Construction of Bhimsen Tower


Location: Sundhara, Kathmandu
BILL OF QUANTITIES

Rate
I/No. Description of Works Unit Quantity Amount (NRs.) Remarks
In Figure In Words
I CIVIL WORKS
1.00 DISMANTLING
Clearing the site of all the unuseful materials and dismantling
the existing steps for excavation and disposing other item as
1.01 job 1.00 5,000.00 5,000.00
per instruction of the site engineer all complete including layout
of buildings, roads and ancillary services.

Earthwork in excavation in trenches, foundation etc. in all kinds


of soft and medium soil including timbering and pumping out
1.02 water (if necessary) dressing of sides, ramming of bottom, lift up cu.m 5.12 512.36 2,620.86
to 3.5m, as per specification, drawings & instruction of site
engineer.

Backfill with associated Earth in 150mm layers in and


foundation including compaction with monkey rammer with
1.03 cu.m 2.56 381.67 976.17
compaction factor above 90% as per specification & instruction
of engineer.

Filling with one layer of flat brick soling in foundation over


1.04 compacted soil complete as per specifications, drawings and sq.m 9.66 925.36 8,935.28
instructions.
Sub Total (A) 17,532.32

2.00 CONCRETE WORKS


2.01 Lean Concrete
Providing, laying, compacting and curing plain cement concrete
M10 (1:3:6) in foundation with cement, sand and stone ballast
20mm gauge finishing to approved level, lines and dimensions cu.m 0.32 13,852.47 4,488.20
all complete as per drawings, specifications and instruction of
site engineer.
2.02 RCC Works
Providing, laying , compacting & curing reinforced cement
Concrete M20 (1 : 1.5 : 3) for footings, column and tie beam
with cement, sand & stone ballast 40 and/or 20mm down
cu.m 3.12 16,523.31 51,557.35
finishings to approved level, lines & dimensions with 28 days of
curing by potable water all complete as per drawings,
specifications & instructions of site engineer.
2.03 Formworks
Centering and shuttering with water proof plywood material for
all kinds of work including all necessary propping, scaffolding,
sq.m 22.86 987.36 22,567.10
staging, supporting etc. all complete as per drawing,
specification, and instruction of site engineer.
2.04 Reinforcement
Reinforcement work including straightening, cleaning, cutting,
bending, binding with 20 SWG annealed wire & fixing in
position as per drawing, bar bending schedule for raft
foundation column, beam, wall, stair, slab in all R.C.C. works as
per specification, drawing & instruction of site engineer.
TMT Bars (Fe 500) kg 232.82 121.36 28,254.69
Sub Total (B) 106,867.34

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
2 of 8

Construction of Bhimsen Tower


Location: Sundhara, Kathmandu
BILL OF QUANTITIES

Rate
I/No. Description of Works Unit Quantity Amount (NRs.) Remarks
In Figure In Words
II METAL WORKS
1.00 STEEL POST
Providing, making, fixing and welding of approved medium
quality ISMB200M of all types of metalworks of column framing
with applying two coat of anti corrosive lead oxide red primer
kg 3,154.68 154.36 486,956.40
coat over the metal surface after proper cleaning, grinding and
rubbing with sand paper as per specification, drawing &
instruction of site engineer.

2.00 STEEL BEAM


Providing, making, fixing and welding of approved medium
quality ISNB100M of all types of metalworks of beam framing
with applying two coat of anti corrosive lead oxide red primer
kg 2,533.74 154.36 391,108.11
coat over the metal surface after proper cleaning, grinding and
rubbing with sand paper as per specification, drawing &
instruction of site engineer.

3.00 BASE PLATE


Providing, making, fixing and welding of approved medium
quality 12mm base plate of all types of metalworks of
connecting column framing with applying two coat of anti
kg 203.47 186.34 37,914.97
corrosive lead oxide red primer coat over the metal surface after
proper cleaning, grinding and rubbing with sand paper as per
specification, drawing & instruction of site engineer.

4.00 ANCHOR BOLT


Providing, making, fixing and welding of approved medium
quality 12mm diameter anchor bolt of all types of metalworks of
connecting column framing with applying two coat of anti
kg 59.73 121.36 7,249.24
corrosive lead oxide red primer coat over the metal surface after
proper cleaning, grinding and rubbing with sand paper as per
specification, drawing & instruction of site engineer.

5.00 TOUGHENED GLASS


Providing and applying double glazing 6mm toughened glass
market
with laminated cover and silicon filing of 10mm thickness as per sq.m 453.25 2,000.00 906,500.00
study
specification, drawing & instruction of site engineer.

6.00 SPIDER FITTING CONNECTION


Providing and Fixing spider fitting glass connection as per market
nos 160.00 150.00 24,000.00
specification, drawing & instruction of site engineer. study
Sub Total (J) 1,853,728.72

Total Amount 1,978,000.00


VAT @ 13%= 257,140.00
GRAND TOTAL COST (INCLUDING VAT @ 13%)= 2,235,000.00

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
3 of 8

Construction of Bhimsen Tower


Quantity Estimate of Earthwork/Dismantling
Location: Sundhara, Kathmandu

Length Breadth Height Total


S.N Description of Works Nos Unit
(m) (m) (m) Quantity Remarks
A Earthwork
1.0 Footing 12 0.6 0.6 0.9 Cu.m 3.9
1 23.2 0.23 0.23 Cu.m 1.2
Cu.m 5.1
B Backfill 50% 2.6
Cu.m 2.6

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
4 of 8

Construction of Bhimsen Tower


Quantity Estimate of Concreting
Location: Sundhara, Kathmandu

Length Breadth Height Total


S.N Description of Works Nos Unit
(m) (m) (m) Quantity Remarks
1.0 Foundation
1.1 Footing 12 0.6 0.6 0.2 Cum 0.9

2.0 Column 12 0.35 0.35 0.7 Cum 1.0

3.0 Tie Beam 1.0 23.2 0.23 0.23 Cum 1.2


3.1
4.0 PCC Works
Footing 12 0.6 0.6 0.08 Cuft 0.3
0.3

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
5 of 8

Construction of Bhimsen Tower


Quantity Estimate of Brick Soling
Location: Sundhara, Kathmandu

Length Breadth Height Total


S.N Description of Works Nos Unit
(m) (m) (m) Quantity Remarks
1.0 Footing 12 0.6 0.6 Sqm 4.3
2.0 Tie Beam 1.0 23.2 0.2 Sqm 5.3
9.7

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
6 of 8

Construction of Bhimsen Tower


Quantity Estimate of Formwork
Location: Sundhara, Kathmandu

Length Breadth Height Total


S.N Description of Works Nos Unit
(m) (m) (m) Quantity Remarks
1.0 Footing 12 0.6 0.6 0.2 Sqm 5.8
2.0 Column 12 0.35 0.35 0.7 Sqm 11.8
3.0 Plinth Beam 1.0 23.2 0.23 Sqm 5.3
22.9

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
7 of 8

Construction of Bhimsen Tower


Quantity Estimate of Reinforcement Bar
Location: Sundhara, Kathmandu

Nos Length Total Diameter Unit Total


S.N Description of Works Nos Remarks
of str (m) length (m) (mm) weight Quantity

1.0 Column
1.1 Main bar 12.0 8.0 0.9 86.40 12.0 0.89 76.8
1.2 Stirrups 12.0 6.0 1.4 100.80 7.0 0.30 30.5

3.0 Tie Beam 1 4.00 23.2 92.8 12.0 0.89 82.5


Stirrups 1 155 0.9 142.3 7.0 0.30 43.0

232.8

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................
8 of 8

Construction of Bhimsen Tower


Quantity Estimate of Metal Works
Location: Sundhara, Kathmandu

Nos of Length Breadth Total Unit Quantity


S.N Description of Works Nos Unit Remarks
Sections (m) (ft) Quantity weight (kg)
1.00 Vertical Column post
ISMB200 4.00 1.00 10.35 41.40 Rm 25.40 1,051.56
4.00 1.00 10.35 41.40 Rm 25.40 1,051.56
4.00 1.00 10.35 41.40 Rm 25.40 1,051.56
3,154.68
2.00 Main Beam
ISNB100 4.00 1.00 23.20 92.80 Rm 12.10 1,122.88
1.00 1.00 15.20 15.20 Rm 12.10 183.92
1.00 1.00 7.80 7.80 Rm 12.10 94.38
12.00 1.00 7.80 93.60 Rm 12.10 1,132.56
2,533.74
3.00 12 ØAnchor Bolt 12.00 8.00 0.70 67.20 Rm 0.89 59.73

4.00 Base Plates


12mm base Plates 12.00 2.00 0.30 0.30 2.16 Sqm 94.20 203.47

5.00 6mm Double glazed toughened glass 1.00 1.00 24.50 10.90 Sqm 267.05
1.00 2.00 24.50 3.80 Sqm 186.20
453.25
6.00 Spider fitting to connect glass 1.00 160.00 Nos 160.00

........................... ........................... ...........................


Prepared by: Checked by: Approved by:
Er.Amok Bajracharya Er.Bikash Shrestha Mr./Mrs...........................