converted Strip Kgs
Each 1.00 15.00 15.00
12mm dia. into Meters and arrived
200mm length strip)
Drilling of staggered holes of 12mm dia to G.I pipe. Set 16.00 6.00 96.00 ELEC-8.4.20 552/667
G.I Bolts, Nuts and Washers. Set 4.00 12.00 48.00 ELEC-8.4.20 552/667
Hard Coke. Set 4.00 20.00 80.00 ELEC-8.1.10 549/667
Salt. Kg 20.00 15.00 300.00 ELEC-8.1.10 549/667
2 Reinforcement steel (HYSD/TMT ) ; Fe-500/Fe- tonne 41,000 G.O.RT.NO.336, dated 19.10.2020 of TR&B Dept
500D
3 Structural steel angle / channel / beam / bars tonne 41,000 G.O.RT.NO.336, dated 19.10.2020 of TR&B Dept
5 Structural steel / MS-Plates tonne 42,500 G.O.RT.NO.336, dated 19.10.2020 of TR&B Dept
1 Water charges (Urban) KiloLitre 110 Materials other than covered under WR Work
items For the year 2020-21, M-189(a), page no
35
Crew
Hire charge
Sl. No Description of machinery Unit Fuel charge in Rs Charge in Total in Rs
in Rs
Rs.
1 2 3 4 5 6 7
1 Agitator car / Transit mixer 2 cum Hour 635.00 1,205.90 344.80 2,185.70
2 Air compressor 5 cmm ( electric ) Hour 86.80 287.00 202.80 576.60
3 Air compressor 7 cmm ( diesel ) Hour 195.20 986.70 259.60 1,441.50
4 Air compressor 7 cmm ( electric ) Hour 109.60 382.70 202.80 695.10
5 Air compressor 8.5 cmm ( diesel) Hour 223.10 1,233.30 259.60 1,716.00
6 Air compressor 8.5 cmm ( electric) Hour 136.90 478.40 202.80 818.10
7 Air compressor 15 cmm ( electric) Hour 108.50 1,063.10 216.30 1,387.90
8 Angle Dozer 90 hp Hour 1,453.50 843.60 287.30 2,584.40
9 Batching plant 0.5 cum ( 6 Cum/hr) Hour 93.40 127.60 415.50 636.50
10 Batching plant 2 x 1.00 cum (15 Cum/hr) Hour 330.40 382.70 415.50 1,128.60
11 Batching plant 2 x 1.50 cum ( 50 Cum/hr) Hour 505.90 467.70 415.50 1,389.10
12 Bending machine 3000 x 12 mm Hour 36.20 127.60 162.20 326.00
13 Clamp shell and hoisting ropes Hour 5.00 0.00 0.00 5.00
14 Concrete bucket 1.5 cum Hour 13.30 0.00 0.00 13.30
15 Concrete hand mixer 45 / 30 ltr Hour 4.80 0.00 0.00 4.80
16 Concrete mixer 300 / 200 ( diesel) Hour 44.90 109.60 270.40 424.90
17 Concrete mixer 300 / 200 ltr (electric) Hour 43.90 42.50 270.40 356.80
18 Concrete mixer 600 / 400 ( diesel) Hour 76.40 219.30 270.40 566.10
19 Concrete mixer 600 / 400 ltr (electric) Hour 74.90 85.00 270.40 430.30
20 Concrete paver 100 sqm / hr Hour 293.30 0.00 519.20 812.50
21 Convey mucker Hour 686.30 296.00 216.30 1,198.60
22 Core drilling machine Hour 267.60 328.90 344.80 941.30
23 Diesel generating set 30 KVA Hour 55.10 877.00 162.20 1,094.30
24 Diesel generating set 50 KVA Hour 68.80 1,315.50 162.20 1,546.50
25 Diesel Loco 45 hp Hour 320.30 740.00 202.80 1,263.10
26 Dewatering pump 5 hp ( diesel ) Hour 8.50 109.60 134.80 252.90
27 Dewatering pump 5 hp ( electric ) Hour 2.50 42.50 101.10 146.10
28 Dewatering pump 10 hp ( diesel ) Hour 12.90 219.30 134.80 367.00
29 Dewatering pump 10 hp ( electric) Hour 5.60 85.00 101.10 191.70
30 Dewatering pump 20 hp ( diesel ) Hour 40.70 438.50 134.80 614.00
31 Dewatering pump 20 hp ( electric Hour 10.30 170.10 101.10 281.50
32 Drifter Hour 269.50 0.00 431.00 700.50
33 Drilling jumbo Hour 318.30 59.20 216.30 593.80
34 Dumper 4.5 cum Hour 499.30 552.50 275.80 1,327.60
35 Geophysical Electric resistivity meter Hour 90.80 0.00 0.00 90.80
36 Grouting pump Hour 20.00 42.50 324.50 387.00
37 Guniting / sand blast equipment Hour 102.50 0.00 270.40 372.90
38 Ice plant & accessories 30 t / day Hour 155.30 1,211.90 162.20 1,100.60
39 Jack hammer Hour 16.50 0.00 405.60 422.10
40 Needle vibrator 40 mm ( petrol ) Hour 6.50 21.90 194.60 223.00
41 Needle vibrator 40 mm ( electric ) Hour 6.90 8.50 194.60 210.00
42 Needle vibrator 60 mm ( petrol ) Hour 6.80 32.80 194.60 234.20
43 Needle vibrator 60 mm ( electric ) Hour 8.40 12.80 194.60 215.80
44 Planing machine 4 m stroke Hour 105.80 127.60 259.60 493.00
45 Plate shearing machine up to 12 mm Hour 37.80 170.10 172.40 380.30
46 Pneumatic placer 0.5 cum Hour 145.50 0.00 105.30 250.80
47 Pneumatic tamper Hour 17.40 0.00 324.50 341.90
48 Pug cutting machine Hour 6.10 0.00 4.30 10.40
49 Pusher leg Hour 11.30 0.00 0.00 11.30
50 Road roller diesel 10 t Hour 170.20 986.70 264.60 1,421.50
51 Shovel 0.50 cum 75 hp Hour 869.30 657.80 287.30 1,814.40
52 Shovel 0.85 cum 110 hp Hour 1,452.20 1,205.90 287.30 2,945.40
53 Stationery derrick crane Hour 71.20 0.00 0.00 71.20
54 Tipper 5 cum Hour 384.40 414.40 215.50 1,014.30
55 Tipping tub 1.5 cum Hour 55.00 0.00 0.00 55.00
56 Tower crane 5 tonne Hour 711.10 221.10 229.80 1,162.00
57 Transformer 250 KVA Hour 4,756.50 0.00 0.00 4,756.50
58 Truck 10 t Hour 348.40 414.40 215.50 978.30
59 Truck mounted derrick crane 5 t Hour 448.00 414.40 215.50 1,077.90
60 Upright drilling machine/grinder Hour 19.20 42.50 236.00 297.70
61 Ventilation fan 20 hp Hour 10.80 170.10 34.90 215.80
62 Vibratory pad foot roller 8 t Hour 1,175.20 1,425.20 324.50 2,924.90
63 Wagon drill Hour 161.20 0.00 344.80 506.00
64 Water tanker 8000 ltr Hour 358.00 414.40 215.50 987.90
65 Welding set Hour 14.20 0.00 102.10 116.30
66 Winch 35 hp (electric ) Hour 117.60 208.40 324.50 650.50
67 Tractor with 2-T roller Hour 345.00 0.00 0.00 345.00
68 Hydraulic Truck Crane 30T Hour 2,763.70 1,627.00 650.20 5,040.90
69 Hydraulic Truck Crane 16T Hour 1,935.40 1,438.90 650.20 4,024.50
70 Heavy Duty Airless Spray Painting Equipment Hour 104.60 0.00 0.00 104.60
Concrete Placer Pump (25 cum/hr) (Electric) / 30
71 Hour 813.60 510.30 202.80 1,526.70
Cum
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
50
Total Total
Payable Payable
Conveyance Charges
Blastin Machine Unload Deduct Net Total Amount in Amount in
Source Total Sub
S. Lead g Crushing Loading ing 13.615% on loading & Add 40% Rs per unit Rs per unit
Description of item (Name of Unit Basic Rate Loading & Total in
NO in KM Charge Charges charges Total Charges in Rs Charge Loading & un unloading GVMC A A including including
quarry) Chargeabl Net unloading Rs
s (25%) Distance as per chargeable s in rs loading charges in Rs loading,unlo loading,unlo
Per e Amount conveyanc
in km CSSR in Amount in ading and ading and
in Rs e
Rs Rs stacking stacking
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
780.00 12.00 130.80 130.80 130.80 910.80 910.80
51
Total Total
Payable Payable
Conveyance Charges
Blastin Machine Unload Deduct Net Total Amount in Amount in
Source Total Sub
S. Lead g Crushing Loading ing 13.615% on loading & Add 40% Rs per unit Rs per unit
Description of item (Name of Unit Basic Rate Loading & Total in
NO in KM Charge Charges charges Total Charges in Rs Charge Loading & un unloading GVMC A A including including
quarry) Chargeabl Net unloading Rs
s (25%) Distance as per chargeable s in rs loading charges in Rs loading,unlo loading,unlo
Per e Amount conveyanc
in km CSSR in Amount in ading and ading and
in Rs e
Rs Rs stacking stacking
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
52
Total Total
Payable Payable
Conveyance Charges
Blastin Machine Unload Deduct Net Total Amount in Amount in
Source Total Sub
S. Lead g Crushing Loading ing 13.615% on loading & Add 40% Rs per unit Rs per unit
Description of item (Name of Unit Basic Rate Loading & Total in
NO in KM Charge Charges charges Total Charges in Rs Charge Loading & un unloading GVMC A A including including
quarry) Chargeabl Net unloading Rs
s (25%) Distance as per chargeable s in rs loading charges in Rs loading,unlo loading,unlo
Per e Amount conveyanc
in km CSSR in Amount in ading and ading and
in Rs e
Rs Rs stacking stacking
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
0.00 9.80 Km 0.00
590.00 12.00 130.80 130.80 130.80 720.80 720.80
53
Seigniorage Charges : 2020 - 21
Total Quantity. of
Quantity Seigniorage charges Seigniorage Charges
Sl. No. Description of Item Unit Description of Material coefficient Material
finished item Per Cum Amount
collected
15,595.00
say 80,000.00