Project: Preliminary Cost Estimate of the Various works including Repair and Maintenance at Naural
Histroy Museum, Swyambhu
Site: Natural Histroy Museum, Swyambhu
SUMMARY SHEET
Particulars Amount Remarks
A. PARK DEVELOPMENT WORKS 775,000.00
B. RAINWATER HARVESTING 698,000.00
C. PROPOSED RCC HALL (EXTENSION WORKS) (CARPET 21,865,697.28
D. SOLAR WATER HEATING SYSTEM 1,000,000.00
E. MISCELLANEOUS WORKS 970,000.00
Sub Total A 25,308,697.28
Consultancy charge @ 2 % 506,173.95
Sub Total B 25,814,871.23
VAT @ 13% 3,355,933.26
Total Amount 29,170,804.48
In Words: Two crore ninety one lakh seventy thousand eight hundred four rupee and fourty eight paisa.
B. RAINWATER HARVESTING
PVC STOREAGE TANK: Supply installation of 5000 ltr. High desity Polythene
Tank upon the Masonry Base including all accessories as per drawings and all Nos 1 1.00
complete.
GUTTER: Supplly and installation of gutter of size300 mm width and 300 mm
m 200 200.00
height of plane coloured GI sheets as per drawings and all complete
110 PVC PIPES: Supply and installation of 110 PVC Pipes including all joints
m 300 300.00
and necessary accessories all complete.
D. SOLAR WATER HEATING SYSTEM
TILE PAVING: Providing and laying 60mm thick factory made cement concrete
interlocking paver block of M -30 grade made by block making machine with
strong vibratory compaction, of approved size, design & shape, laid in required
color and pattern over and including 50mm thick compacted bed of coarse sand, sq.m 1 20 2 40.00
filling the joints with line sand etc. all complete as per the direction of Engineer-
in-charge
TOILET CONSTRUCTION: Dismentaling existing Masonry Tank and
construction of a new toilet covered by 75 mm Puff panel including a comode Job 1 1.00
supply of water lines, waste pipes all complete.