Professional Documents
Culture Documents
Abstract of Cost
Page 1
WATER TANK
ABSTRACT OF COST
Project : Construction and Supervision of Janakpur Oil Refinery Factory
Location : Janakpur
Structure : Water Tank 30 KL- 2 Compartments including 500 mm free baord (L=2m, B= 2.5 m, H= 2m 2 COMPARTMENTS)
ABSTRACT OF COST- UG WATER TANK (6MX2.5MX2 M -2 COMPARTMENTS) - CIVIL WORKS
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Abstract of Cost
Page 3
WATER TANK
DETAILED MEASUREMENT SHEET
#REF!
#REF!
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
1 Site Clearance and cleaning after completion
2 Foundation Works
Water Tank
1 7.000 3.500 3.000 73.50
Total: 73.50
GRAVELLY MIXED SOIL PACKING BELOW FOOTING: Providing,
laying, spreading, watering, levelling and full compaction (90%) of 500
2.2 mm thick gravelly mixed soil subbase grading material as per table m3
12.1 of standard specification(DoR Specification) and instruction of
Engineer.
1 7.000 3.500 0.300 7.35
Total: 7.35
Water Tank
1 7.000 3.500 0.150 3.68
Total: 3.68
Measurement Sheet Page 6 Main Building Block
DETAILED MEASUREMENT SHEET
#REF!
#REF!
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
PCC - M10/40 :Providing and placing machine mixed cement concrete
Grade M10/40 for foundation PCC including compaction, curing,
2.4 m3
testing and lead 30m. etc. all complete as per specification and
drawing.
Water Tank
1 7.000 3.500 0.100 2.45
Total: 2.45
22.05
Total: 22.05
3 Concrete Works
#REF!
#REF!
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
Water Tank
Long Wall 4 6.540 3.000 78.48
Short Wall 6 3.000 3.000 54.00
Top Salb 1 6.540 3.000 19.62
Bottom Slab 1 19.080 0.500 9.54
Total: 161.64
#REF!
#REF!
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
RATE ANALYSIS
Item No : 6.1
Description of item : Earth work for foundation through all types of soil including relevant lift 1.5m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.07.01 907 Unskilled md 2.000 700.00 1400.00 tools 3 % of labour cost 42.00
Sub - total (A) 1400.00 Sub - total (B) 0.00 Sub total (c) 42.00
Direct Cost (A+B+C) = NRs. 1442.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 216.30
Total Item Rate = NRs. 1658.30
Say per cu.m. 1658.30
Item No : 2.1
Description of item : Earth work for foundation through all types of soil including relevant lift more than 1.5m up to 3.0m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
0.00
0.00
9.07.01 907 Unskilled md 3.000 700.00 2100.00 0.00 tools 3 % of labour cost 63.00
Sub - total (A) 2100.00 Sub - total (B) 0.00 Sub total (c) 63.00
Direct Cost (A+B+C) = NRs. 2163.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 324.45
Total Item Rate = NRs. 2487.45
Say per cu.m. 2487.45
RATE ANALYSIS
Item No : 3.9
Description of item : Backfilling with the graded filter material in layer with necessary watering and compaction,lead 30m, lift 1.5m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.11 2404 Skilled md 0.000 960.00 0.00 Gravel cu.m 1.1000 3309.98 3640.98
3110 Unskilled md 0.800 700.00 560.00 filter
Sub - total (A) 560.00 Sub - total (B) 3640.98 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4200.98
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 630.15
Total Item Rate = NRs. 4831.13
Say per cu.m. 4831.13
Item No : 3.10
Description of item : Backfilling in layers in foundation pits,trenches,etc including compaction and watering etc. complete lead10m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.1 908 Unskilled md 1.140 700.00 798.00 Diesel Ltr. 0.11 55.500 6.11
tools % 3 % of labour cost 23.94
Vibrator Roller hr. 0.11 500 55
1-1.5tons
Sub - total (A) 798.00 Sub - total (B) 6.11 Sub total (c) 78.94
Direct Cost (A+B+C) = NRs. 883.05
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 132.46
Total Item Rate = NRs. 1015.50
Say per cu.m. 1015.50
RATE ANALYSIS
Item No : 6.2
Description of item : Providing and fabricating gabion crates of more than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*1) 2.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.01.02 2401 Skilled md 0.840 960.00 806.40 G.I wire(Mesh) kg 25.4500 110.21 2804.84
24.02.01 Unskilled md 2.750 700.00 1925.00 G.I wire(Salvage )kg 3.4100 110.21 375.82 3 % of labour cost 81.94
24.02.04 Stone cum 2.2000 2691.63 5921.59
Sub - total (A) 2731.40 Sub - total (B) 9102.25 Sub total (c) 81.94
Direct Cost (A+B+C) = NRs. 11915.60
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1787.34
Total Item Rate = NRs. 13702.93
Say per cu.m. 6851.47
Item No : 6.4
Description of item : Providing and fabricating gabion crates of less than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*.5) 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.01.02 2401 Skilled md 0.480 960.00 460.80 G.I wire(Mesh) kg 17.3000 110.21 1906.63
24.02.01 Unskilled md 1.390 700.00 973.00 G.I wire(Salvage )kg 2.8000 110.21 308.59 3 % of labour cost 43.01
24.02.04 Stone cum 1.1000 2691.63 2960.80
Sub - total (A) 1433.80 Sub - total (B) 5176.02 Sub total (c) 43.01
Direct Cost (A+B+C) = NRs. 6652.83
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 997.92
Total Item Rate = NRs. 7650.76
Say per cu.m. 7650.76
RATE ANALYSIS
Item No : 6.5
Description of item : Providing and laying random rubble stone masonry of hard stone in 1 : 4 cement sand mortar including stone dressing,mortar transportation all complete, masoned height 0 to 5 m
lead 30m
Unit: 1.00 cu.m.
Norms Specification
activity Clause Resources
Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 4590.00 Sub - total (B) 7360.41 Sub total (c) 137.70
Direct Cost (A+B+C) = NRs. 12088.11
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1813.22
Total Item Rate = NRs. 13901.33
Say per cu.m. 13901.33
Item No : 2.3 (i)
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80
Sub - total (A) 2930.00 Sub - total (B) 8045.77 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 11288.27
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1693.24
Total Item Rate = NRs. 12981.52
Say per cu.m. 12981.52
RATE ANALYSIS
Item No : 3.1
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80
Sub - total (A) 7164.00 Sub - total (B) 10434.96 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17911.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2686.72
Total Item Rate = NRs. 20598.18
Say per cu.m. 20598.18
Item No : 3.2
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.2000 55.50 177.60
Water lit. 225.0000 0.10 22.50
Sub - total (A) 7164.00 Sub - total (B) 11280.37 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 18756.87
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2813.53
Total Item Rate = NRs. 21570.40
Say per cu.m. 21570.40
RATE ANALYSIS
Item No : 4.1
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
i) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 3.00 594.00
Sub - total (A) 4968.00 Sub - total (B) 11009.16 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16289.66
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2443.45
Total Item Rate = NRs. 18733.11
Say per cu.m. 18733.11
Item No : 4.2
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
ii) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
Operator md 0.200 960.00 192.00 10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50
Sub - total (A) 5160.00 Sub - total (B) 11269.27 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16741.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2511.27
Total Item Rate = NRs. 19253.03
Say per cu.m. 19253.03
RATE ANALYSIS
Item No : 4.3
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M30/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.4100 17736.60 7272.01 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5700 3309.98 1886.69 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3300 3309.98 1092.29
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 246.0000 0.10 24.60
Sub - total (A) 4968.00 Sub - total (B) 11924.89 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17205.39
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2580.81
Total Item Rate = NRs. 19786.19
Say per cu.m. 19786.19
Item No : 2.5
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick m3 0.0525 43502.23 2283.87
18.01 1804 Skilled md 1.500 960.00 1440.00 (0.42m3/8 times)
1805 Unskilled md 2.000 700.00 1400.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.18/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 2840.00 Sub - total (B) 3183.90 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 6023.90
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 903.59
Total Item Rate = NRs. 6927.49
Say per sq.m. 692.75
RATE ANALYSIS
Item No : 3.4
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for walls.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 9mm thick m2 1.3750 1850.44 2544.36
18.02 1804 Skilled md 2.400 960.00 2304.00 (11m2/8 times)
(i and ii
avg.) 1805 Unskilled md 2.500 700.00 1750.00 Struts balis etc cu.m 0.0750 43502.23 3262.67
(.45/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 4054.00 Sub - total (B) 6054.53 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10108.53
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.28
Total Item Rate = NRs. 11624.81
Say per sq.m. 1162.48
Item No : 4.5
Description of item : Providing , Preparing and Installing form work & removing after completion for Slab & beam structure.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick cu.m 0.1000 43502.23 4350.22
18.05 1804 Skilled md 3.000 960.00 2880.00 (0.60m3/6 times)
(I and ii
avg.) 1805 Unskilled md 3.000 700.00 2100.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.22/8 times)
Nails kg 4.0000 90.00 360.00
Sub - total (A) 4980.00 Sub - total (B) 5362.76 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10342.76
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1551.41
Total Item Rate = NRs. 11894.17
Say per sq.m. 1189.42
RATE ANALYSIS
Item No : 5.2
Description of item : Road way excavation in soft soil including disposal upto 10m and lift upto 1.5 m etc. all complete as per specification.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.01 905 Unskilled md 0.750 700.00 525.00 tools 3 % of labour cost 15.75
Sub - total (A) 525.00 Sub - total (B) 0.00 Sub total (c) 15.75
Direct Cost (A+B+C) = NRs. 540.75
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 81.11
Total Item Rate = NRs. 621.86
Say per cu.m. 621.86
Item No : 5.3
Description of item : Formation of embankment including compaction in layers not exceeding 150mm. Compacted depth, watering and haulage 10m. etc. all complete as per specification.
Skilled md 0.002 960.00 1.92 Suitable Materialm3 1.1000 200.00 220.00 Grader hr 0.0050 3000.00 15.00
9.05.01 903 (2) Unskilled md 0.008 700.00 5.60 Diesel ltr 0.1200 55.50 6.66 Roller hr 0.0167 1500.00 25.05
Sub - total (A) 7.52 Sub - total (B) 226.66 Sub total (c) 40.05
Direct Cost (A+B+C) = NRs. 274.23
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 41.13
Total Item Rate = NRs. 315.36
Say per cu.m. 315.36
RATE ANALYSIS
Item No : 5.4
Description of item : Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil:
1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 105.00 Sub - total (B) 0.00 Sub total (c) 3.15
Direct Cost (A+B+C) = NRs. 108.15
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 16.22
Total Item Rate = NRs. 124.37
Say per sq.m. 124.37
Item No : 5.5
Description of item : Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m .
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 32.80 Sub - total (B) 1903.35 Sub total (c) 139.20
Direct Cost (A+B+C) = NRs. 2075.35
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 311.30
Total Item Rate = NRs. 2386.65
Say per cu.m. 2386.65
RATE ANALYSIS
Item No : 5.6
Description of item : Supply and laying grass turfing on the various slope with cutting, watering and transportaion up to 1000m etc. all complete
Unit: 1.00 sq.m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 35.00 Sub - total (B) 39.88 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 74.88
Note :- 1 m3 turffing = 10 m2 Contractor's Overhead @ 15 % of (A+B+C) = NRs. 11.23
Total Item Rate = NRs. 86.11
Say per sq.m. 86.11
Item No : 6.3
Description of item : Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Unit: 1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 11.90 Sub - total (B) 448.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 460.40
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 69.06
Total Item Rate = NRs. 529.46
Say per sq.m. 529.46
RATE ANALYSIS
Item No : 3.3 and 4.4
Description of item : Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Diameter above 8mm and 16mm ii and iii average Unit: 1.00 ton
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 17430.00 Sub - total (B) 112309.82 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 129739.82
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 19460.97
Total Item Rate = NRs. 149200.79
Say per ton. 149200.79
Item No : 3.5
Description of item : Supplying and placing of dry stone layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 1976.00 Sub - total (B) 2960.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4936.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 740.52
Total Item Rate = NRs. 5677.32
Say per cum. 5677.32
RATE ANALYSIS
Item No : 3.6
Description of item : Supplying and placing of dry gravel layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 560.00 Sub - total (B) 1597.92 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 2157.92
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 323.69
Total Item Rate = NRs. 2481.60
Say per cum. 2481.60
Item No : 3.7
Description of item : Supplying and placing of dry sand layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 560.00 Sub - total (B) 3680.99 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4240.99
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 636.15
Total Item Rate = NRs. 4877.14
Say per cum. 4877.14
RATE ANALYSIS
Item No : 3.8
Description of item : Providing, jointing and laying HDP pipes with or without collar etc. complete in place as per specification.
Unit: 50.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 3.000 960.00 2880.00 HDP pipe m 50.00 83.30 4165.00 Screw Jack hr 8.00 70.00 560.00
Unskilled md 3.000 700.00 2100.00 Petrol ltr 0.50 104.00 52.00 Blow lamps no 5.00 180.00 900.00
7.01 701
Sub - total (A) 4980.00 Sub - total (B) 4217.00 Sub total (c) 1460.00
Direct Cost (A+B+C) = NRs. 10657.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1598.55
Total Item Rate = NRs. 12255.55
Say per m. 245.11
Item No : 4.6
Description of item : Providing and installing different types of Bearing including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 20000.00 Sub total (c) 2000.00
Direct Cost (A+B+C) = NRs. 22000.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3300.00
Total Item Rate = NRs. 25300.00
Say per no 25300.00
RATE ANALYSIS
Item No : 4.7
Description of item : Providing and installing expansion joints including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 1980.00 Sub total (c) 198.00
Direct Cost (A+B+C) = NRs. 2178.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 326.70
Total Item Rate = NRs. 2504.70
Say per m 2504.70
Item No : 6.6
Description of item : Providing and laying brick masonry in manual mixed cement mortar including preparation of mortar as per specification.
(Cement :Sand) 1:6 Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
2502 Cement t 0.06 17736.60 1064.20
25.02 2503 skilled md 1.5 960.00 1440.00 Sand m3 0.3 3346.35 1003.91 Tools 3% of labour cost 106.20
2504 Unskilled md 3.00 700.00 2100.00 Bricks no 560 8.50 4761.86
2505 water lit 36 0.1 3.60
2507
Sub - total (A) 3540.00 Sub - total (B) 6833.57 Sub total (c) 106.20
Direct Cost (A+B+C) = NRs. 10479.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1571.97
Total Item Rate = NRs. 12051.73
Say per m3 12051.73
RATE ANALYSIS
Item No : 4.8
Description of item : Supply and fixing 100mm G.I. Pipe, medium class for drainage spout necessary accessory complete as per drawing and specification.
0.75 m long (Rate =market price*l) Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 1503.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 1503.50
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 1653.85
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 248.08
Total Item Rate = NRs. 1901.93
Say per no 1901.93
Item No : 4.9
Description of item : Supply and fixing of 50mm G.I. Pipe railing as per drawings all complete
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) Sub - total (B) 631.33 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 631.33
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 694.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 104.17
Total Item Rate = NRs. 798.63
Say per m 798.63
RATE ANALYSIS
Item No : 4.11
Description of item : Laying primer course and two coats of readymade Ist grade enamel paint ncluding supply of material all complete
Unit: 100.00 m2
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Painter md 12 700.00 8400.00 Enamel Primer lit 8.1 220.00 1782.00 Tools
13-5(a)+
(b)+© Unskilled md 8.00 700.00 5600.00 Enamel Paint lit 16 272.80 4364.80
Sub - total (A) 14000.00 Sub - total (B) 6146.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 20146.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3022.02
Total Item Rate = NRs. 23168.82
Say per m2 231.69
Item No : 2.2
Description of item : Preparing well sinking site, opening road access, making island and providing and laying cutting edge of mild steel et. complete.
Unit: 1.00 tonne
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 15.000 960.00 14400.00 Mild Steel tonne 1.1000 106833.66 117517.03 Gas Cutter hr 1.0000 250.00 250.00
Unskilled md 15.000 700.00 10500.00 Nut and Bolts kg 17.0000 106.83 1816.11 Welding Machin hr 0.5000 300.00 150.00
17.02 1703
(4) Electrodes,Gas Etc (5% of Above) 5966.66
Sub - total (A) 24900.00 Sub - total (B) 125299.79 Sub total (c) 400.00
Direct Cost (A+B+C) = NRs. 150599.79
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 22589.97
Total Item Rate = NRs. 173189.76
Say per tonne. 173189.76
RATE ANALYSIS
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
i) Depth up to 3m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.600 960.00 576.00 Diesel lt. 23.0000 55.50 1276.50 hr 2.3000 3000.00 6900.00
10t. -Crane
Semiskilled md 1.200 790.00 948.00 with Grab
17.06.01 1705 Accesseries
(4)
Sub - total (A) 1524.00 Sub - total (B) 1276.50 Sub total (c) 6900.00
Direct Cost (A+B+C) = D NRs. 9700.50
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 10670.55
Contractor's Overhead @ 15 % of (D) = NRs. 1600.58
Total Item Rate = NRs. 12271.13
Say per m 12271.13
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
ii) Depth up to 3-6m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.700 960.00 672.00 Diesel lt. 24.0000 55.50 1332.00 hr 2.4000 3000.00 7200.00
10t. -Crane
Semiskilled md 1.400 790.00 1106.00 with Grab
17.06.01 1705 Accesseries
(4)
Sub - total (A) 1778.00 Sub - total (B) 1332.00 Sub total (c) 7200.00
Direct Cost (A+B+C) = D NRs. 10310.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 11341.00
Contractor's Overhead @ 15 % of (D) = NRs. 1701.15
Total Item Rate = NRs. 13042.15
Say per m 13042.15
RATE ANALYSIS
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
iii) Depth up to 6-9m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.800 960.00 768.00 Diesel lt. 26.0000 55.50 1443.00 hr 2.6000 3000.00 7800.00
10t. -Crane
Semiskilled md 1.600 790.00 1264.00 with Grab
17.06.01 1705 Accesseries
Sub - total (A) 2032.00 Sub - total (B) 1443.00 Sub total (c) 7800.00
Direct Cost (A+B+C) = D NRs. 11275.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 12402.50
Contractor's Overhead @ 15 % of (D) = NRs. 1860.38
Total Item Rate = NRs. 14262.88
Say per m 14262.88
Item No : 2.7
Description of item : Providing and filling sand in well
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
17.08 1707
(4)
Sub - total (A) 9.60 Sub - total (B) 4015.63 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 4025.23
Contractor's Overhead @ 15 % of (D) = NRs. 603.78
Total Item Rate = NRs. 4629.01
Say per m3 4629.01
Item No : 5.8
Description of item : Providing and Laying RCC hume Pipes 900mm Dia
RATE ANALYSIS
Sub - total (A) 1423.64 Sub - total (B) 8388.31 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 9811.95
Additional Cost 3% for ballies, crow,bars,chain,pulley,blocks &ropes etc.= 1.03*D 10106.31
Contractor's Overhead @ 15 % of (1.03*D) = NRs. 1515.95
Total Item Rate = NRs. 11622.25
Say per m 11622.25
Item No : 5.9
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M15/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.01 2000 Skilled md 0.500 960.00 480.00 Cement t 0.2600 17736.60 4611.52 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4600 3346.35 1539.32
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 156.0000 0.10 15.60
Sub - total (A) 2930.00 Sub - total (B) 6866.94 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 10109.44
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.42
Total Item Rate = NRs. 11625.86
Say per cu.m. 11625.86
RATE ANALYSIS
Item No : 5.12
Description of item : Providing, Mixing and Pointing Cement Mortar over rubble masonry works including all complete as per spec.
Cement:Sand (1:3)
100.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50
Sub - total (A) 2930.00 Sub - total (B) 8880.08 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 12122.58
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1818.39
Total Item Rate = NRs. 13940.97
Say per cu.m. 13940.97
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
Timber Unit :m3
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.3 700 210 ltr 0.14 55.50 7.77 hr 0.09 844.40 78.95 296.72
For 2 KM md 0.3 700 210 ltr 0.28 55.50 15.54 hr 0.10 844.40 88.24 313.78
For3 KM md 0.3 700 210 ltr 0.42 55.50 23.31 hr 0.12 844.40 97.53 330.84
For 4 KM md 0.3 700 210 ltr 0.56 55.50 31.08 hr 0.13 844.40 106.82 347.90
For5 KM md 0.3 700 210 ltr 0.70 55.50 38.85 hr 0.14 844.40 116.11 364.96
For 6 KM md 0.3 700 210 ltr 0.84 55.50 46.62 hr 0.15 844.40 125.39 382.01
For 7 KM md 0.3 700 210 ltr 0.98 55.50 54.39 hr 0.16 844.40 134.68 399.07
For 8 KM md 0.3 700 210 ltr 1.12 55.50 62.16 hr 0.17 844.40 143.97 416.13
RCC Hume Pipe(900mm Dia) Unit :m
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.4 700 280 md 0.04 960 ltr 0.08 55.50 4.33 hr 0.11 844.40 93.73 378.06
For 2 KM md 0.4 700 280 md 0.04 960 ltr 0.16 55.50 8.66 hr 0.12 844.40 98.79 387.45
For3 KM md 0.4 700 280 md 0.04 960 ltr 0.23 55.50 12.99 hr 0.12 844.40 103.86 396.85
For 4 KM md 0.4 700 280 md 0.04 960 ltr 0.31 55.50 17.32 hr 0.13 844.40 108.93 406.24
For5 KM md 0.4 700 280 md 0.04 960 ltr 0.39 55.50 21.65 hr 0.14 844.40 113.99 415.64
For 6 KM md 0.4 700 280 md 0.04 960 ltr 0.47 55.50 25.97 hr 0.14 844.40 119.06 425.03
For 7 KM md 0.4 700 280 md 0.04 960 ltr 0.55 55.50 30.30 hr 0.15 844.40 124.13 434.43
For 8 KM md 0.4 700 280 md 0.04 960 ltr 0.62 55.50 34.63 hr 0.15 844.40 129.19 443.83
#REF!
#REF!
BILL OF QUANTITY 1
Item Amount
Description Unit Quantity Rate (NRs) Rate in Words Remarks
No. (NRs)
#REF!
BILL OF QUANTITY 2
Item Amount
Description Unit Quantity Rate (NRs) Rate in Words Remarks
No. (NRs)
PLASTERING AND CEMENT PUNNING: Providing and
applying 12.5 thick cement plaster (1 cement: 4 sand) on the
internal walls, plus on ceiling .including 3 mm thick cement
punning (1 cement: 1 sand) .To be of good finishing including
10 water bead wherever necessary, raking the joints, cleaning and m2 94.86
wetting the surface, curing the works including Alkali resistance
fibre reinforcement all complete as per drawings, specifications
and instruction of A/E
Sub Total:
VAT 13%
Total :
In Words:
Submitted By:
Signature:
Contractor's Representative:
Contractor's Seal:
BILL OF QUANTITY 3