Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
14 including T&P and scaffolding wherever necessary, sorting the dismantled CUM 185.4 342.35 63471.69 18.21 18.21 342.35 6234.19
material, disposal of unserviceable material and stacking the serviceable
material with all lifts complete as per specifications. iii) Dismantling Stone
Masonry. -do- Rubble stone masonry in cement mortar including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, woodwork, steelwork,
8 15 including T&P and scaffolding wherever necessary, sorting the dismantled CUM 46.35 380.38 17630.613 68.69 11.59 380.38 57.10 380.38 26128.3
material, disposal of unserviceable material and stacking the serviceable material
with all lifts completeas per specifications. i) By Mechanical Means, Cement
Concrete Grade M-15 & M-20. including all lead and lifts etc., complete and as
per the direction of the Engineer-in-charge.
416619.71
Providing and laying heavy duty cobble stones interlock pavers 75mm thick,
using cement and course sand for manufacture of blocks of approved size,
shape and colour with a minimum compressive strength of 281 kg per sqm over
50mm thick sand bed (average thickness) and compacting with plate vibrator Additional road length of 60m has been
SQM 9182.75 1085.56 9968426.09 taken for development as per the site
6 7 having 3 tons compaction force thereby forcing part of sand underneath to come 9182.75 9968426.09 53.68 9236.43 58272.86 0 58272.860 inspection note of the GM(Tech)
up in between JOints, final compaction of paver surface JOints into its final dated:10.07.2020. Hence the quantity has
level, including cost of materials, labour and HOM complete as per been increased
specifications. including all lead and lifts etc., complete and as per the direction
of the Engineer-in-charge.
Qty Upto 125% 1085.56
Qty more than 125%
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, In DPR this item has been considered only
for Road no. 2 & 4, but in site it is found that
including T&P and scaffolding wherever necessary, sorting the dismantled CUM 185.4 342.35 63471.69 there was existing SSM drain in all the roads.
material, disposal of unserviceable material and stacking the serviceable Additional storm water drain length of 200m
8 14 185.4 63471.69 18.21 203.61 6234.19 0 6234.19
material with all lifts complete as per specifications. iii) Dismantling Stone has been taken for development as per the
Masonry. -do- Rubble stone masonry in cement mortar including all lead and lifts joint site inspection note of the GM(Tech),
etc., complete and as per the direction of the Engineer-in-charge. HDSCL & BSCL dated:28.08.2020. Hence the
quantity has been increased
Qty Upto 125% 342.35
Qty more than 125%
Dismantling of existing structures like culverts, bridges, retaining walls and other In DPR this item has been considered only
structure comprising of masonry, cement concrete, woodwork, steelwork, for Road no. 2 & 4, but in site it is found that
CUM 46.35 380.38 17630.613 68.69 there was existing SSM drain in all the roads.
including T&P and scaffolding wherever necessary, sorting the dismantled Additional storm water drain length of 200m
9 15 material, disposal of unserviceable material and stacking the serviceable material 46.35 17630.61 115.04 4408.60 21719.70 26128.30 has been taken for development as per the
with all lifts completeas per specifications. i) By Mechanical Means, Cement joint site inspection note of the GM(Tech),
Concrete Grade M-15 & M-20. including all lead and lifts etc., complete and as HDSCL & BSCL dated:28.08.2020. Hence the
per the direction of the Engineer-in-charge. quantity has been increased
Qty Upto 125% 380.38 11.59
Qty more than 125% 380.38 57.10
Total 394900.01 21719.70 416619.71
Add 12% GST 47388.00 2606.36 49994.37
Grand total 442288.01 24326.06 466614.08
Anticipated quantity to
As per BOQ Upto 125 % Above 125 % Excess Savings
Item Complete the work Variation/Excess
SNo Item Name Unit Reasons for excess/savings
Code qty
Quoted Total Amount
Quantity Quantity Amount Qty Rate Amount Qty Rate Amount Qty Amount Qty Amount
Rate (Rs.) (Rs.)
Construction of granular sub-base Grading-V as Sub-base and drainage layer Additional road length of 60m has been
by providing coarse graded crushed stone aggregates of granite/trap/basalt taken for development as per the site
5 5 material, mixing by mix in place method by rotavator at OMC, spreading in CUM 421.92 1706.85 720154.15 443.13 756348.76 21.21 21.21 1706.85 36202.290 21.21 36202.29 inspection note of the GM(Tech)
dated:10.07.2020. Hence the quantity has
uniform layers with motor grader on prepared surface and compacting with been increased
vibratory power roller to achieve the 98 % proctor density, complete as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Providing and laying heavy duty cobble stones interlock pavers 75mm thick,
using cement and course sand for manufacture of blocks of approved size, Additional road length of 60m has been
shape and colour with a minimum compressive strength of 281 kg per sqm taken for development as per the site
7 7 SQM 9182.75 1085.56 9968426.09 9236.43 10026700.04 53.68 53.68 1085.56 58272.860 53.68 58272.860 inspection note of the GM(Tech)
over 50mm thick sand bed (average thickness) and compacting with plate dated:10.07.2020. Hence the quantity has
vibrator having 3 tons compaction force thereby forcing part of sand been increased
underneath to come up in between JOints, final compaction of paver surface
JOints into its final level, including cost of materials, labour and HOM
complete as per specifications. including all lead and lifts etc., complete and as
per the direction of the Engineer-in-charge.
Plain cement concrete M10 mix with crushed stone aggregate 40mm nominal
size mechanically mixed, placed in foundation and compacted by vibration
8 8 CUM 174.05 4186.18 728604.63 170 711650.60 4.05 16954.03
including curing including cost of materials, labour, HOM complete as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Providing T.M.T bar Fe500 steel reinforcement for R.C.C work including
strenghting,cutting,bending,hooking,placing in position,lapping and/or welding
11 11 wherever required,typing with binding wire and anchoring to the adjoining TONNE 48.91 68572.61 3353886.36 44 3017194.84 4.91 336691.5151
members wherever necessary complete as per design (laps,hooks,and wastage
shall not be measured and paid) cost of materials,labuor,HOM of Machinaery
complete sa per specification. including all lead and lifts etc., complete and as
per the direction of the Engineer-in-charge.
Supply and fixing of Cast Steel Double Flanged Dual Plate check valve class
150 Cinforming to API 594 with latest amendments of 100 mm diameters and
19 19 types and conveying to work site, loading unloading, stacking etc., complete EACH 2 4668.98 9337.96 2 9337.96
with all lead and lift.The rates are inclusive of cost of Bolts and Nuts. including
all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
Constructing brick masonry inspection chamber for single pipeline, using table
moulded non-modular bricks of class designation 50 in cement mortar 1:5, C
I cover withframe (light duty) internal dimensions, total weight of cover
with frame to be not less than 38 kg ( weight of cover 23kg and weight of
frame 15 kg) R. C. C. top slab with cement concrete M 15 with 20mm and
downsize granite metal, foundation concrete M 5 with 40mm and downsize
20 20 EACH 4 5881.33 23525.32 4 23525.32
granite metal inside plastering 12mm thick with cement mortar 1:3, finish
smooth with a floating coat of cement on walls and bed concrete complete as
per standard design including cost of materials, labour charges, curing
complete as per specifications. 450x450mm and 600mm depth (clear inside
dimension) for single pipeline, using table moulded non-modular bricks of
class designation 50 in cement mortar 1 5, C I cover withframe (light duty)
450x450mmx600mm including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 2nd Year: Cleaning of outer periphery like
21 21
roads, footpaths, kerb stones including removing grass, dust etc., to the nearest Sqm 9182 1.01 9273.82 9182 9273.82
garbage pit using suitable coconut broomstic, bombay broomstick,
squezers / wipers / rubber brushes, coir brushes, bamboo baskets, plastic
buckets, mugs trolley etc., complete including all lead and lifts etc., complete
and as per the direction of the Engineer-in-charge.
23 23 Operation and Maintenance for 2nd Year: Removing and resetting of CC Sqm 183.64 199.82 36694.94 183.64 36694.94
interlocking paver blocks from carriageway area including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 2nd Year: Providing and laying heavy duty
cobble stones interlock pavers of 75mm thick, using cement and course sand
for manufacture of blocks of approved size, shape and colour with a
minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
24 24 Sqm 183.64 1128.99 207327.72 183.64 207327.72
(average thickness) and compacting with plate vibrator having 3 tons
compaction force thereby forcing part of sand underneath to come up in
between Joints, final compaction of paver surface Joints into its final level,
including cost of materials, labour and HOM complete as per specifications.
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 2nd Year: Removing and resetting of drain
25 25 slab including all lead and lifts etc., complete and as per the direction of the Sqm 13.64 199.82 2725.54 13.64 2725.54
Engineer-in-charge.
Operation and Maintenance for 2nd Year: Cleaning surface drains including
removing of dirt dust etc., using suitable soap powder, coconut broomstick,
26 26 squeezers I wipers/ rubber brushes, coir brushes, plastric brushes, mugs, M 1818 8.12 14762.16 1818 14762.16
booster pumps with portable arrangement, hose pipe etc., complete. including
all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
Operation and Maintenance for 3rd Year: Cleaning of outer periphery like
27 27 roads, footpaths, kerb stones including removing grass, dust etc., to the nearest Sqm 9182 1.03 9457.46 9182 9457.46
garbage pit using suitable coconut broomstic, bombay broomstick,
squezers / wipers / rubber brushes, coir brushes, bamboo baskets, plastic
buckets, mugs trolley etc., complete including all lead and lifts etc., complete
and as per the direction of the Engineer-in-charge.
29 29 Operation and Maintenance for 3rd Year: Removing and resetting of CC Sqm 275.46 203.67 56102.94 275.46 56102.94
interlocking paver blocks from carriageway area including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Providing and laying heavy duty
cobble stones interlock pavers of 75mm thick, using cement and course sand
for manufacture of blocks of approved size, shape and colour with a
minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
30 30 Sqm 275.46 1150.69 316969.07 275.46 316969.07
(average thickness) and compacting with plate vibrator having 3 tons
compaction force thereby forcing part of sand underneath to come up in
between Joints, final compaction of paver surface Joints into its final level,
including cost of materials, labour and HOM complete as per specifications.
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 3rd Year: Plain cement concrete M10 mix with
34 34 crushed stone aggregate 40mm nominal size mechanically mixed, placed in Cum 5.73 4437.36 25426.07 5.73 25426.07
foundation and compacted by vibration including curing including cost of
materials, labour, HOM complete as per specifications. including all lead and
lifts etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Providing T.M.T bar Fe500 steel
reinforcement for R.C.C work including
strenghting,cutting,bending,hooking,placing in position,lapping and/or welding
35 35 Tonne 1.37 72686.96 99581.14 1.37 99581.14
wherever required,typing with binding wire and anchoring to the adjoining
members wherever necessary complete as per design (laps,hooks,and wastage
shall not be measured and paid) cost of materials,labuor,HOM of Machinaery
complete sa per specification.Specification No. KBS 4.6.3 - TMT bars Fe 500
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 3rd Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal of form work for vertical
36 36 surface such as walls at any thickness, including attached pilasters, buttresses, Sqm 57.26 369.09 21134.09 57.26 21134.09
plinth cills and string courses cost of all materials, labour complete as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal ofform work for suspended
37 37 floors, landings, balconies and likes, thickness upto 200 mm, 0 to 5mts Sqm 24.54 409.41 10046.92 24.54 10046.92
height including cost of all materials, labour complete as per specifications
for heights more than
3.50m from ground level. including all lead and lifts etc., complete and as per
the direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Providing and laying in position
reinforced cement concrete of design Mix M25 with OPC @ 340kgs, with
20mm and down size graded granite metal coarse aggregates @0.70cum
and fine aggregtes @ 0.47cum, with super plasticisers @31ts confirming to
38 38 IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in layers not Cum 17.18 6298.31 108204.97 17.18 108204.97
exceeding 15 ems thick, vibrated for all works in ground floor level for roof
slabs, staircase, lintels and beams retaining walls, return walls, walls (any
thickness) including attached pilasters, columns, lintles, pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping, bed blocks, anchor
blocks, plain window cills, fillets etc., including cost of all materials, labour,
HOM curing, complete but excluding cost of reinforcement as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Refilling of available earth around
pipelines, in layers not exceeding 20cms in depth, compacting each deposited
39 39 layer by ramming after watering all lead and lift including cost of all labour Cum 11.45 64.1 733.95 11.45 733.95
including consolidation by mechanical means approved by Engineer In charge,
when earth is at suitable moisture content with desired field density upto 95%
maximum dry density (modified heavy proctor test) for restoration of roads
without settlement including HOM of machineries, complete. including all
lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 3rd Year: Removing and resetting of drain
40 40 slab including all lead and lifts etc., complete and as per the direction of the Sqm 20.45 203.67 4165.05 20.45 4165.05
Engineer-in-charge.
Operation and Maintenance for 3rd Year: Cleaning surface drains including
removing of dirt dust etc., using suitable soap powder, coconut broomstick,
41 41 squeezers I wipers/ rubber brushes, coir brushes, plastric brushes, mugs, M 1818 8.27 15034.86 1818 15034.86
booster pumps with portable arrangement, hose pipe etc., complete. including
all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
Operation and Maintenance for 4th Year: Cleaning of outer periphery like
42 42 roads, footpaths, kerb stones including removing grass, dust etc., to the nearest Sqm 9182 1.05 9641.10 9182 9641.10
garbage pit using suitable coconut broomstic, bombay broomstick,
squezers / wipers / rubber brushes, coir brushes, bamboo baskets, plastic
buckets, mugs trolley etc., complete including all lead and lifts etc., complete
and as per the direction of the Engineer-in-charge.
44 44 Operation and Maintenance for 4th Year: Removing and resetting of CC Sqm 367.28 207.52 76217.95 367.28 76217.95
interlocking paver blocks from carriageway area including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 4th Year: Providing and laying heavy duty
cobble stones interlock pavers of 75mm thick, using cement and course sand
for manufacture of blocks of approved size, shape and colour with a
minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
45 45 Sqm 367.28 1017.55 373725.76 367.28 373725.76
(average thickness) and compacting with plate vibrator having 3 tons
compaction force thereby forcing part of sand underneath to come up in
between Joints, final compaction of paver surface Joints into its final level,
including cost of materials, labour and HOM complete as per specifications.
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 4th Year: Providing T.M.T bar Fe500 steel
reinforcement for R.C.C work including
strenghting,cutting,bending,hooking,placing in position,lapping and/or welding
50 50 Tonne 1.72 74058.41 127380.47 1.72 127380.47
wherever required,typing with binding wire and anchoring to the adjoining
members wherever necessary complete as per design (laps,hooks,and wastage
shall not be measured and paid) cost of materials,labuor,HOM of Machinaery
complete sa per specification.Specification No. KBS 4.6.3 - TMT bars Fe 500
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 4th Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal of form work for vertical
51 51 surface such as walls at any thickness, including attached pilasters, buttresses, Sqm 76.35 376.06 28712.18 76.35 28712.18
plinth cills and string courses cost of all materials, labour complete as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 4th Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal ofform work for suspended
52 52 floors, landings, balconies and likes, thickness upto 200 mm, 0 to 5mts Sqm 32.72 417.13 13648.49 32.72 13648.49
height including cost of all materials, labour complete as per specifications
for heights more than
3.50m from ground level. including all lead and lifts etc., complete and as per
the direction of the Engineer-in-charge.
Operation and Maintenance for 4th Year: Providing and laying in position
reinforced cement concrete of design Mix M25 with OPC @ 340kgs, with
20mm and down size graded granite metal coarse aggregates @0.70cum
and fine aggregtes @ 0.47cum, with super plasticisers @31ts confirming to
53 53 IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in layers not Cum 22.91 6417.15 147016.91 22.91 147016.91
exceeding 15 ems thick, vibrated for all works in ground floor level for roof
slabs, staircase, lintels and beams retaining walls, return walls, walls (any
thickness) including attached pilasters, columns, lintles, pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping, bed blocks, anchor
blocks, plain window cills, fillets etc., including cost of all materials, labour,
HOM curing, complete but excluding cost of reinforcement as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 4th Year: Refilling of available earth around
pipelines, in layers not exceeding 20cms in depth, compacting each deposited
54 54 layer by ramming after watering all lead and lift including cost of all labour Cum 15.27 65.31 997.28 15.27 997.28
including consolidation by mechanical means approved by Engineer In charge,
when earth is at suitable moisture content with desired field density upto 95%
maximum dry density (modified heavy proctor test) for restoration of roads
without settlement including HOM of machineries, complete. including all
lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 4th Year: Removing and resetting of drain slab
55 55 including all lead and lifts etc., complete and as per the direction of the Sqm 27.27 207.52 5659.07 27.27 5659.07
Engineer-in-charge.
Operation and Maintenance for 4th Year: Cleaning surface drains including
removing of dirt dust etc., using suitable soap powder, coconut broomstick,
56 56 squeezers I wipers/ rubber brushes, coir brushes, plastric brushes, mugs, M 1818 8.43 15325.74 1818 15325.74
booster pumps with portable arrangement, hose pipe etc., complete. including
all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
Operation and Maintenance for 5th Year: Cleaning of outer periphery like
57 57 roads, footpaths, kerb stones including removing grass, dust etc., to the nearest Sqm 9182 1.08 9916.56 9182 9916.56
garbage pit using suitable coconut broomstic, bombay broomstick,
squezers / wipers / rubber brushes, coir brushes, bamboo baskets, plastic
buckets, mugs trolley etc., complete including all lead and lifts etc., complete
and as per the direction of the Engineer-in-charge.
59 59 Operation and Maintenance for 5th Year: Removing and resetting of CC Sqm 183.64 211.36 38814.15 183.64 38814.15
interlocking paver blocks from carriageway area including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Providing and laying heavy duty
cobble stones interlock pavers of 75mm thick, using cement and course sand
for manufacture of blocks of approved size, shape and colour with a
minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
60 60 Sqm 183.64 1194.12 219288.20 183.64 219288.20
(average thickness) and compacting with plate vibrator having 3 tons
compaction force thereby forcing part of sand underneath to come up in
between Joints, final compaction of paver surface Joints into its final level,
including cost of materials, labour and HOM complete as per specifications.
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 5th Year: Plain cement concrete M10 mix with
64 64 crushed stone aggregate 40mm nominal size mechanically mixed, placed in Cum 3.82 4604.8 17590.34 3.82 17590.34
foundation and compacted by vibration including curing including cost of
materials, labour, HOM complete as per specifications. including all lead and
lifts etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Providing T.M.T bar Fe500 steel
reinforcement for R.C.C work including
strenghting,cutting,bending,hooking,placing in position,lapping and/or welding
65 65 Tonne 0.86 75429.87 64869.69 0.86 64869.69
wherever required,typing with binding wire and anchoring to the adjoining
members wherever necessary complete as per design (laps,hooks,and wastage
shall not be measured and paid) cost of materials,labuor,HOM of Machinaery
complete sa per specification.Specification No. KBS 4.6.3 - TMT bars Fe 500
including all lead and lifts etc., complete and as per the direction of the
Engineer-in-charge.
Operation and Maintenance for 5th Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal of form work for vertical
66 66 surface such as walls at any thickness, including attached pilasters, buttresses, Sqm 38.18 383.02 14623.70 38.18 14623.70
plinth cills and string courses cost of all materials, labour complete as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Providing and removing centering,
shuttering, strutting, propping etc., and removal ofform work for suspended
67 67 floors, landings, balconies and likes, thickness upto 200 mm, 0 to 5mts Sqm 16.36 424.86 6950.71 16.36 6950.71
height including cost of all materials, labour complete as per specifications
for heights more than
3.50m from ground level. including all lead and lifts etc., complete and as per
the direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Providing and laying in position
reinforced cement concrete of design Mix M25 with OPC @ 340kgs, with
20mm and down size graded granite metal coarse aggregates @0.70cum
and fine aggregtes @ 0.47cum, with super plasticisers @31ts confirming to
68 68 IS9103-1999 Reaffirmed-2008, machine mixed, concrete laid in layers not Cum 11.45 6535.98 74836.97 11.45 74836.97
exceeding 15 ems thick, vibrated for all works in ground floor level for roof
slabs, staircase, lintels and beams retaining walls, return walls, walls (any
thickness) including attached pilasters, columns, lintles, pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping, bed blocks, anchor
blocks, plain window cills, fillets etc., including cost of all materials, labour,
HOM curing, complete but excluding cost of reinforcement as per
specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Refilling of available earth around
pipelines, in layers not exceeding 20cms in depth, compacting each deposited
69 69 layer by ramming after watering all lead and lift including cost of all labour Cum 7.64 66.52 508.21 7.64 508.21
including consolidation by mechanical means approved by Engineer In charge,
when earth is at suitable moisture content with desired field density upto 95%
maximum dry density (modified heavy proctor test) for restoration of roads
without settlement including HOM of machineries, complete. including all
lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Operation and Maintenance for 5th Year: Removing and resetting of drain slab
70 70 including all lead and lifts etc., complete and as per the direction of the Sqm 13.64 211.36 2882.95 13.64 2882.95
Engineer-in-charge.
Operation and Maintenance for 5th Year: Cleaning surface drains including
removing of dirt dust etc., using suitable soap powder, coconut broomstick,
71 71 squeezers I wipers/ rubber brushes, coir brushes, plastric brushes, mugs, M 1818 8.58 15598.44 1818 15598.44
booster pumps with portable arrangement, hose pipe etc., complete. including
all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
Total 24946070.08 24327983.81 416619.71 1034686.94
Scarifying the Existing Bituminous surface to a depth of 50mm by Mechanical Means. Scarifying the existing bituminous road surface
1 1 to a depth of 50mm and disposal of scarified material and complete as per specifications. including all lead and lifts etc., complete and
as per the direction of the Engineer-in-charge.
ROAD 1 from chainage 0+ 000 to 0+158 1 158 5.2 821.60
ROAD 2 from chainage 0+000 to 0+007 1 7 6 42.00
0+007 to 0+105 1 98 7 686.00
ROAD 3 from chainage 0+000 to 0+198 1 198 5.5 1089.00
ROAD 4 from chainage 0+000 to 0+210 1 210 7.9 1659.00
0+210 to 0+ 300 1 90 8.2 738.00
0+330 to 0+470 1 134.45 9.3 1255.76
GRAND TOTAL SQM 6291.36
BOQ QUANTITY 5564.60
NET EXCESS QUANTITY 726.76
UPTO 125% 726.76
ABOVE 125% 0.00
Compaction of original ground by mechanical means including filling in depression occuring during rolling including cost of all
2 2 labour, HOM complete as per specifications. including all lead and lifts etc., complete and as per the direction of the Engineer-in-
charge.
ROAD 1 from chainage 0+ 000 to 0+158 1 158 5.2 821.60
ROAD 2 from chainage 0+000 to 0+007 1 7 6 42.00
0+007 to 0+105 1 98 7 686.00
ROAD 3 from chainage 0+000 to 0+198 1 198 5.5 1089.00
ROAD 4 from chainage 0+000 to 0+210 1 210 7.9 1659.00
0+210 to 0+ 300 1 90 8.2 738.00
0+330 to 0+470 1 134.45 9.3 1255.76
GRAND TOTAL SQM 6291.36
BOQ QUANTITY 5564.60
Page 13 of 32
NET EXCESS QUANTITY 726.76
UPTO 125% 726.76
ABOVE 125% 0.00
Construction of sub-grade and earthen shoulders with approved material Gravei/Murrum with all lifts & leads, transporting to site,
spreading, grading to required slope and compacted to meet requirement of Table No. 300-2 complete as per specifications, including
4 4
cost of earth, watering charges & compaction by vibratory roller to 97% of modified proctors density) including all lead and lifts
etc., complete and as per the direction of the Engineer-in-charge.
Construction of granular sub-base Grading-V as Sub-base and drainage layer by providing coarse graded crushed stone aggregates of
granite/trap/basalt material, mixing by mix in place method by rotavator at OMC, spreading in uniform layers with motor grader on
5 5
prepared surface and compacting with vibratory power roller to achieve the 98 % proctor density, complete as per specifications.
including all lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Page 14 of 32
Providing, laying, spreading and compacting crushed stone aggregates of granite / trap / basalt to wet mix macadam specifications
including pre mixing the material with water at OMC in mechanical mix plant carriage of mixed materials by tipper to site, laying in
6 6
uniform layers with paver in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired
density complete as per specifications. including all lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Providing and laying heavy duty cobble stones interlock pavers 75mm thick, using cement and course sand for manufacture of
blocks of approved size, shape and colour with a minimum compressive strength of 281 kg per sqm over 50mm thick sand bed
7 7 (average thickness) and compacting with plate vibrator having 3 tons compaction force thereby forcing part of sand underneath to
come up in between JOints, final compaction of paver surface JOints into its final level, including cost of materials, labour and HOM
complete as per specifications. including all lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Page 15 of 32
1 TO 30 1 30 7 210
30 TO 60 1 30 6.9 207
60 TO 90 1 30 7.1 213
90 TO 120 1 30 7.05 211.5
120 TO 150 1 30 6.9 207
150 TO 180 1 30 6.85 205.5
180 TO 198 1 18 7.85 141.3
DEDUCTION 35.758
TOTAL 3 1359.542
ROAD 4 0+000 to 0+030 1 30 10.05 301.5
ROAD 4 0+030 to 0+050 1 20 9.8 196
ROAD 4 0+050 to 0+080 1 30 9.8 294
ROAD 4 0+080 to 0+110 1 30 9.95 298.5
ROAD 4 0+110 to 0+140 1 30 9.95 298.5
ROAD 4 0+140 to 0+170 1 30 10.1 303
ROAD 4 0+170 to 0+210 1 40 10.03 401.2
ROAD 4 0+210 to 0+240 1 30 11.75 352.5
ROAD 4 0+240 to 0+270 1 30 11.95 358.5
ROAD 4 0+270 to 0+300 1 30 12.2 366
ROAD 4 0+300 to 0+330 1 30 12.35 370.5
ROAD 4 0+330 to 0+360 1 30 12.9 387
ROAD 4 0+360 to 0+390 1 30 13.6 408
ROAD 4 0+390 to 0+420 1 30 13.95 418.5
ROAD 4 0+420 to 0+450 1 30 14.15 424.5
ROAD 4 0+450 to 0+480 1 30 14.3 429
ROAD 4 0+480 to 0+510 1 30 14.3 429
DEDUCTION 236.250
TOTAL 4 5799.951
GRAND TOTAL (1+2+3+4) SQM 9236.431
BOQ QUANTITY 9182.75
NET EXCESS QUANTITY 53.681
UPTO 125% 53.681
ABOVE 125% 0
Page 16 of 32
Providing and laying Plain / Reinforced Cement Concrete in Foundation with OPC design mix M30 @ 360kgs, with 20mm and down
size graded granite metal coarse aggregates @0.69cum and fine aggregates@ 0.46cum, with superplasticizer @31ts confirming to
12 12 IS9103-1999 Reaffirmed-2008 complete as per Drawing and Technical Specifications including cost of all materials, labour, HOM
curing, form works, scaffolding and centering complete as per specifications. including all lead and lifts etc., complete and as per the
direction of the Engineer-in-charge.
ROAD 1 from chainage 0+ 000 to 0+158 LONGITUDINAL 2 158 0.2 0.2 12.64
ROAD 1 TRANSVERSE DIRECTION @ 29 1 7.25 0.15 0.125 0.136
ROAD 1 TRANSVERSE DIRECTION @ 52 1 6.9 0.15 0.125 0.129
ROAD 1 TRANSVERSE DIRECTION @ 75 1 7.55 0.15 0.125 0.142
ROAD 1 TRANSVERSE DIRECTION @ 105 1 7.3 0.15 0.125 0.137
ROAD 1 TRANSVERSE DIRECTION @ 131 1 6.9 0.15 0.125 0.129
ROAD 2 from chainage 0+ 000 to 0+105 LONGITUDINAL 2 105 0.2 0.2 8.400
ROAD 2 TRANSVERSE DIRECTION @ 25 1 9.2 0.15 0.125 0.173
ROAD 2 TRANSVERSE DIRECTION @ 50 1 9.45 0.15 0.125 0.177
ROAD 2 TRANSVERSE DIRECTION @ 80 1 9.47 0.15 0.125 0.178
ROAD 3 from chainage 0+000 to 0+198 2 198 0.2 0.2 15.840
ROAD 3 TRANSVERSE DIRECTION @ 33 1 7 0.15 0.125 0.131
ROAD 3 TRANSVERSE DIRECTION @ 60 1 6.9 0.15 0.125 0.129
ROAD 3 TRANSVERSE DIRECTION @ 85 1 7.1 0.15 0.125 0.133
ROAD 3 TRANSVERSE DIRECTION @ 111 1 7.05 0.15 0.125 0.132
ROAD 3 TRANSVERSE DIRECTION @ 135 1 6.9 0.15 0.125 0.129
ROAD 3 TRANSVERSE DIRECTION @ 164 1 6.85 0.15 0.125 0.128
ROAD 4 LONGITUDINAL from chainage 0+000 to 0+470 2 470 0.2 0.2 37.6
ROAD 4 LONGITUDINAL from chainage 0+470to 0+507.3 2 37.3 0.5 0.2 7.46
ROAD 4 TRANSVERSE DIRECTION @ 25 1 9.8 0.15 0.125 0.184
ROAD 4 TRANSVERSE DIRECTION @ 50 1 9.8 0.15 0.125 0.184
ROAD 4 TRANSVERSE DIRECTION @ 75 1 9.8 0.15 0.125 0.184
ROAD 4 TRANSVERSE DIRECTION @ 100 1 9.95 0.15 0.125 0.187
ROAD 4 TRANSVERSE DIRECTION @ 130 1 9.95 0.15 0.125 0.187
ROAD 4 TRANSVERSE DIRECTION @ 150 1 10.1 0.15 0.125 0.189
ROAD 4 TRANSVERSE DIRECTION @ 173 1 10.03 0.15 0.125 0.188
ROAD 4 TRANSVERSE DIRECTION @ 233 1 10.03 0.15 0.125 0.188
ROAD 4 TRANSVERSE DIRECTION @ 258 1 10.03 0.15 0.125 0.188
ROAD 4 TRANSVERSE DIRECTION @ 282 1 12.1 0.15 0.125 0.227
ROAD 4 TRANSVERSE DIRECTION @ 307 1 12.3 0.15 0.125 0.231
ROAD 4 TRANSVERSE DIRECTION @ 335 1 12.3 0.15 0.125 0.231
ROAD 4 TRANSVERSE DIRECTION @ 360 1 13.3 0.15 0.125 0.249
Page 17 of 32
ROAD 4 TRANSVERSE DIRECTION @ 389 1 13.9 0.15 0.125 0.261
ROAD 4 TRANSVERSE DIRECTION @ 413 1 13.3 0.15 0.125 0.249
ROAD 4 TRANSVERSE DIRECTION @ 440 1 13.3 0.15 0.125 0.249
ROAD 4 TRANSVERSE DIRECTION @ 485 1 12.5 0.15 0.125 0.234
ROAD 4 TRANSVERSE DIRECTION @ 507.3 1 11.9 0.15 0.125 0.223
GRAND TOTAL CUM 87.756
BOQ QUANTITY 77.850
NET EXCESS QUANTITY 9.906
UPTO 125% 9.906
ABOVE 125% 0.000
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete,
wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
14 14
material and stacking the serviceable material with all lifts complete as per specifications. iii) Dismantling Stone Masonry. -do- Rubble
stone masonry in cement mortar including all lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
ROAD 2 RHS FROM CHAINAGE 0+040 To 0+070 2 30.00 0.38 0.60 13.68
ROAD 2 RHS FROM CHAINAGE 0+070 To 0+100 2 30.00 0.38 0.60 13.68
ROAD 2 RHS FROM CHAINAGE 0+100 To 0+103 2 3.00 0.38 0.60 1.37
Total 28.73
ROAD 2 LHS FROM CHAINAGE 0+065 To 0+095 1 30.00 0.38 0.60 6.84
ROAD 2 LHS FROM CHAINAGE 0+095 To 0+103 1 8.00 0.38 0.60 1.82
Total 8.66
ROAD 3 LHS FROM CHAINAGE 0+000 To 0+200 1 200.00 0.38 0.60 45.60
ROAD 4 RHS FROM CHAINAGE 0+210 To 0+240 2 30 0.38 0.6 13.68
ROAD 4 RHS FROM CHAINAGE 0+240 To 0+270 2 30 0.38 0.6 13.68
ROAD 4 RHS FROM CHAINAGE 0+270 To 0+300 2 30 0.38 0.6 13.68
ROAD 4 RHS FROM CHAINAGE 0+300 To 0+330 2 30 0.38 0.6 13.68
ROAD 4 RHS FROM CHAINAGE 0+319.1 To 0+322.4 2 3.3 0.38 0.6 -1.5
Total 53.22
ROAD 4 RHS FROM CHAINAGE 0+000 To 0+030 2 30.00 0.38 0.60 13.68
ROAD 4 RHS FROM CHAINAGE 0+030 TO 0+060 2 30.00 0.38 0.60 13.68
ROAD 4 RHS FROM CHAINAGE 0+060 To 0+090 2 30.00 0.38 0.60 13.68
ROAD 4 RHS FROM CHAINAGE 0+090 To 0+120 2 30.00 0.38 0.60 13.68
ROAD 4 RHS FROM CHAINAGE 0+8.2 To 0+20.4 2 12.20 0.38 0.60 -5.56
Total 49.16
ROAD 4 RHS FROM CHAINAGE 0+120 TO 0+150 1 30.00 0.38 0.60 6.84
ROAD 4 RHS FROM CHAINAGE 0+150 To 0+180 1 30.00 0.38 0.60 6.84
ROAD 4 RHS FROM CHAINAGE 0+180 To 0+200 1 20.00 0.38 0.60 4.56
Page 18 of 32
Total 18.24
GRAND TOTAL CUM 203.61
BOQ QUANTITY 185.40
NET EXCESS QUANTITY 18.21
UPTO 125% 18.21
ABOVE 125% 0.00
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete,
woodwork, steelwork, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
15 15
material and stacking the serviceable material with all lifts completeas per specifications. i) By Mechanical Means, Cement Concrete
Grade M-15 & M-20. including all lead and lifts etc., complete and as per the direction of the Engineer-in-charge.
Page 19 of 32
Total 1 31.25 4.36
Dismantelling Drain Bottom(RHS) Road - 04
From Ch- 0 to 30 30 0.6 0.15 2.7
From Ch- 30 to 60 30 0.6 0.15 2.7
From Ch- 60 to 90 30 0.6 0.15 2.7
From Ch- 90 to 120 30 0.6 0.15 2.7
From Ch- 8.2 to 20.4 12.2 0.38 0.15 -0.70
Total 120 10.10
From Ch- 120 to 150 2 30 0.6 0.1 3.6
From Ch- 150 to 180 2 30 0.6 0.1 3.6
From Ch- 180 to 200 2 20 0.6 0.1 2.4
Total 80 9.6
From Ch- 210 to 240 1 30 0.6 0.15 2.7
From Ch- 240 to 270 1 30 0.6 0.15 2.7
From Ch- 270 to 300 1 30 0.6 0.15 2.7
From Ch- 300 to 330 1 30 0.6 0.15 2.7
From Ch- 319.1 to 322.4 1 3.3 0.6 0.15 -0.297
Total 123.3 10.503
Dismantelling slab concrete (RHS) Road - 02
From Ch- 6.7 to 9.7 3 0.8 0.15 0.34
From Ch- 40.45 to 48.6 (CD) 8.15 1 0.2 1.39
Total 1.72
From Ch- 79.9 to 83.4 3.5 0.75 0.15 0.39
From Ch- 84.6 to 88.0 3.4 0.75 0.15 0.38
0.78
Dismantelling Drain Bottom(RHS) Road - 02
From Ch- 40 to 70 30 0.6 0.1 1.8
From Ch- 70 to 100 30 0.6 0.1 1.8
From Ch- 100 to 103 3 0.6 0.1 0.18
Total 63 3.78
Dismanteling of drain bottom (LHS) Road - 02
From Ch- 65 to 95 30 0.38 0.6 6.84
From Ch- 95 to 103 8 0.38 0.6 1.824
8.664
Dismantelling Slab conrete (RHS) Road - 03
From Ch- 3.7 to 5.65 1.95 0.9 0.15 0.26
from Ch- 14.5 to 19.9 5.4 1 0.15 0.81
From Ch- 26.1 to 33.5 7.4 0.85 0.15 0.94
From Ch- 37.8 to 40.25 2.45 0.9 0.15 0.33
Page 20 of 32
From Ch- 43.55 to 45.4 1.85 0.9 0.15 0.25
from Ch- 51 to 54.4 3.4 0.9 0.15 0.46
From Ch- 61.6 to 68.5 6.9 1 0.15 1.04
From Ch- 76 to 77.7 1.7 0.85 0.15 0.22
From Ch- 78.3 to 80.1 1.8 0.9 0.15 0.24
From Ch- 86.2 to 89.6 3.4 1 0.15 0.51
From Ch- 96.4 to 100.4 4 0.9 0.15 0.54
from Ch- 111.8 to 118.7 6.9 1 0.15 1.04
From Ch- 125.35 to 130 4.65 0.85 0.15 0.59
From Ch- 136.65 to 140 3.35 1 0.15 0.50
From Ch- 150 to 153.9 3.9 0.9 0.15 0.53
From Ch- 160.8 to 163.95 3.15 1 0.15 0.47
From Ch- 173.1 to 175.6 2.5 0.9 0.15 0.34
From Ch- 176.8 to 180 3.2 1 0.15 0.48
Total 9.55
Dismantelling Slab Road No 3 LHS
Chanage
From Ch- 28.1 to 32.2 1 4.1 1.05 0.15 0.65
From Ch- 40.1 to 44.2 1 4.1 0.95 0.15 0.58
From Ch- 54 to 58.6 1 4.6 1 0.15 0.69
From Ch- 64.9 to 70 1 5.1 0.85 0.15 0.65
From Ch- 72 to 83.8 1 11.8 0.75 0.15 1.33
From Ch- 85.4 to 90.4 1 5 1 0.15 0.75
From Ch- 102.1 to 106.1 1 4 1.1 0.15 0.66
From Ch- 113 to 120.2 1 7.2 1 0.15 1.08
From Ch- 126.3 to 142.1 1 15.8 0.9 0.15 2.13
From Ch- 148.7 to 154.4 1 5.7 0.95 0.15 0.81
From Ch- 163.5 to 168.2 1 4.7 0.9 0.15 0.63
From Ch- 175.5 to 180 1 4.5 0.85 0.15 0.57
From Ch- 191.7 to 193.8 1 2.1 0.8 0.15 0.25
From Ch- 196 to 200 1 4 0.75 0.15 0.45
Total 11.24
Dismantelling Drain bottom Road No 3 LHS
Chanage Nos L B D Q
0-30 1 30 1.05 0.15 4.73
30-60 1 30 1.05 0.15 4.73
60-90 1 30 1.05 0.15 4.73
90-120 1 30 1.05 0.15 4.73
120-150 1 30 1.05 0.15 4.73
Page 21 of 32
150-180 1 30 1.05 0.15 4.73
180-200 1 20 1.05 0.15 3.15
31.50
Page 22 of 32
Dismantelling Slab concrete Road - 01
11.2 - 15 3.8 0.75 0.15 0.43
23.1 - 25.1 2 0.75 0.15 0.23
31.1 - 34.95 3.85 0.75 0.15 0.43
45.8 - 49.65 3.85 0.75 0.15 0.43
57.35 - 61.85 4.5 0.75 0.15 0.51
68.4 - 72.9 4.7 0.75 0.15 0.53
79.65 - 84.55 4.9 0.75 0.15 0.55
104.85 - 110.65 5.8 0.75 0.15 0.65
115.7 - 119.45 3.75 0.75 0.15 0.42
153.7 - 158 4.3 0.75 0.15 0.48
Total 4.66
GRAND TOTAL CUM 115.04
BOQ QUANTITY 46.35
NET EXCESS QUANTITY 68.69
UPTO 125% 10.75
ABOVE 125% 57.94
Page 23 of 32
BELAGAVI SMART CITY LIMITED, BELAGAVI
work order no: BSCL/BID/PB-14/WO/2019-20/3045/4,Dtd: 07/01/2020
CONTRACTOR: SHRI BHARATESH J BUDAVI
Name of work: CONSTRUCTION OF ROAD WITH PAVER BLOCK AT SBI COLONY (RANI CHENNAMMA NAGAR) IN BELAGAVI CITY - PACKAGE-14
Variation No:- 01
Rate Analysis For BOQ Items
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, woodwork, steelwork,
1 including T&P and scaffolding wherever necessary, sorting the dismantled 16.00 Cum 390.00 19.50 409.50 29.12 380.38
material, disposal of unserviceable material and stacking the serviceable material
with all lifts completeas per specifications. i) By Mechanical Means, Cement
Concrete Grade M-15 & M-20. including all lead and lifts etc., complete and as
per the direction of the Engineer-in-charge.
Nil
Total Amount:- - - -
A Contract Details
2 _NA_
*does this NON-BOQ item is a substitute of a BOQ item? If so, give cost implication.
NO
1.2 Proposed variation quantity. (+)/(-) X BOQ rate or Non BOQ rate amount.
1.4 Sketch of Drawing or Photos explaining varation - Length, Dia, RLs Etc. shall be furnished. BOQ Provision shall be shown in continous line and proposed
variation shall be shown in dotted lines on sketch or drawing may explain more than one item.
a) for BOQ
D Scheule no. :
1.1 to 4: as above
Summary of variation statement no….......................... Schedule wise
₹ -618,067.23
upto date % increase = -2.48%
₹ 24,946,070.08
Contractor PMC Assistant Engineer Assistant Executive Engineer Excutive Engineer General Manager - (Technical)
BSCL BSCL BSCL BSCL
General Abstract of variation
CONSTRUCTION OF ROAD WITH PAVER BLOCK AT SBI COLONY (RANI CHENNAMMA NAGAR) IN BELAGAVI
1 Name of work
CITY - PACKAGE-14
2 Contract package PAVER BLOCKS -14
3 Contract amount in rupees 24946070.08
4 Name of contractor SHRI. BHARATESH J BUDAVI,Class-I Contractor ,Tilakwadi,Belagavi.
₹ -618,067.23
% of variation with respect to WO cost= -2.48%
₹ 24,946,070.08
₹ -618,067.23
Net % of variation wrt the DPR Amount= -1.91%
₹ 32,400,000.00
Contractor PMC Assistant Engineer Assistant Executive Engineer Excutive Engineer General Manager - (Technical)
BSCL BSCL BSCL BSCL
BELAGAVI SMART CITY LIMITED
CONSTRUCTION OF ROAD WITH PAVER BLOCK AT SBI COLONY (RANI CHENNAMMA NAGAR) IN BELAGAVI CITY -
PACKAGE-14
Variation Order 01
Nil
Name of work: CONSTRUCTION OF ROAD WITH PAVER BLOCK AT SBI COLONY (RANI
CHENNAMMA NAGAR) IN BELAGAVI CITY - PACKAGE-14
Variation No:- 01
Statement -2 The Details of Non BoQ items in Variation-1
Rate inclusive As per Variation
SNo Item Name Unit of TP @ Remarks
-0.094483% Qty Amount
Nil
Total Amount :- -