Abstract of Bill -Oct-2022

Job No & Name: 3025, BMRCL Project, Bangalore


WO No: 4600023676 Bill Date: 30-10-2022
Project: PHASE 2A/P1/60(a): “Construction of elevated structures (Viaduct & Stations) of length 9.859 km from Chainage 0.000 m to 9859.000 m and 6 Nos of elevated metro stations viz, Central Silk Board, HSR layout, Agara, Ibbalur, Bellandur, Kadubeesanahalli
including road widening, Utility diversion and allied works of Bengaluru Metro Rail Project Phase-2A”. & “Construction of loops, ramps for road flyover at Central Silk Board junction of approx. length of 2.84 Km including Road widening & allied works in Reach-5 line
(R5/P4) of Bengaluru Metro Rail Project, Phase-2.”

Sub Contractor: M/s. PRAVEEN KUMAR CONSTRUCTIONS Site / Location: Steel Yard& CSB-3025 Bill Period : From 26.09.2022 to 25.10.2022
Job Description :Pile Cap,Pier Civil Works RA Bill : 02

Rate QUANTITY CERTIFIED AMOUNT CERTIFIED (RUPEES)


S.No. Description Unit
(Rs) Till last bill This month Up to Date Till last bill This month Up to Date
Labour charges for Earthwork excavation by manual means for foundation of buildings, water supply and sanitary lines
and electrical conduits. either in pits or in trenches 1.5m and above in width in soil not exceeding1.5 m.in depth
1 including dressing the bottom and sides of pits and trenches, stacking the excavated soil clear from edges of Cum 250.00 75.978 54.000 129.978 18,994.50 13,500.00 32,494.50
excavation with lead up to 50 m including breaking of clods complete as per specification in Ordinary soil as per the
instruction of EIC
LABOUR CHARGES FOR PLACING OF Plain Cement CONCRETE FOR FOUNDATION WORKS. RATES ARE
INCLUSIVE OF POURING OF CONCRETE, CURING ETC. MEASURMENT OF CONCRETE VOLUME SHALL BE AS
2 Cum 120.00 - 2.809 2.809 - 337.07 337.07
PER DRAWINGS / AS PER ACTUAL WHICHEVER IS LESS. OVER FLOW VOLUME CANNOT BE MEASURED FOR
PAYMENT. WORK SHALL BE CARRIED OUT AS PER SPECIFICATION AND AS DIRECTED BY EIC..

Labour charges for carrying out backfilling in plinth area manually with selected/approved earth within 30mtr. lead in 300mm thick
3 layers including consolidation and watering etc., complete as per specification, approved methodology and as per instructions of the Cum 60.00 2.175 36.720 38.895 130.50 2,203.20 2,333.70
Engineer-in-charge.

Labour charges for Pile cap Tying and stacking of reinforcement of various diameters at site including Scope includes
shifting of reinforcement, necessary tools and tackles required for cutting & bending of reinforcement.. Reinforcement &
5 MT 3,800.00 25.746 22.365 48.111 97,834.80 84,987.00 1,82,821.80
Binding wire will be provided by AFCONS. Measurement of qty shall be as per drawings / as per actuals whichever is
less. All works are to be completed as directed by EIC-New
Labour charges for Shuttering & de-shuttering of Pile Cap. Scope of work includes erection of shutter plate by using
nuts and bolts in true line and level, Cleaning of shutter and applying shutter releasing agents prior to fixing, providing
6 Sqm 150.00 74.520 110.160 184.680 11,178.00 16,524.00 27,702.00
of foam to make water-tight joints. Rates are exclusive of cost of materials which shall be provided by Afcons on FOC
basis. All works are to be carried-out as per the instructions of EIC.
Labour charges for placing of Ready Mix concrete RCC for Pile Cap works by using Con. Pump. Rates are inclusive
of setting of concrete pump pipe, applying of vibrator ,compacting ,finishing , levelling ,collection of materials from store
8 and return to store after completion of works, and curing etc. Measurement of concrete volume shall be as per Cum 140.00 141.176 140.454 281.630 19,764.64 19,663.56 39,428.20
drawings / as per actuals whichever is less. All works are to be completed as directed by EIC-Rate revised w.e.f sept
22
Labour charges for Pier ,Tying, and stacking of reinforcement of various diameters site including Scope includes
shifting of reinforcement, necessary tools and tackles required for cutting & bending of reinforcement.. Reinforcement &
10 MT 4,200.00 2.074 3.448 5.522 8,710.80 14,481.60 23,192.40
Binding wire will be provided by AFCONS. Measurement of qty shall be as per drawings / as per actuals whichever is
less. All works are to be completed as directed by EIC
Labour charges for placing of Ready-Mix concrete RCC for Pier works by using Boom placer. Rates are inclusive of
applying of vibrator ,compacting ,finishing , levelling ,collection of materials from store and return to store after
11 Cum 250.00 - 4.577 4.577 - 1,144.25 1,144.25
completion of works, and curing etc. Measurement of concrete volume shall be as per drawings / as per actuals
whichever is less. All works are to be completed as directed by EIC
R2-Labour charges for Shuttering & de-shuttering of Pier. Scope of work includes erection of shutter plate by using
nuts and bolts in true line and level, Cleaning of shutter and applying shutter releasing agents prior to fixing, providing
12 Sqm 250.00 - 19.780 19.780 - 4,945.02 4,945.02
of foam to make water-tight joints. Rates are exclusive of cost of materials which shall be provided by Afcons on FOC
basis. All works are to be carried-out as per the instructions of EIC.-Rate revision -R2

Labour charges Grouting of piles through Sonic pipe. Scope includes shifting of all material, grouting using approved
13 Per pile 120.00 2.000 3.000 5.000 240.00 360.00 600.00
material. All works are to be carried-out as per the instructions of EIC.

1 of 2
Abstract of Bill -Oct-2022

Job No & Name: 3025, BMRCL Project, Bangalore


WO No: 4600023676 Bill Date: 30-10-2022
Project: PHASE 2A/P1/60(a): “Construction of elevated structures (Viaduct & Stations) of length 9.859 km from Chainage 0.000 m to 9859.000 m and 6 Nos of elevated metro stations viz, Central Silk Board, HSR layout, Agara, Ibbalur, Bellandur, Kadubeesanahalli
including road widening, Utility diversion and allied works of Bengaluru Metro Rail Project Phase-2A”. & “Construction of loops, ramps for road flyover at Central Silk Board junction of approx. length of 2.84 Km including Road widening & allied works in Reach-5 line
(R5/P4) of Bengaluru Metro Rail Project, Phase-2.”

Sub Contractor: M/s. PRAVEEN KUMAR CONSTRUCTIONS Site / Location: Steel Yard& CSB-3025 Bill Period : From 26.09.2022 to 25.10.2022
Job Description :Pile Cap,Pier Civil Works RA Bill : 02

Rate QUANTITY CERTIFIED AMOUNT CERTIFIED (RUPEES)


S.No. Description Unit
(Rs) Till last bill This month Up to Date Till last bill This month Up to Date

Labour Charges for Welding of Earthing rods -Scope includes welding-material required for welding will be provided by
Per pile 130.00 - 12.000 12.000 - 1,560.00 1,560.00
AFCONS. Work to be carried out as per Direction of Engineer In Charge

Labour Charges for Straightening of Pile rods and making L for pile cap -material required will be provided by
15 Per pile 180 10.000 12.000 22.000 1,800.00 2,160.00 3,960.00
AFCONS. Work to be carried out as per Direction of Engineer In Charge

Labour Charges for un loading of reinforcement steel as per approved method statement and as per the instruction of
16 Mt 55.00 25.746 22.365 48.111 1,416.03 1,230.08 2,646.11
Engineer-In-Charge.

17 Labour Charges fo Stagging&destagging Works -upto 10m height Cum 40.00 108.000 322.927 430.927 4,320.00 12,917.08 17,237.08

A Total 1,65,689.27 1,93,076.60 3,58,765.87


B Add: IGST on Sub Total A @ 18% 14,912.03 17,376.89 32,288.93
C Sub Total (A+B) 1,80,601.30 2,10,453.50 3,91,054.80
D Less: Retention on Sub Total C @ 5% (8,284.46) (9,653.83) (17,938.29)
E Less: TDS on Sub Total A @ 1% (1,656.89) (1,930.77) (3,587.66)
F Net Amount (C-D-E) 1,70,659.95 1,98,868.90 3,69,528.85
1,70,660.00 1,98,869.00 3,69,529.00

SES :

Site QS Sub Contractor Accounts QS Manager PM

2 of 2