Professional Documents
Culture Documents
In Words-Twenty One Lakh Fifty Five Thousand Seven Hundred Seventeen and Oen
Paisa Only
Government of Nepal
National Disaster Risk Reduction and Management Authority
Project Implementation Unit
Singh Durbar, Kathmandu, Nepal.
1 Provisional Sum
Making fitting & fixing room number plates all complete work as per
b PS 1 LS 5,000.00
drawing, specification, and instruction of Engineer.
Providing and maintining site office of two rooms having total area 20
sq.m(approximately) for the use of client, consultant, contractor and
visitors during the entire period of construction including office 4 number
d of chair, 2 number of table, lockable file cabinet etc. as per the given Job 1 LS 100,000.00
drawing.The site ofice to be located near the entrance of the construction
area wherever possible.Payment shall be made in prorata basis over the
entire project duration.
Stripping off the existing cement plaster on the cement mortar masonry
wall and column, surface cleaning and disposing the debris in directed
b sq.m 220.41 86.94 19,162.45
place including cleaning the site, etc. all complete as per drawing details,
specification and instruction of site Engineer.
2 Demolition Works
Dismantling Floor of plain cement concrete, screeding and bedding
materials and disposing the debris in directed place including cleaning
a cu.m 5.18 3,220.00 16,669.14
the site etc. , all complete as per drawing, specification and instruction of
site Engineer.
3 Earthwork in excavation
Earthwork excavation (Manual excavation) in Gravel mixed soil in the
foundation including stacking the soil 1 m from the edge of the
a foundation and 30m hauling distance and 3m lift all complete as per cu.m 6.34 580.41 3,682.60
Specification and instruction by site engineer.
4 Brick Work
Providing and soiling with first class chimney made brick on flat in floor
a of building as per drawings, specification and instruction of the sq.m. 20.45 904.02 18,482.73
consultant/Engineer, all complete.
Providing and laying first class chimney fired brick one or more brick
thick wall (230mm thick or more) in cement mortar 1:6 in foundation up
to plinth and other specified places in all heights and level including the
b cu.m 1.33 14,501.73 9,140.19
cost of single or multi stage scaffolding, soaking bricks, curing, raking
joints, provision for recesses, openings, toothing etc., all complete as per
drawing, specifications and instructions of the Engineer.
5 Earthwork in Backfilling
6 Concrete Works
a P.C.C. (1:3:6) Works
Providing and laying machine mixed Plain Cement Concrete of nominal
mix 1:3:6, M10 grade for leveling course in foundations and under floor
of building, etc. in all level with broken stone aggregate of size not more
than 25 mm of approved quality including formwork wherever necessary, cu.m 0.65 11,357.06 7,390.13
dewatering, batching, mixing, transporting, placing, compacting, curing,
including all lead and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
b P.C.C. (1:2:4) Works
Providing and laying machine mixed Plain Cement Concrete of nominal
mix 1:2:4,M15 grade for leveling course in foundations and under floor
of building, etc. in all level with broken stone aggregate of size not more
than 25 mm of approved quality including formwork wherever necessary, cu.m 0.81 13,272.04 10,707.35
dewatering, batching, mixing, transporting, placing, compacting, curing,
including all lead and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
c P.C.C. for R.C.C. (1:1.5:3) Works -
d Microconcreting (1:1.5:3)
7 Reinforcement Works
Providing and fixing in position Fe 500 or other specified steel
reinforcement of various diameter confirming to relevant NBC and IS
code in R.C.C. works including straightening, cutting, bending, binding
with 20 SWG annealed wire for tying the reinforcement bars at each
a junctions (binding wire shall not be measured separately) including all kg 742.31 149.17 110,729.20
waste and cut pieces, provision for adequate numbers of spacers, chairs,
providing and placing cement mortar (1:1) cover blocks to keep the bars
in intended position at all levels all complete as per drawings,
specifications and instructions of the Engineer.
8 Formworks
Supplying and laying centering, shuttering of various pattern formworks
with 19mm thick water proof ply wood & steel adjustable props for all
kinds of RCC works, including nails, propping scaffolding, staging,
a supporting and bracing in proper lines and level, sealing the joints with sq.m 139.18 1,548.35 215,503.06
heavy duty brown self adhesive tape, aligning to line and levels.
Applying De-shuttering as approved by the Engineer etc., complete at all
levels as per drawing, specifications and instructions of the Engineer.
9 Plastering Works
12.50mm. Th. Cement sand plaster (1:4)work on building inner and outer
surfaces of good finish in perfect line level and plumb including grooving
a in plaster wherever shown in drawings including chiselling racking the sq.m 175.60 393.54 69,104.64
joints, wetting the surface and curing the work all complete as per
specification an.d construction of the consultant/engineer all complete
10 Drilling Works
Drilling for anchor in masonry wall for Splint and Band upto depth of
250mm, hole of diameter 10mm and filling the holes by cement slurry
a nos. 208.00 90.75 18,875.27
with 8mm dia bar all complete as per drawing,specification and
instruction of the Engineer.
Drilling the 10mm dia holes rotatory drill on concrete slab upto max
c 150mm and filling holes by epoxy grout as per instruction by site nos. 163.00 59.98 9,776.73
engineer.
11 Painting Works
a Exterior Weather Paint
50mm thick P.C.C. in (1:2:4) with cement punning (1:1) for flooring
work with approved floor hardener and water proofing (Dreitop FH,
Mapetop, Fairtop, Sika Chapdur or equivalent floor hardener) with
b sq.m 62.63 829.60 51,956.45
approved quality cement, sand & aggregate 12mm and down grade
including mixing,laying curing all complete work as per specification and
instruction of site engineer.
C Demolition Works
a Demolition of existing PCC floor
Ground Floor
Room 1 1.00 5.82 4.35 0.038 0.96 cu.m Thickness of floor=38mm
Room 2 1.00 6.12 4.35 0.038 1.01 cu.m
Roof 1.00 12.78 6.60 0.038 3.21
Total Demolition of existing PCC floor 5.18 cu.m
2 Earthwork
Earthwork in Excavation in ordinary to
mixed/hard soil in foundation including
dressing of sides and proper compaction to
A
trench bed, disposing of excess soil and filling
in tenches by proper compaction after
construction of structure
a For Splint
i Non corner (300mm) Depth of excavation 355mm
Inside 6.00 0.28 0.55 0.36 0.32 cu.m
Outside 21.00 0.28 0.55 0.36 1.13 cu.m
ii Corner A1
Inside 1.00 0.43 0.51 0.36 0.08 cu.m
Outside 1.00 0.28 1.54 0.36 0.15 cu.m
Corner C1 0.00
Inside 1.00 0.51 0.58 0.36 0.10 cu.m
Outside 1.00 0.28 0.79 0.36 0.08 cu.m
Corner C2 0.00
Inside 1.00 0.58 0.41 0.36 0.08 cu.m
Outside 1.00 0.28 0.69 0.36 0.07 cu.m
Corner A2 0.00
Inside 1.00 0.46 0.43 0.36 0.07 cu.m
Outside 1.00 0.28 1.99 0.36 0.19 cu.m
Crosswall intersection B1 0.00
Inside 1 1.00 0.66 0.43 0.36 0.10 cu.m
Inside 2 1.00 0.89 0.43 0.36 0.13 cu.m
Crosswall intersection B2 0.00
Inside 1 1.00 0.66 0.43 0.36 0.10 cu.m
Inside 2 1.00 0.43 0.43 0.36 0.06 cu.m
Inner Splint of width 914mm 6.00 0.28 1.16 0.36 0.68 cu.m
Inner Splint of width 864mm 1.00 0.28 1.11 0.36 0.11 cu.m
Inner Splint of width 940mm 1.00 0.28 1.19 0.36 0.12 cu.m
Total earthwork in excavation 3.57 cu.m
3 Brick soling in one layer
a For Splint
i Non corner (300mm) Depth of excavation 355mm
Inside 6.00 0.28 0.55 0.91 sq.m. Width=Width of Splint+2*50mm+2*75mm
Outside 21.00 0.28 0.25 1.44 sq.m.
ii Corner A1 0.00
Inside 1.00 0.43 0.51 0.21 sq.m.
Outside 1.00 0.28 0.25 0.07 sq.m.
Corner C1 0.00
Inside 1.00 0.51 0.58 0.29 sq.m.
Outside 1.00 0.28 0.79 0.22 sq.m.
Corner C2 0.00
Inside 1.00 0.58 0.41 0.23 sq.m.
Outside 1.00 0.28 0.69 0.19 sq.m.
Corner A2 0.00
Inside 1.00 0.46 0.43 0.19 sq.m.
Outside 1.00 0.28 1.99 0.55 sq.m.
Crosswall intersection B1 0.00
Inside 1 1.00 0.66 0.43 0.28 sq.m.
Inside 2 1.00 0.89 0.43 0.38 sq.m.
Crosswall intersection B2 0.00
Inside 1 1.00 0.66 0.43 0.28 sq.m.
Inside 2 1.00 0.43 0.43 0.18 sq.m.
Inner Splint of width 914mm 6.00 0.28 0.25 0.41 sq.m.
Inner Splint of width 864mm 1.00 0.28 0.68 0.19 sq.m.
Inner Splint of width 940mm 1.00 0.28 0.68 0.19 sq.m.
Total brick soling 6.20 sq.m.
4 Earthback Filling
Filling Upto Ground Level 1.00 As per excavation 3.57 3.57 cu.m
Deduction for soling -1.00 0.34 -0.34 cu.m
Deduction of PCC -1.00 1.17 -1.17 cu.m
Total earthwork in backfilling 2.06 cu.m
5 Concreting Work
a For Splint
i Non corner (300mm)
Inside 6.00 0.05 0.30 2.97 0.27 cu.m
Outside 21.00 0.05 0.30 3.54 1.12 cu.m H=2.97+0.572
ii Corner A1 0.00 0.00
Inside 1.00 0.05 0.58 2.97 0.09 cu.m
Outside 1.00 0.05 1.39 3.54 0.25 cu.m
Corner C1 0.00 0.00
Inside 1.00 0.05 0.73 2.97 0.11 cu.m B=2*0.175
Outside 1.00 0.05 0.76 3.54 0.13 cu.m
Corner C2 0.00 0.00
Inside 1.00 0.05 0.63 2.97 0.09 cu.m
Outside 1.00 0.05 0.66 3.54 0.12 cu.m
Corner A2 0.00 0.00
Inside 1.00 0.05 0.53 2.97 0.08 cu.m
Outside 1.00 0.05 0.71 3.54 0.13 cu.m
Crosswall intersection B1 0.00 0.00
Inside 1 1.00 0.05 0.73 2.97 0.11 cu.m
Inside 2 1.00 0.05 1.16 2.97 0.17 cu.m
Crosswall intersection B2 0.00 0.00
Inside 1 1.00 0.05 0.73 2.97 0.11 cu.m
Inside 2 1.00 0.05 0.50 2.97 0.07 cu.m
Inner Splint of width 914mm 6.00 0.05 0.91 2.97 0.81 cu.m
Inner Splint of width 864mm 1.00 0.05 0.86 2.97 0.13 cu.m
Inner Splint of width 940mm 1.00 0.05 0.94 2.97 0.14 cu.m
b For Band 0.00 0.00
Outer 0.00 0.00
At Sill level 1.00 35.35 0.30 0.05 0.53 cu.m L=2(12.773+4.902)
At Lintel level 0.00 0.00
For East, North, South face 1.00 30.45 0.30 0.05 0.46 cu.m
For West face 1.00 4.90 0.87 0.05 0.21 cu.m
Inner 0.00 0.00
Room1 2.00 20.32 0.30 0.05 0.61 cu.m L=2(5.817+4.343)
Room2 2.00 20.93 0.30 0.05 0.63 cu.m L=2(6.121+4.343)
Sub-Total micro-concreting of 50 mm thickness for Splint and Band 6.36 cu. m
B Providing, mixing and laying RCC in
1:1.5:3 (M20) for footing
Just below Splint
a For Splint
i Non corner (300mm)
Inside 6.00 0.20 0.40 0.20 0.10 cu.m
Outside 21.00 0.20 0.40 0.20 0.34 cu.m Width of footing=Width of splint+0.05*2
ii Corner A1 0.00
Inside 1.00 0.20 0.68 0.20 0.03 cu.m
Outside 1.00 0.20 1.49 0.20 0.06 cu.m
Corner C1 0.00
Inside 1.00 0.20 0.83 0.20 0.03 cu.m
Outside 1.00 0.20 0.86 0.20 0.03 cu.m
Corner C2 0.00
Inside 1.00 0.20 0.73 0.20 0.03 cu.m
Outside 1.00 0.20 0.76 0.20 0.03 cu.m
Corner A2 0.00
Inside 1.00 0.20 0.63 0.20 0.03 cu.m
Outside 1.00 0.20 0.81 0.20 0.03 cu.m
Crosswall intersection B1 0.00
Inside 1 1.00 0.20 0.83 0.20 0.03 cu.m
Inside 2 1.00 0.20 1.26 0.20 0.05 cu.m
Crosswall intersection B2 0.00
Inside 1 1.00 0.20 0.83 0.20 0.03 cu.m
Inside 2 1.00 0.20 0.60 0.20 0.02 cu.m
Inner Splint of width 914mm 6.00 0.20 1.01 0.20 0.24 cu.m
Inner Splint of width 864mm 1.00 0.20 0.96 0.20 0.04 cu.m
Inner Splint of width 940mm 1.00 0.20 1.04 0.20 0.04 cu.m
Sub-Total M20 grade (1:1.5:3) concreting 1.17 cu. m
Total Microconcreting 7.52 cu.m
6 Reinforcement
A Reinforcement Bar
a For Splint
i Non corner (300mm)
Inside (6*3bars) 18.00 3.61 8.00 0.39 25.64 kg
Outside (21*3bars) 63.00 4.18 8.00 0.39 103.93 kg
ii Corner A1 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Outside (1*5bars) 5.00 4.18 8.00 0.39 8.25 kg
Corner C1 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Outside (1*4bars) 4.00 4.18 8.00 0.39 6.60 kg
Corner C2 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Outside (1*4bars) 4.00 4.18 8.00 0.39 6.60 kg
Corner A2 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Outside (1*5bars) 5.00 4.18 8.00 0.39 8.25 kg
Crosswall intersection B1 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Crosswall intersection B2 0.00
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Inside (1*3 bars) 3.00 3.61 8.00 0.39 4.27 kg
Inner Splint of width 914mm (6*5bars) 30.00 3.61 8.00 0.39 42.74 kg
Inner Splint of width 864mm (1*5bars) 5.00 3.61 8.00 0.39 7.12 kg
Inner Splint of width 940mm (1*5bars) 5.00 3.61 8.00 0.39 7.12 kg
b For Band 0.00
Outer 0.00
At Sill level 1.00 36.15 8.00 0.39 14.27 kg
At Lintel level 8.00 0.39 0.00
For East, North, South face 1.00 31.25 8.00 0.39 12.33 kg
For West face 1.00 5.70 8.00 0.39 2.25 kg
Inner 0.00
Room1 2.00 21.92 8.00 0.39 17.30 kg
Room2 2.00 22.53 8.00 0.39 17.78 kg
Sub-Total Reinforcement Bar of 8mm dia for Splint and Band 314.37 kg
c For Tie Beam
a For Splint
i Non corner (300mm)
Inside 24.00 0.64 10.00 0.62 9.47 kg
Outside 84.00 0.64 10.00 0.62 33.15 kg
ii Corner A1 0.00
Inside 4.00 1.02 10.00 0.62 2.52 kg
Outside 4.00 1.63 10.00 0.62 4.02 kg
Corner C1 0.00
Inside 4.00 1.17 10.00 0.62 2.89 kg
Outside 4.00 1.00 10.00 0.62 2.47 kg
Corner C2 0.00
Inside 4.00 1.07 10.00 0.62 2.64 kg
Outside 4.00 0.90 10.00 0.62 2.22 kg
Corner A2 0.00
Inside 4.00 0.97 10.00 0.62 2.39 kg
Outside 4.00 0.95 10.00 0.62 2.34 kg
Crosswall intersection B1 0.00
Inside 1 4.00 1.17 10.00 0.62 2.89 kg
Inside 2 4.00 1.40 10.00 0.62 3.46 kg
Crosswall intersection B2 0.00
Inside 1 4.00 1.17 10.00 0.62 2.89 kg
Inside 2 4.00 0.94 10.00 0.62 2.32 kg
Inner Splint of width 914mm 24.00 1.25 10.00 0.62 18.56 kg
Inner Splint of width 864mm 4.00 1.20 10.00 0.62 2.97 kg
Inner Splint of width 940mm 4.00 1.28 10.00 0.62 3.16 kg
Sub-Total Reinforcement Bar of 10mm dia for Tie Beam 100.35 kg
B Links
a For Splint
i Non corner (300mm)
Inside 180.00 0.41 4.75 0.14 10.27 kg
Outside 756.00 0.41 4.75 0.14 43.12 kg
ii Corner A1 0.00 0.00
Inside 30.00 0.79 4.75 0.14 3.30 kg
Outside 36.00 1.40 4.75 0.14 7.01 kg
Corner C1 0.00 0.00
Inside 30.00 0.94 4.75 0.14 3.93 kg
Outside 36.00 0.77 4.75 0.14 3.86 kg
Corner C2 0.00 0.00
Inside 30.00 0.84 4.75 0.14 3.50 kg
Outside 36.00 0.67 4.75 0.14 3.35 kg
Corner A2 0.00 0.00
Inside 30.00 0.74 4.75 0.14 3.09 kg
Outside 36.00 0.72 4.75 0.14 3.61 kg
Crosswall intersection B1 0.00 0.00
Inside 1 30.00 0.94 4.75 0.14 3.94 kg
Inside 2 30.00 1.17 4.75 0.14 4.89 kg
Crosswall intersection B2 0.00 0.00
Inside 1 30.00 0.94 4.75 0.14 3.94 kg
Inside 2 30.00 0.71 4.75 0.14 2.96 kg
Inner Splint of width 914mm 180.00 1.02 4.75 0.14 25.64 kg
Inner Splint of width 864mm 30.00 0.97 4.75 0.14 4.07 kg
Inner Splint of width 940mm 30.00 1.05 4.75 0.14 4.38 kg
b For Band 0.00
Outer 0.00
At Sill level 354.00 0.41 4.75 0.14 20.19 kg
At Lintel level 0.00 0.00 0.00
For East, North, South face 305.00 0.41 4.75 0.14 17.40 kg
For West face 50.00 0.98 4.75 0.14 6.78 kg
Inner 0.00 0.00
Room1 408.00 0.41 4.75 0.14 23.27 kg
Room2 420.00 0.41 4.75 0.14 23.96 kg
Sub-Total Stirrups of 4.75mm dia for Splint and Band 226.45 kg
c For Tie Beam
a For Splint
i Non corner (300mm)
Inside 18.00 0.79 8.00 0.39 5.61 kg
Outside 63.00 0.79 8.00 0.39 19.64 kg
ii Corner A1 0.00
Inside 5.00 0.79 8.00 0.39 1.56 kg
Outside 10.00 0.79 8.00 0.39 3.12 kg
Corner C1 0.00
Inside 6.00 0.79 8.00 0.39 1.87 kg
Outside 6.00 0.79 8.00 0.39 1.87 kg
Corner C2 0.00
Inside 5.00 0.79 8.00 0.39 1.56 kg
Outside 6.00 0.79 8.00 0.39 1.87 kg
Corner A2 0.00
Inside 5.00 0.79 8.00 0.39 1.56 kg
Outside 6.00 0.79 8.00 0.39 1.87 kg
Crosswall intersection B1 0.00
Inside 1 6.00 0.79 8.00 0.39 1.87 kg
Inside 2 9.00 0.79 8.00 0.39 2.81 kg
Crosswall intersection B2 0.00
Inside 1 6.00 0.79 8.00 0.39 1.87 kg
Inside 2 4.00 0.79 8.00 0.39 1.25 kg
Inner Splint of width 914mm 42.00 0.79 8.00 0.39 13.09 kg
Inner Splint of width 864mm 7.00 0.79 8.00 0.39 2.18 kg
Inner Splint of width 940mm 7.00 0.79 8.00 0.39 2.18 kg
Sub-Total Stirrups of 8mm dia for Tie Beam 65.78 kg
Electrical Works
a Wiring of whole building 1.00 350.00 350.00 r.m
b Electrical Bulbs 12.00 12.00 nos.
Fixing loose objects like tall cabinets, fan,
c 1.00 1.00 Job
computer etc
d Fire Extinguisher 1.00 1.00 nos
e Earthing System 1.00 1.00 set
Government of Nepal
National Disaster Risk Reduction and Management Authority
Project Implementation Unit
Singh Durbar, Kathmandu, Nepal.
1 Concrete Test
cubes or cylinder
a 3.00 Nos 150.00 450.00
crushing
2 Brick Test
a Brick Crossing Test 3.00 Nos 100.00 300.00
b Water Absortion Test 3.00 Nos 100.00 300.00
c Brick Test 3.00 Nos 1400.00 4,200.00
3 Aggregate Test
Aggregate Crushing
a 3.00 Nos 489.00 1,467.00
Value Test
Aggregate Impact
b 3.00 Nos 350.00 1,050.00
Value
4 Sieve Analysis
a Sieve Analysis (Wet) 3.00 Nos 844.00 2,532.00
b Sieve Analysis (Dry) 3.00 Nos 450.00 1,350.00
U.T.M. Tensile
5 Nos
Strength Test
a 4.75mm 3.00 Nos
a 8mm Ø 3.00 Nos 1200.00 3,600.00
b 10mm Ø 3.00 Nos 1200.00 3,600.00
c 12mm Ø 3.00 Nos 1200.00 3,600.00
6 Cement Test
Cement mortar cube
a 3.00 Nos 450.00 1,350.00
Crushing 3 Nos.
Intial setting & Final
b 3.00 Nos 500.00 1,500.00
Setting
25,299.00
Provisional sum (Insurance premium as per contract,Lab Test charge for paymnet towards the test,Confirmatory Soil test atleast at three locations around
1.2.1 building complex as per instruction of Engineer,Performance Bond Commision,As built Drawing,Environment enhancement (Including plantation of PS Err:509
trees/Hedges,maintaining greenary within school compound) and others.
Barricating the construction area to maintain construction site safe and also constructing toilet and camp for labour during entire construction period as
1.2.2 Job 20000.00
per site condition and as per instruction of Engineer.
Making fitting & fixing project information and social/safeguard information board of approximately 4'x6' size written in plain sheet in tubular pipe frame
1.2.3 No. 18000.00
all complete as per drawing, specification and instruction of Engineer.
1.2.4 Making fitting & fixing classroom name plate all complete work as per drawing,specification and instruction of Engineer. No. 150.00
Health and Safety-Helmets,Gloves,Boot,Safety glasses/face shields,earplugs/ear muffs,First Aid tools,etc as required bythe contract clause and techical
1.2.5 specification,the number of safety materials personel protection equipment(PPE) shall be minimum but not limited to 40 sets during construction LS 150000.00
period.Payment shall be made in prorata basis over the entire project duration.
Providing and fixing the green saftey net around the building with MS scaffolding (that need not to removed during construction) including removing it
1.2.6 Sq.m 150.00
after completion of the work and cleaning thoroughly all complete as original condition or as per instruction by the site Engineer.
Providing and fixing the 500 gauge thick polythene sheet with adhesive tape and nail for protection of existing door/ window (that need not to removed
1.2.7 during construction) including frame, shutters, security film and its all fixtures by covering, including removing it after completion of the work and Sq.m 465.18
cleaning thoroughly all complete as original condition or as per instruction by the site Engineer.
2 DEMOLITION WORK
Dismantling of exising building by appropriate method safely and cleaning and transporting of all the construciton debris to a specified location as per
drawing and instruction of the Engineer. Note : No extra payment of cleaning and transporting shall be paid to the contractor.
Demolition of the existing brick masonry wall in cement/bajra/surkhi mortar and disposing the debris in directed place including cleaning the site, etc. all
2.1 Cu.m 1706.60
complete as per drawing details, specification and instruction of site Engineer.
Stripping off the existing cement plaster on the cement mortar masonry wall, raking out the cement mortar to a depth of 10 mm at joint, surface cleaning
2.2 and disposing the debris in directed place including cleaning the site, etc. all complete as per drawing details, specification and instruction of site Sq.m 86.94
Engineer.
Dismantling Floor of plain cement concrete, screeding and bedding materials and disposing the debris in directed place including cleaning the site etc. ,
2.3 Cu.m 3220.00
all complete as per drawing, specification and instruction of site Engineer.
Dismantling RCC and disposing the debris in directed place including cleaning the site etc. , all complete as per drawing, specification and instruction of
2.4 Cu.m 8855.00
site Engineer.
Removing Floor of single layer flat brick soling including bedding materials of cement/sand/mud mortar and stacking the brick including disposing the
2.5 Sq.m 66.33
debris in directed place including cleaning the site, etc. all complete as per drawing,specification and approval of site Engineer.
Excavation in foundations in all type of soils for foundation, trenches, footing, pits etc. to the required depth including dewatering by manual or
mechanical means etc. as per specifications with all contractor’s own machinery and equipment's, providing crossing of track, shoring, strutting,
timbering and buttressing with appropriate materials and all such measures necessary to retain in position the sides of the foundation pit and including Cu.m 580.41
refilling the excavated material with watering, ramming, leveling the site and disposing off the surplus/unusable earth within 50m all complete as per
drawings, specifications and instructions of the Engineer.
Back filling in foundation and sides of foundation with approved soil obtained from the excavation at site and stacked at site or brought from outside in
5.1 layer not exceeding 30 cm thick (compacted thickness) including transportation of soil, spreading in required line and level, sprinkling water, ramming, Cu.m 404.28
compacting with mechanical rammers, testing, etc., all complete as per drawing, specification and instructions of the Engineer.
Disposing of excess excavated soil and debris coming out from the demolition of PCC, RCC, Masonry and plaster, etc out of school premises by 3 T
5.2 Cu.m 582.82
capacity truck upto haulage distance of 6 Km as per instruction of site engineer.
6.0 BRICK SOLING
Providing and soiling with first class chimney made brick on flat in floor of building as per drawings, specification and instruction of the
6.1 Sq.m 904.02
consultant/Engineer, all complete.
Providing and laying first class chimney fired brick one or more brick thick wall (230mm thick or more) in cement mortar 1:6 (1 cement : 6 coarse sand)
in foundation up to plinth and other specified places in all heights and level including the cost of single or multi stage scaffolding, soaking bricks, curing, Cu.m 14501.73
raking joints, provision for recesses, openings, toothing etc., all complete as per drawing, specifications and instructions of the Engineer.
Providing and laying first class local chimney made brick one or more brick thick wall (230mm thick or more) in cement mortar 1:4 (1 cement : 4 coarse
sand) in superstructure in all heights and level including the cost of single or multi stage self standing scaffolding, soaking bricks, curing, raking joints, Cu.m 15505.45
provision for recesses, openings, toothing etc., all complete as per drawing, specifications and instructions of the Engineer.
Providing and laying machine mixed Plain Cement Concrete of nominal mix 1:3:6, (1 cement : 3 sand : 6 coarse aggregate ) M10 grade for leveling
course in foundations and under floor of building, etc. in all level with broken stone aggregate of size not more than 25 mm of approved quality including
Cu.m 11357.06
formwork wherever necessary, dewatering, batching, mixing, transporting, placing, compacting, curing, including all lead and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
Providing and laying machine mixed Plain Cement Concrete of nominal mix 1:2:4, (1 cement : 2 sand : 4 coarse aggregate ) M15 grade for leveling
course in foundations and under floor of building, etc. in all level with broken stone aggregate of size not more than 25 mm of approved quality including
Cu.m 13272.04
formwork wherever necessary, dewatering, batching, mixing, transporting, placing, compacting, curing, including all lead and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
Providing and laying in position machine mixed and machine vibrated cement concrete of mix 1:1.5:3 (1 cement:1.5 sand: 3 coarse aggreagate) M20
grade for reinforced cement concrete work using approved cement with 20 mm graded machine crushed stone aggregate of approved quality in various
locations and heights including transportation of concrete to site of placing, compaction, finished to required line and level, protection and curing, etc. all Cu.m 15591.24
complete as per drawings, specifications and the instructions of the Engineer, but excluding the cost of centering, shuttering, and reinforcement all
complete as per drawings, specifications and instructions of the Engineer.
Providing and laying in position cement concrete of mix 1:1.5:3 (1 cement:1.5 sand: 3 coarse aggreagate) M20 grade for microconcreting work using
approved cement with 10 mm graded machine crushed stone aggregate of approved quality in various locations and heights including transportation of
8.4.2 concrete to site of placing, compaction, finished to required line and level, protection and curing, etc. all complete as per drawings, specifications and the Cu.m 17142.48
instructions of the Engineer, but excluding the cost of centering, shuttering, and reinforcement all complete as per drawings, specifications and
instructions of the Engineer.
Supplying and laying centering, shuttering of various pattern formworks with 19mm thick water proof ply wood & steel adjustable props for all kinds of
RCC works for foundations, columns, shear walls, beams, slab, staircase, lintel, sill, pergola, including nails, propping scaffolding, staging, supporting
and bracing in proper lines and level, sealing the joints with heavy duty brown self adhesive tape, aligning to line and levels including Ties, PVC Spacer, Sq.m 1548.35
Providing openings/ cutouts/ pockets, applying De-shuttering chemical, De-shuttering as approved by the Engineer etc., complete at all levels as per
drawing, specifications and instructions of the Engineer.
Providing and fixing in position Fe 500 steel reinforcement of various diameter confirming to relevant IS code in R.C.C. works including straightening,
cutting, bending, binding with 20 SWG annealed wire for tying the reinforcement bars at each junctions (binding wire shall not be measured separately)
including all waste and cut pieces, provision for adequate numbers of spacers, chairs, providing and placing cement mortar (1:1) cover blocks to keep the Kg 149.17
bars in intended position at all levels all complete as per drawings, specifications and instructions of the Engineer. (Authorized lap length and for the bar
length exceeding 10 meter in length shall be measured for the payment).
50mm thick P.C.C. in (1:2:4) with cement punning (1:1) for flooring work with approved floor hardener and water proffing (Dreitop
11.2 FH,Mapetop,Fairtop,Sika Chapdur or equivalent floor hardener) with approved quality cement, sand & aggregate 12mm and down grade including Sq.m 829.60
mixing,laying curing all complete work as per specification
Providing and laying of 3mm thick cement and sand punning in 1:1 cement sand ratio on floors, skirting, dado etc. including claening , watering in
11.3 Sq.m 302.57
surface and rubbing with steel trowel for hard and smooth syrface and curing all complete as per drawing, specification and instructions of the Engineer.
12.50mm. Th. Cement sand plaster (1:4)work on building inner and outer surfaces of good finish in perfect line level and plumb including grooving in
12.2 plaster wherever shown in drawings including chiselling racking the joints, wetting the surface and curing the work all complete as per specification an.d Sq.m 393.54
construction of the consultant/engineer all complete
3/4X1.5" thick pani patti in cement sand mortar(1:3) in cantiliver portion of slab in perfect line and level racking the joints, wetting the surface and
12.4 Rm 182.77
curing the work all complete as per specification and instruction of the consultant/engineer all complete
12.5 CEMENT SKIRTING
Providing, laying and curing 100 mm height and 18 mm thick Cement Plaster Skirting with C.M. 1:3 (1 Cement :3 Coarse sand), on perfect line & level,
finished with a floating coat of neat cement including rounding of junctions and slanted finish at top in 45 degree, as per design, specification and Rm 68.27
instruction of the Engineer, all complete.
13 DOORS AND WINDOWS
13.1 DOOR FRAME
Providing and fixing in position wooden frames in doors and wondows of specified section (75*100 mm) of seasoned salwood assembled with wooden
nails including cost of hold fast, screws etc and applying two coats of bitumen paint to the surface contacting to walls or other works etc all complete as Cu.m 395213.60
per drawings, specification and instruction of the Engineer.
Making, fitting & fixing 38mm thick sal wood pannelled door/window shutter in existing frame including all necessary approved quality of hardware
13.2 Sq.m 19549.46
fittings all complete as per drawings, specification and instruction of the Engineer.
Fitting anf fixing of glazed shutter in 38x75mm thick salwood frame with 5mm thick plain glass fitting including all necessary hardware fittings all
13.3 Sq.m 13779.06
complete as per drawings, specification and instruction of the Engineer.
14 PAINT WORKS
14.1 DISTEMPER PAINT
Providing and applying two or more coats of washable distemper paint of approved manufacturer and shade over a coat of alkali resistant cement primer
of approved manufacturer as per manufacturer's specifications to the surface of wall, ceiling, beams columns, canopies, staircase, lobbies etc., all
Sq.m 191.41
complete as per drawings, specifications and instruction. The rates shall include for scraping, washing the surface with water, surface preparation,
scaffolding etc., all complete as per the manufacturer's recommendations and as approved by the Engineer.
Staircase railing work with 50mm stainless steel pipe hand railing with 50mm stainless steel pipe vertical post at 2m
15.1 spacing and three 25mm stainless steel pipe between hand rail and ground on height 750 to 900 mm as per design drawing r.m. 5094.50
& specification & instructon site incharge.
15.2 Supplying,fitting and fixing Stainless Steel plates for parapet railing work as per drawing, specification and instruction of the engineer . Kg 364.32
15.3 Supplying,fitting and fixing anchor bolts for parapet railing work as per drawing, specification and instruction of the engineer . Kg 226.49
16 MISCELLANEOUS WORK
Drilling for anchor in masonry wall upto depth of 350mm,hole of diameter 10mm @450mmc/c staggered and filling the holes by cement slurry with 8mm
16.1 No 90.75
dia bar all complete as per drawing,specification and instruction of the Engineer.
Drilling for anchor in masonry wall upto depth of 230mm,hole of diameter 10mm @450mmc/c staggered and filling the holes by cement slurry with 8mm
16.2 No 97.78
dia bar all complete as per drawing,specification and instruction of the Engineer.
Drilling for anchor in masonry wall upto depth of 120mm,hole of diameter 14mm @150mmc/c staggered and filling the holes by cement slurry with
16.3 No 93.09
12mm dia bar all complete as per drawing,specification and instruction of the Engineer.
16.4 Drilling the 10mm dia holes rotatory drill on concrete surface upto max 125mm and filling holes by epoxy grout as per instruction by site engineer. No 59.98
16.5 Drilling the 12mm dia holes rotatory drill on concrete surface upto max 125mm and filling holes by epoxy grout as per instruction by site engineer. No 81.12
16.6 Drilling the 14mm dia holes rotatory drill on concrete surface upto max 125mm and filling holes by epoxy grout as per instruction by site engineer. No 128.93
16.7 Drilling the 18mm dia holes rotatory drill on concrete surface upto max 125mm and filling holes by epoxy grout as per instruction by site engineer. No 155.47
Drilling for anchor in masonry wall upto depth of 125mm,hole of diameter 14mm @450mmc/c staggered and filling the holes by epoxy grout with 12 dia
16.8 No 215.85
bar all complete as per drawing,specification and instruction of the Engineer.
Chipping of unsound / weak concrete material from slabs, beams, columns, etc. with manual chisel and / or by standard power driven percussion type or
of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement
16.9 Sqm 179.10
with wire brushes etc. and disposal of debris up-to a distance of 10m all complete as per direction of site-in-charge. (25mm average thickness for cover
removal)
22 Providing and laying 0.5 mm thick Coloured CGI sheet sq.m 1777.04
Site clearance work before starting the work and after completion of work including disposing of unused materials away from site and proper levelling
24 LS 10000.00
all complete as per instruction of site technician.
Total
Name of Facility:Shree Mahadev Janata Namunaa Ma. Vi. and Hariwan Health Post and Shree Jana Jagriti Ma. Vi. Location: Hariwan-8, Sarlahi
Distances (km)
Weight/unit
S.No Materials Unit Unit Rate Market / Source Earthen
(kg) Metalled
(Average)
1 Cement bag 50.00 875.00 Sarlahi 0.0 0.0
2 Reinforcement kg 1.00 102.00 Sarlahi 0.0 0.0
3 Wall Putty kg 1.00 150.00 Sarlahi 0.0 0.0
4 Enamel Paint liter 1.30 715.00 Sarlahi 0.0 0.0
5 Apex Paint/Weather coat liter 1.30 1285.00 Sarlahi 0.0 0.0
6 Emulsion Paint liter 1.30 850.00 Sarlahi 0.0 0.0
l, Prakash NS equivalent
Unit Rate/unit cost
nos 1,000.00 750.00
nos 900.00 1,170.00
nos 700.00 1,050.00
Rm 72.10 7,210.00
Ls 18.00 1,800.00
Actual rate 11,980.00
15% conctractor overhead 1,797.00
13,777.00
versafe or equivalent
Unit Rate/unit cost
nos 1,000.00 1,000.00
nos 7,130.00 7,130.00
Actual rate 8,130.00
15% contractor over 1,219.50
Total (Rs.) 9,349.50
9940.00 9940.00
15.00 270.00
263.00 263.00
15.00 15.00
12.00 480.00
322.00 1288.00
645.00 645.00
377.00 377.00
13278.00
1000.00 200.00
900.00 1350.00
700.00 3500.00
5050.00
18328.00
18328.00
2749.2
21077.20 /job
Civil Rate Analysis
F/Y: 2079/080 District: Sarlahi
Labour rate
Skilled labour 1000.00
Unskilled Labour 700.00
1 Site Clearance and grass cutting, root digging, breaking sods, clearing ground and carrying away from site Unit: 1 m2
A Labour
Unskilled MD 0.023 700.00 16.10
B Material
Nil
C Equipment
D Subtotal (A+B+C) 16.10
E Contractor's Overhead@ 15% of (D) 2.42
Total(D+E) 18.52
Rate per 1 m2 18.52
Scrapping of weak mortared plaster that can't be removed easily by hand tools and needs additional hammering ,raking the joint upto 10mm,surface
2 clening disposing the debris Unit: 100m2
A Labour
Unskilled MD 0.70 700.00 490.00
B Material
Nil
C Equipment
@ 3% of (A) LS 1.00 14.70
D Subtotal (A+B+C) 504.70
E Contractor's Overhead@ 15% of (D) 75.70
Total(D+E) 580.41
Rate per 1 m3 580.41
3 Earthwork excavation in all type of soil using hydraulic excavation (capacity 0.8 m3) all complete as per instruction by site engineer. Unit: 1 m3
A Labour
Unskilled MD 700.00
B Material
Diesel Lt 0.125 90.00 11.25
C Equipment
Hydraulic Excavator m3 0.0104 1800.00 18.72
D Subtotal (A+B+C) 29.97
E Contractor's Overhead@ 15% of (D) 4.50
Total(D+E) 34.47
Rate per 1 m3 34.47
4 Earthwork in filling by laying 15-15 cm layer soil with spraying water and compacted by labour Unit: 1 m3
A Labour
Unskilled MD 0.50 700.00 350.00
B Material
water ltr 5.00 0.31 1.55
C Equipment
D Subtotal (A+B+C) 351.55
E Contractor's Overhead@ 15% of (D) 52.73
Total(D+E) 404.28
Rate per 1 m3 404.28
6 Dry stone soling with sand foundation/floor including sand filling in joint levelling ramming to level including sand filling joints. Unit: 1 m3
A Labour
Skilled MD 0.00 1000.00 0.00
Unskilled MD 1.50 700.00 1050.00
B Material
Stone m3 1.00 2300.00 2300.00
River Sand m3 0.20 1100.00 220.00
C Equipment
Nil
D Subtotal (A+B+C) 3570.00
E Contractor's Overhead@ 15% of (D) 535.50
Total(D+E) 4105.50
Rate per 1 m3 4105.50
8 Supplying and laying 500micron tear proof good quality polythene above the compacted boulder stone. Unit: 10 m2
A Labour
Skilled MD 0.60 1000.00 600.00
Unskilled MD 0.60 700.00 420.00
B Material
500 Micron Polythene Sheet m2 11.00 275.00 3025.00
C Subtotal (A+B) 4045.00
D Contractor's Overhead @ 15% of (C) 606.75
= Total (C+D) 4651.75
Rate per m2 465.18
First class local chimney made Brickwork in 1:6 C/S mortar on ground floor in perfect line level finished including wetting the bricks,racking the joints
9 Unit:1m3
and curing the work for at least 7 days all complete.
A Labour
Skilled MD 1.50 1000.00 1500.00
Unskilled MD 2.20 700.00 1540.00
Unskilled MD 0.20 700.00 140.00
B Material
Cement MT 0.07 17500.00 1225.00
Sand m3 0.30 1100.00 330.00
Brick Nos 560.00 14.00 7840.00
water ltr 100.00 0.31 31.00
C Equipment
3% of A LS 1.00 4.20
D Subtotal (A+B+C) 12610.20
E Contractor's Overhead @15% of (D) 1891.53
Total(D+E) 14501.73
First class local chimney made Brickwork in 1:4 C/S mortar above ground floor in perfect line level finished including wetting the bricks,racking the
10 Unit:1m3
joints and curing the work for at least 7 days all complete.
A Labour
Skilled MD 1.50 1000.00 1500.00
Unskilled MD 2.20 700.00 1540.00
Unskilled MD 0.70 700.00 490.00
B Material
Cement MT 0.10 17500.00 1750.00
Sand m3 0.28 1100.00 308.00
Brick Nos 560.00 14.00 7840.00
water ltr 130.00 0.31 40.30
C Equipment
3% of A LS 1.00 14.70
D Subtotal (A+B+C) 13483.00
E Contractor's Overhead @15% of (D) 2022.45
Total(D+E) 15505.45
Rate per 1 m3 15505.45
11 110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ). (per 10 sq.m.) Unit:10 m2
A Labour
Skilled MD 1.90 1000.00 1900.00
Unskilled MD 2.60 700.00 1820.00
B Material
Cement MT 0.11 17500.00 1925.00
Sand m3 0.30 1100.00 330.00
Brick Nos 673.00 14.00 9422.00
Water ltr 100.00 0.31 31.00
C Equipment
3% of A LS 1.00 54.60
D Subtotal (A+B+C) 15482.60
E Contractor's Overhead @15% of (D) 2322.39
Total(D+E) 17804.99
Rate per 1 m2 1780.50
12 Providing and Laying Rubble masonry works including supply of hard stone blocks, preparing cement mortar (1:6) and construction of wall upto 5 m Unit:1m3
high (Haulage distance up to 10 m)
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 1.50 1000.00 1500.00
Unskilled MD 5.00 700.00 3500.00
B Material
Cement MT 0.106 17500.00 1855.00
Sand m3 0.47 1100.00 517.00
Block stone m3 1.00 2300.00 2300.00
Bond stone m3 0.10 2300.00 230.00
water ltr 70.00 0.31 21.70
C Equipment
Providing and Laying Rubble masonry works including supply of hard stone blocks, preparing cement mortar (1:4) and construction of wall upto 5 m
13 Unit:1m3
high (Haulage distance up to 10 m)
A Labour
Skilled MD 1.50 1000.00 1500.00
Unskilled MD 5.00 700.00 3500.00
B Material
Cement MT 0.159 17500.00 2782.50
Sand m3 0.45 1100.00 495.00
Block stone m3 1.00 2300.00 2300.00
Bond stone m3 0.10 2300.00 230.00
water ltr 100.00 0.31 31.00
C Equipment
A Labour
Skilled MD 1.00 1000.00 1000.00
Unskilled MD 4.00 700.00 2800.00
B Material
Cement MT 0.22 17500.00 3850.00
River Sand m3 0.47 1100.00 517.00
Crushed agg.40mm down m3 0.65 1870.00 1215.50
Crushed agg.20mm down m3 0.24 1900.00 456.00
water ltr 120.00 0.31 37.20
C Equipment
Nil
D Subtotal (A+B+C) 9875.70
E Contractor's Overhead@ 15% of (D) 1481.36
Total(D+E) 11357.06
Rate per 1 m3 11357.06
P.C.C. in 1:2:4 (M15)work for levelling in ground with approved quality of cement and sand and crushed stone aggregate including mixing,laying,curing
15 Unit: 1 m3
etc all as per instruction and specification all complete.
A Labour
Skilled MD 1.00 1000.00 1000.00
Unskilled MD 4.00 700.00 2800.00
B Material
Cement MT 0.32 17500.00 5600.00
River Sand m3 0.445 1100.00 489.50
Crushed agg.40mm down m3 0.52 1870.00 972.40
Crushed agg.20mm down m3 0.22 1900.00 418.00
Crushed agg.10mm down m3 0.11 1950.00 214.50
water ltr 150.00 0.31 46.50
C Equipment
Nil
D Subtotal (A+B+C) 11540.90
E Contractor's Overhead@ 15% of (D) 1731.14
Total(D+E) 13272.04
Rate per 1 m3 13272.04
P.C.C. in 1:1.5:3 (M20) work for reinforced cement concrete work with approved quality of cement and sand and crushed stone aggregate including
16 Unit: 1 m3
mixing,laying,curing etc all as per instruction and specification all complete.
A Labour
Skilled MD 0.50 1000.00 500.00
Unskilled MD 3.50 700.00 2450.00
B Material
Cement MT 0.40 17500.00 7000.00
River Sand m3 0.425 1100.00 467.50
Crushed agg.20mm down m3 0.57 1900.00 1083.00
Crushed agg.10mm down m3 0.29 1950.00 565.50
Water ltr 200.00 0.31 62.00
Diesel ltr 3.00 90.00 270.00
Petrol ltr 0.10 104.00 10.40
C Equipment
Vibrator Hrs 0.25 96.80 24.20
Mixer Hrs 0.60 1875.00 1125.00
D Subtotal (A+B+C) 13557.60
E Contractor's Overhead@ 15% of (D) 2033.64
Total(D+E) 15591.24
Rate per 1 m3 15591.24
P.C.C. in 1:1.5:3 (M20) work for column jacketing with approved quality of cement and sand and crushed stone aggregate including mixing,laying,curing
17 Unit: 1 m3
etc all as per instruction and specification all complete.
A Labour
Skilled MD 0.80 1000.00 800.00
Unskilled MD 7.00 700.00 4900.00
B Material
Cement MT 0.40 17500.00 7000.00
River Sand m3 0.425 1100.00 467.50
Crushed agg.10mm down m3 0.86 1950.00 1677.00
Water ltr 200.00 0.31 62.00
C Equipment
Mahendra Bouddha SS Page 34 of 51 Civil Rate Analysis
D Subtotal (A+B+C) 14906.50
E Contractor's Overhead@ 15% of (D) 2235.98
Total(D+E) 17142.48
Rate per 1 m3 17142.48
P.C.C. in 1:1:2 (M25) work for for reinforced cement concrete work with approved quality of cement and sand and crushed stone aggregate including
18 Unit: 1 m3
mixing,laying,curing etc all as per instruction and specification all complete.
A Labour
Skilled MD 0.50 1000.00 500.00
Unskilled MD 3.50 700.00 2450.00
B Material
Cement MT 0.61 17500.00 10675.00
River Sand m3 0.425 1100.00 467.50
Crushed agg.20mm down m3 0.64 1900.00 1216.00
Crushed agg.10mm down m3 0.21 1950.00 409.50
Water ltr 300.00 0.31 93.00
Diesel ltr 3.00 90.00 270.00
Petrol ltr 0.10 104.00 10.40
C Equipment
Vibrator Hrs 0.25 96.80 24.20
Mixer Hrs 0.60 1875.00 1125.00
D Subtotal (A+B+C) 17240.60
E Contractor's Overhead@ 15% of (D) 2586.09
Total(D+E) 19826.69
Rate per 1 m3 19826.69
P.C.C. in 1:1:2 (M25) work for for Column jacketing work with approved quality of cement and sand and crushed stone aggregate including
19 Unit: 1 m3
mixing,laying,curing etc all as per instruction and specification all complete.
A Labour
Skilled MD 0.80 1000.00 800.00
Unskilled MD 7.00 700.00 4900.00
B Material
Cement MT 0.61 17500.00 10675.00
River Sand m3 0.425 1100.00 467.50
Crushed agg.10mm down m3 0.85 1950.00 1657.50
Water ltr 300.00 0.31 93.00
C Equipment
D Subtotal (A+B+C) 18593.00
E Contractor's Overhead@ 15% of (D) 2788.95
Total(D+E) 21381.95
Rate per 1 m3 21381.95
25mm first coat microconcreting 1:1.5:3 with superplasticizer for base preparation including filling of raked 25mm old mortar cavity, size of aggregate
20 Unit: 100m2
less than 10mm.
A Labour
Skilled MD 15.00 1000.00 15000.00
Unskilled MD 20.00 700.00 14000.00
B Material
Cement MT 0.88 17500.00 15400.00
River Sand m3 1.310 1100.00 1441.00
Crushed agg.10mm down m3 2.63 1950.00 5128.50
Superplasticizer ltr 13.20 250.00 3300.00 1.50%
C Equipment
@ 1.5% of (A) LS 435.00
D Subtotal (A+B+C) 54704.50
E Contractor's Overhead@ 15% of (D) 8205.68
Total(D+E) 62910.18
Rate per 1 m2 629.10
25mm thick flooring which includes 20mm (1:2:4) cement concrete with 5mm thick (1:1) white cement and stone chips as
19 Unit: 10m2
per the instruction of site engineer
Amount
S. N. Description Unit Quantity Rate (NRs.) Remarks
(NRs.)
A Labour
Skilled MD 2.50 1000.00 2500.00
Unskilled MD 16.00 700.00 11200.00
B Material
Cement MT 0.07 17500.00 1137.50
River Sand m3 0.088 1100.00 96.80
12.5 mm Aggregrate m3 0.176 1900.00 334.40
Mahendra Bouddha SS Page 35 of 51 Civil Rate Analysis
White Cement MT 0.061 40000.00 2440.00
Stone Chips m3 0.06 19135.20 1167.25
carborandum stone approx. 120.00
C Equipment
D Subtotal (A+B+C) 18995.95
E Contractor's Overhead@ 15% of (D) 2849.39
Total(D+E) 21845.34
Rate per 1 m2 2184.53
25mm outer coat microconcreting 1:1.5:3 with superplasticizer for base preparation including filling of raked 25mm old mortar cavity, size of aggregate
21 Unit: 100m2
less than 10mm.
A Labour
Skilled MD 15.00 1000.00 15000.00
Unskilled MD 20.00 700.00 14000.00
B Material
Cement MT 0.70 17500.00 12250.00
River Sand m3 1.050 1100.00 1155.00
Crushed agg.10mm down m3 2.10 1950.00 4095.00
Superplasticizer ltr 10.50 250.00 2625.00 1.50%
C Equipment
@ 1.5% of (A) LS 435.00
D Subtotal (A+B+C) 49560.00
E Contractor's Overhead@ 15% of (D) 7434.00
Total(D+E) 56994.00
Rate per 1 m2 569.94
22 Rate of microconcreting
23 Plywood formworks with steel adjustable pipe props for floor and slab Unit: 100 m2
24 19mm plywood formworks for beam including materials and removing with transpotation upto 30m. Unit: 10 m2
A Labour:
Skilled md 2.67 1000.00 2670.00
Unskilled md 4.00 700.00 2800.00
B Material:
ply board m2 1.65 1625.00 2681.25
local wood cum 0.039 66000.00 2574.00
steel prop no. 0.40 3855.60 1542.24
nails Kg 2.50 135.00 337.50
C Subtotal (A+B) 12604.99
D Contractor's Overhead @ 15% of (C) 1890.75
Total (C+D) 14495.74
Rate per 1 m2 1449.57
25 19mm plywood formworks for column including materials,erection,nailing, removing with transpotation upto 30m.(formwork on 2m dia column) Unit: 4.20 m2
27 Cutting, bending & placing of reinforcement bars in position as shown in the drawings and binding by GI wire for RCC works with 30 m lead all complete Unit: 1 Kg
28 Providing and Laying 38mm PCC (1:2:4) with 1:1 C/S punning on all rooms Unit:10 m2
A Labour
Skilled MD 1.25 1000.00 1250.00
Unskilled MD 2.00 700.00 1400.00
B Material
Cement MT 0.13 17500.00 2275.00
Sand m3 0.18 1100.00 198.00
12mm Aggregate m3 0.36 1950.00 702.00
Floor Hardener Kg 4.99 22.40 111.82
C Equipment
Nil
D Subtotal (A+B+C) 5936.82
E Contractor's Overhead @15% of (D) 890.52
Total(D+E) 6827.34
Rate per 1 m2 682.73
29 Providing and Laying 50mm PCC (1:2:4) with 1:1 C/S punning on terrace. Unit:10 m2
A Labour
Skilled MD 1.25 1000.00 1250.00
Unskilled MD 2.50 700.00 1750.00
B Material
Cement MT 0.17 17500.00 2975.00
Sand m3 0.23 1100.00 253.00
20mm Aggregate m3 0.46 1900.00 874.00
Floor Hardener Kg 5.00 22.40 111.96
C Equipment
Nil
A Labour
Skilled MD 1.00 1000.00 1000.00
Unskilled MD 1.00 700.00 700.00
B Material
Cement MT 0.0532 17500.00 931.00
C Equipment
Nil
D Subtotal (A+B+C) 2631.00
E Contractor's Overhead @15% of (D) 394.65
Total(D+E) 3025.65
Rate per 1 m2 302.57
Providing and laying 6mm porcelain glazed tiles on walls and floor of approved colored laid with cement sand mortar(1:4) finished with white cement
31 Unit: 10 m2
including polishing all complete as per specification and instruction of site engineer
Providing and laying 6mm porcelain non glazed tiles on walls and floor of approved colored laid with cement sand mortar(1:4) finished with white cement
32 Unit: 10 m2
including polishing all complete as per specification and instruction of site engineer
33 12.5 mm thick plastering for levelling surface,1:3 cement sand mortar on ceiling Unit:100 m2
A Labour
Skilled MD 15.00 1000.00 15000.00
Unskilled MD 20.00 700.00 14000.00
B Material
Cement MT 0.625 17500.00 10937.50
Sand m3 1.28 1100.00 1408.00
C Equipment
Nil
D Subtotal (A+B+C) 41345.50
E Contractor's Overhead @15% of (D) 6201.83
Total(D+E) 47547.33
Rate per 1 m2 475.47
34 20 mm thick plastering for levelling surface,1:6 cement sand mortar other than ceiling Unit:100 m2
A Labour
Skilled MD 14.00 1000.00 14000.00
Unskilled MD 19.00 700.00 13300.00
35 12.5 mm thick plastering for levelling surface,1:4 cement sand mortar other than ceiling Unit:100 m2
A Labour
Skilled MD 12.00 1000.00 12000.00
Unskilled MD 16.00 700.00 11200.00
B Material
Cement MT 0.538 17500.00 9415.00
Sand m3 1.46 1100.00 1606.00
C Equipment
Nil
D Subtotal (A+B+C) 34221.00
E Contractor's Overhead @15% of (D) 5133.15
Total(D+E) 39354.15
Rate per 1 m2 393.54
A Labour
Skilled MD 14.00 1000.00 14000.00
Unskilled MD 19.00 700.00 13300.00
B Material
Cement MT 0.81 17500.00 14175.00
Sand m3 2.20 1100.00 2420.00
C Equipment
Nil
D Subtotal (A+B+C) 43895.00
E Contractor's Overhead @15% of (D) 6584.25
Total(D+E) 50479.25
Rate per 1 m2 504.79
A Labour
Skilled MD 0.025 1000.00 25.00
Unskilled MD 0.01 700.00 7.00
B Material
Cement MT 0.007 17500.00 122.50
Sand m3 0.004 1100.00 4.40
Water proofing lit 0.0001 275.00 0.03
D Subtotal (A+B) 158.93
E Contractor's Overhead @15% of (D) 23.84
Total(D+E) 182.77
Rate per 1 rm 182.77
A. Labour
Skilled MD 34.00 1000.00 34000.00
Unskilled MD 3.40 700.00 2380.00
B. Material:
Agrakh wood cu.m 1.10 275000.00 302500.00
Holdfast Nos 92.00 50.00 4600.00
Screw Nails Nos 184.00 1.00 184.00
C. Subtotal 343664.00
D. Contractor's Overhead @ 15% of (C) 51549.60
Total (C+D) 395213.60
A. Labour
Skilled MD 17.65 1000.00 17650.00
Unskilled MD 1.76 700.00 1232.00
B. Material:
Agrakh wood cu.m 1.05 275000.00 288750.00
Screw Nails LS 60.00
C. Subtotal 307692.00
D. Contractor's Overhead @ 15% of (C) 46153.80
Total (C+D) 353845.80
Rate per 1 m3 353845.80
Making, fitting & fixing pannel door shutter with 38mm thick sal wood frame including all necessary approved quality of hardware fittings according to
40 Unit: 2.114m2
inst. of site eng.all complete work.
A Labour
Skilled MD 10.00 1000.00 10000.00
Unskilled MD 1.000 700.00 700.00
B Material
Agrakh wood cum 0.084 275000.00 23100.00
100mm Hinge Nos 6.00 37.00 222.00
150mm tower bolt Nos 1.00 95.00 95.00
300mm tower bolt Nos 1.00 225.00 225.00
300mm locking set Nos 1.00 1050.00 1050.00
Handle Nos 2.00 250.00 500.00
Screw nail L.S. 45.00
C Subtotal (A+B) 35937.00
D Contractor's Overhead @15% of (C) 5390.55
Total(C+D) 41327.55
Rate per 1 m2 19549.46
Fitting anf fixing of glazed shutter in 38x75mm thick salwood frame with 5mm thick plain glass fitting including all necessary hardware fittings all
41 Unit: 2.114m2
complete as per drawings, specification and instruction of the Engineer.
A Labour
Skilled MD 9.00 1000.00 9000.00
Unskilled MD 0.900 700.00 630.00
B Material
Agrakh wood cum 0.049 275000.00 13475.00
5mm glass Sqm 1.085 1100.00 1193.50
75mm Hinge Nos 8.00 30.00 240.00
100mm tower bolt Nos 4.00 64.00 256.00
Handle Nos 2.00 250.00 500.00
Screw nail L.S. 35.00
C Subtotal (A+B) 25329.50
D Contractor's Overhead @15% of (C) 3799.43
Total(C+D) 29128.93
Rate per 1 m2 13779.06
A Labour
Skilled MD 0.06 1000.00 60.00
Unskilled MD 0.006 700.00 4.20
B Material
5mm glass sq.m 1.00 1100.00 1100.00
Wooden listy rm 4.050 52.48 212.54
Screw nail L.S. 15.00
D Subtotal (A+B+C) 1391.74
E Contractor's Overhead @15% of (D) 208.76
Total(D+E) 1600.51
Rate per 1 m2 1600.51
Removing of existing door or window,its safe storage before construction and reinstate it after retrofitting including cleaning and fixing all complete as
43 Unit: 1 no
original condition or as per instruction by engineer.
A Labour
Skilled MD 0.25 1000.00 250.00
Labour for removing and
Unskilled MD 0.25 700.00 175.00 safe storage
B Equipment
3% of (A) LS 38.25
C Subtotal (A+B) 1313.25
D Contractor's Overhead @15% of (C) 196.99
Total(C+D) 1510.24
Rate per 1 no 1510.24
Colouring with Two coats distemper paint with one coat primer to give uniform colouring after rendering the surface on wall,ceiling,column,beam,etc as
44 Unit:100 m2
per specification and instruction all complete.
A Labour
Skilled MD 5.80 1000.00 5800.00
Unskilled MD 5.80 700.00 4060.00
B Material
Washable distemper LT 16.00 264.00 4224.00
Primer LT 8.00 320.00 2560.00
C Equipment
Nil
D Subtotal (A+B+C) 16644.00
E Contractor's Overhead @15% of (D) 2496.60
Total(D+E) 19140.60
Rate per 100 m2 19140.60
Rate per 1 m2 191.41
45 2 coats of apex paint (weather coat) of approved colour with one coat primer to give uniform coloring after rendering the surface on wall,column etc over Unit:100 m2
properly cleaned surface all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 5.80 1000.00 5800.00
Unskilled MD 5.80 700.00 4060.00
B Material
Apex paint LT 16.00 1285.00 20560.00
Primer LT 8.00 320.00 2560.00
C Equipment
Nil
D Subtotal (A+B+C) 32980.00
E Contractor's Overhead @15% of (D) 4947.00
Total(D+E) 37927.00
Rate per 100 m2 37927.00
Rate per 1 m2 379.27
46 2 coats of ready made enamel paint of approved colour over 1 coats of primer Painting over properly sanded wooden surface all complete. Unit:100 m2
A Labour
Skilled MD 12.00 1000.00 12000.00
Unskilled MD 8.00 700.00 5600.00
B Material
Primer LT 8.10 320.00 2592.00
Enamel paint LT 16.00 715.00 11440.00
C Equipment
Nil
D Subtotal (A+B+C) 31632.00
E Contractor's Overhead @15% of (D) 4744.80
Total(D+E) 36376.80
Rate per 100 m2 36376.80
Rate per 1 m2 363.77
Staircase railing work with 50mm stainless steel pipe hand railing with 50mm stainless steel pipe vertical post at 2m spacing and three 25mm stainless
47 Unit:1 rm
steel pipe between hand rail and ground on height 750 to 900 mm as per design drawing & specification & instructon site incharge.
Supplying & fixing of spiral staircase with 4"-6" black pipe post medium class, 20mm square pipe railing , 32mm handrail, width of staircase 90cm
48 Unit:1 rm
including red oxide primer coat and necessary fittings
50 Providing materials and constructing 2ft wide ridge from 0.5mm plain GI sheet and also fixing Unit:10 rm
A. Labour:
Skilled md 2.00 1000.00 2000.00
Unskilled md 3.00 700.00 2100.00
B. Material:
Coloured Plain sheet (0.5 mm) RM 12.00 798.00 9576.00
8 mm nut bolt LS 70.00
C. Subtotal (A+B) 13746.00
D. Contractor's Overhead @ 15% of (C) 2061.90
Total (C+D) 15807.90
Rate per 1 rm 1580.79
Rate Per 1m2 2634.65
51 Providing & fixing of MS truss with one coat red oxide Unit: 18.94 kg
Labour:
A. Skilled md 1.10 1000.00 1100.00
Unskilled md 1.25 700.00 875.00
Material:
B. 1.2mm GI folded plate m2 12.00 750.00 9000.00
8 mm nut bolt nos. 30.00 22.00 660.00
J hook nos. 25.00 15.40 385.00
Bitumen washer nos. 55.00 3.50 192.50
C. Subtotal (A+B) 12212.50
D. Contractor's Overhead @ 15% of (C) 1831.88
Total (C+D) 14044.38
Rate per 1 m2 1404.44
Drilling for anchor in masonry wall upto depth of 350mm,hole of diameter 10mm @450mmc/c staggered and filling the holes by cement slurry with 8mm
53 Unit: 1 no
dia bar all complete as per drawing,specification and instruction of the Engineer.
Labour:
A. Skilled md 0.02 1000.00 20.00 30 holes per day
Unskilled md 0.01 700.00 7.00
Material:
8mm dia bar kg 0.20 102.00 20.40
B. Cement MT 0.00004 17500.00 0.70
Drilling machine Per day 0.05 500.00 25.00
Drilling bit Nos 0.01 500.00 5.00
C. Equipment:
@ 3% of (A) LS 0.81
D. Subtotal (A+B+C) 78.91
E. Contractor's Overhead @ 15% of (D) 11.84
Total (D+E) 90.75
Rate per 1 no 90.75
Drilling for anchor in masonry wall upto depth of 125mm,hole of diameter 14mm @450mmc/c staggered and filling the holes by epoxy grout with 12 dia
54 Unit: 1 no
bar all complete as per drawing,specification and instruction of the Engineer.
Labour:
A. Skilled md 0.02 1000.00 20.00 30 holes per day
Unskilled md 0.01 700.00 7.00
Material:
12mm dia bar kg 0.24 102.00 24.89
B. Epoxy Grout MT 0.00004 2625000.00 105.00
Drilling machine Per day 0.05 500.00 25.00
Drilling bit Nos 0.01 500.00 5.00
C. Equipment:
@ 3% of (A) LS 0.81
D. Subtotal (A+B+C) 187.70
E. Contractor's Overhead @ 15% of (D) 28.15
Total (D+E) 215.85
Rate per 1 no 215.85
Drilling for anchor in masonry wall upto depth of 230mm,hole of diameter 10mm @450mmc/c staggered and filling the holes by cement slurry with 8mm
55 Unit: 1 no
dia bar all complete as per drawing,specification and instruction of the Engineer.
Labour:
A. Skilled md 0.02 1000.00 20.00 30 holes per day
Unskilled md 0.01 700.00 7.00
Material:
8mm dia bar kg 0.26 102.00 26.52
B. Cement MT 0.00004 17500.00 0.70
Drilling machine Per day 0.05 500.00 25.00
Drilling bit Nos 0.01 500.00 5.00
C. Equipment:
@ 3% of (A) LS 0.81
D. Subtotal (A+B+C) 85.03
E. Contractor's Overhead @ 15% of (D) 12.75
Total (D+E) 97.78
Rate per 1 no 97.78
Drilling for anchor in masonry wall upto depth of 120mm,hole of diameter 14mm @150mmc/c staggered and filling the holes by cement slurry with 12mm
56 Unit: 1 no
dia bar all complete as per drawing,specification and instruction of the Engineer.
Labour:
A. Skilled md 0.02 1000.00 20.00 30 holes per day
Unskilled md 0.01 700.00 7.00
Material:
12mm dia bar kg 0.22 102.00 22.44
B. Cement MT 0.00004 17500.00 0.70
Drilling machine Per day 0.05 500.00 25.00
Drilling bit Nos 0.01 500.00 5.00
C. Equipment:
@ 3% of (A) LS 0.81
D. Subtotal (A+B+C) 80.95
E. Contractor's Overhead @ 15% of (D) 12.14
Total (D+E) 93.09
Rate per 1 no 93.09
57 Drilling the 12mm dia holes rotatory drill on masonry wall upto max 400mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.02 1000.00 20.00 50 holes per day
Unskilled md 0.01 700.00 7.00
Material:
B. Drilling machine Per day 0.02 500.00 10.00
Drilling bit Nos 0.02 500.00 10.00
C. Equipment:
@ 3% of (A) LS 0.81
D. Subtotal (A+B+C) 47.81
E. Contractor's Overhead @ 15% of (D) 7.17
Total (D+E) 54.98
Rate per 1 no 54.98
58 Drilling the 10mm dia holes rotatory drill on concrete surface upto max 125mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.013 1000.00 13.00 25 holes per day
Unskilled md 0.013 700.00 9.10
Material:
B. Drilling machine Per day 0.013 500.00 6.50
Drilling bit Nos 0.013 500.00 6.50
C. Equipment:
@ 3% of (A) LS 0.66
D. Subtotal (A+B+C) 52.16
E. Contractor's Overhead @ 15% of (D) 7.82
Total (D+E) 59.98
Rate per 1 no 59.98
59 Drilling the 12mm dia holes rotatory drill on concrete surface upto max 125mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.015 1000.00 14.95 25 holes per day
Unskilled md 0.015 700.00 10.46
Material:
B. Drilling machine Per day 0.015 500.00 7.47
Drilling bit Nos 0.015 500.00 7.47
Epoxy grout LS 29.41 1 Ltr for 68 holes
C. Equipment:
@ 3% of (A) LS 0.76
D. Subtotal (A+B+C) 70.54
E. Contractor's Overhead @ 15% of (D) 10.58
Total (D+E) 81.12
Rate per 1 no 81.12
60 Drilling the 14mm dia holes rotatory drill on concrete surface upto max 125mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.017 1000.00 16.90 25 holes per day
Unskilled md 0.017 700.00 11.83
Material:
B. Drilling machine Per day 0.017 500.00 8.45
Drilling bit Nos 0.017 500.00 8.45
Epoxy grout LS 65.63 1 Ltr for 40 holes
C. Equipment:
@ 3% of (A) LS 0.86
D. Subtotal (A+B+C) 112.12
E. Contractor's Overhead @ 15% of (D) 16.82
Total (D+E) 128.93
Rate per 1 no 128.93
61 Drilling the 18mm dia holes rotatory drill on concrete surface upto max 125mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.019 1000.00 18.85 25 holes per day
Unskilled md 0.019 700.00 13.19
Material:
B. Drilling machine Per day 0.019 500.00 9.42
Drilling bit Nos 0.019 500.00 9.42
Epoxy grout LS 83.33 1 Ltr for 24 holes
C. Equipment:
@ 3% of (A) LS 0.96
D. Subtotal (A+B+C) 135.19
E. Contractor's Overhead @ 15% of (D) 20.28
62 Drilling the 22mm dia holes rotatory drill on concrete surface upto max 125mm depth as per instruction by site engineer. Unit: 1 no
Labour:
A. Skilled md 0.021 1000.00 20.80 25 holes per day
Unskilled md 0.021 700.00 14.56
Material:
B. Drilling machine Per day 0.021 500.00 10.40
Drilling bit Nos 0.021 500.00 10.40
Epoxy grout LS 125.00 1 Ltr for 16 holes
C. Equipment:
@ 3% of (A) LS 1.06
D. Subtotal (A+B+C) 182.22
E. Contractor's Overhead @ 15% of (D) 27.33
Total (D+E) 209.55
Rate per 1 no 209.55
62 Providing & fixing of MS grill with sanded and one coat red oxide Unit: 1 kg
Supply,fitting and fixing of MS grill made in 4.5mm X 20mm size MS patti frame with 12mm X 12mm solid core square rod grill with sandpapering and
63 Unit: 10 sqm
prime coat all complete as per instruction of site incharge
A. Material:
4.5mm X 20mm size MS patti frame kg 28.24 130.00 3671.20
Making and fixing 12mm X 12mm solid core square rod grill kg 215.00 120.00 25800.00
C. Subtotal 30591.20
D. Contractor's Overhead @ 15% of (C) 4588.68
Total (C+D) 35179.88
Rate per sqm. 3517.99
Supplying and Installation of Gypsum board False Ceiling with GI framing and all accessories complete as per drawing, specification and instruction of
64 Unit: 1 m2
the consultant/ Engineer all complete
A 12.5mm thick Gypsum Board False ceiling including all necessary material Sq.m 1.00 1506.17 1506.17
B Subtotal 1506.17
C Contractor's Overhead @ 15% of (B) 225.93
Total (B+C) 1732.10
Rate per 1 m2 1732.10
Elastocrete cementitious elastometric water proofing coating 2 components capacity per kg 6 sq.ft 2 coat including supply and applying all complete work
65 Unit: 1 m2
as per drawing, specification and direction of the engineer .
A Labour:
Skilled md 0.00 1000.00 0.00
Unskilled md 0.00 700.00 0.00
B Material:
Metal Gate sq.m 10.00 5550.00 55500.00
C Subtotal 55500.00
D Contractor's Overhead @ 15% of (C) 8325.00
Total (C+D) 63825.00
Rate per 1 m2 6382.50
Providing 1.5 meter high chain link fence having mesh size 50mm x 50mm woven with SWG 10 heavy GI coated wire with 50x50x5 mm
ISA line post spaced at 2.5 meter center to center, 50x50x5 mm corner and end post , 50x50x5 mm ISA bracing post at every 15 meter
=
straight run and at every change in direction more than 15 degree and at end and corner post, 40x40x4 mm ISA top and bottom rail
67 Unit: 15 m2
including installation of all post by excavating hole (300x300x600) and filling with concrete 1:2:4 (1 cement : 2 sand : 4 stone aggregate 20
mm and down grade), rails, stretching chain link fabric, fixing chain link fabric securely in all post, top and bottom rail, etc., all complete
as per drawings, specification and instruction of the Engineer.
A Labour
md 0.1 700.00 70.00
B Equipment
@ 3% of (A) LS 2.10
C Subtotal (A+B) 72.10
D Contractor's Overhead@ 15% of (C) 10.82
Total(D+E) 82.91
Rate per 1 m2 82.91
70 Demolition of roof of sheet with wooden/metal truss removing the material at a distance of 10m Unit: 1 m2
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.027 1000.00 27.00
Unskilled MD 0.04 700.00 28.00
B Subtotal (A) 55.00
71 Demolition of wall with mud mortar and removing the material at a distance of 10m Unit: 1 m3
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled md 1.06 700.00 742.00
B Subtotal (A) 742.00
C Contractor's Overhead@ 15% of (B) 111.30
Total(B+C) 853.30
Rate per 1 m3 853.30
72 Demolition of wall with cement mortar and removing the material at a distance of 10m Unit: 1 m3
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled md 2.12 700.00 1,484.00
B Subtotal (A) 1,484.00
C Contractor's Overhead@ 15% of (B) 222.60
Total(B+C) 1,706.60
Rate per 1 m3 1,706.60
A Labour
md
Unskilled 0.108 700.00 75.60
B Subtotal (A) 75.60
C Contractor's Overhead@ 15% of (B) 11.34
Total(B+C) 86.94
Rate per 1 m2 86.94
74 Demolition of roof of PCC works removing the material at a distance of 10m Unit: 1 m3
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
md
Unskilled 4 700.00 2,800.00
B Subtotal (A) 2,800.00
C Contractor's Overhead@ 15% of (B) 420.00
Total(B+C) 3,220.00
Rate per 1 m3 3,220.00
75 Demolition of roof of RCC works removing the material at a distance of 10m Unit: 1 m3
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
md
Unskilled 11 700.00 7,700.00
B Subtotal (A) 7,700.00
C Contractor's Overhead@ 15% of (B) 1,155.00
Total(B+C) 8,855.00
Rate per 1 m3 8,855.00
75 Demolition of brick soling works removing the material at a distance of 10m Unit: 1 m2
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
md
Unskilled 0.08 700.00 56.00
B Equipment
@ 3% of (A) LS 1.68
76 This work includes taking out door and windows and celerestory windows shutters (steel or wood ) including stacking within 50 meters lead: Unit: 1 no
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
md
Skilled 0.05 1000.00 50.00
A Labour
Skilled MD 0.08 1000.00 80.00
Unskilled MD 0.08 700.00 56.00
B Sundries
@ 5% of (A) LS 6.80
C Add 1% water charges LS 1.43
D Subtotal (A+B+C) 144.23
E Contractor's Overhead@ 15% of(D) 21.63
Total(D+E) 165.86
Rate per 1 rm 16.59
78 Demolition of false ceiling and removing the material at a distance of 10m Unit: 10 m2
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled MD 0.2 1000.00 200.00
Unskilled MD 0.3 700.00 210.00
B Sundries
@ 5% of (A) LS 20.50
C Add 1% water charges LS 4.31
D Subtotal (A+B+C) 434.81
E Contractor's Overhead@ 15% of (D) 65.22
Total(D+E) 500.03
Rate per 1 m2 50.00
Providing and Laying of grass (local duboo with root carrying and anchoring with 8" bamboo peg and watering for 10 days( on soil ) near Retaining wall),
79 all complete as per specification and instructions of the Engineer. Unit: 100 m2
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Unskilled md 5.04 700.00 3,528.00
B Equipment
Dubo Sqm 100 322.80 32,280.00
Compost Manure Kg 7 28.00 196.00
C Subtotal (A+B) 36,004.00
D Contractor's Overhead@ 15% of (C) 5,400.60
Total(C+D) 41,404.60
Rate per 1 m2 414.05
Supplying and fixing SEALGUARD GEOTEX [P] -Polyester Geotextile behind retaining wall/breast wall before backfilling as per instruction of site
80 engineer. Unit: 1 m2
A Labour:
Skilled md 0.00 1000.00 0.00
Unskilled md 0.017 700.00 11.90
B Material:
SEALGUARD GEOTEX [P] -Polyester Geotextile m2 1.20 150.00 180.00
C Subtotal (A+B) 191.90
D Contractor's Overhead @ 15% of (C) 28.79
Total (C+D) 220.69
Rate per 1 m2 220.69
Providing material and laying 1:2 cement sand Ruled pointing works true to line and level as per instructions including chipping, hacking and wetting of
82 Unit:100 m2
surface, scaffolding, curing, etc.
A Labour
Skilled md 10.000 1000.00 10000.00
Unskilled md 14.00 700.00 9800.00
B Material
Cement MT 0.408 17500.00 7140.00
Sand m3 0.570 1100.00 627.00
C Subtotal (A+B) 27567.00
D Contractor's Overhead @15% of (C) 4135.05
Total(C+D) 31702.05
Rate per 1 m2 317.02
83 Mechanically Selvedge Double Twist Wire Mesh Gabion Box (2x1x1) MBG/10x12/2.7/3.4/2.2/ZN Unit: per box
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Material
2mx1mx1m nos 1 2182.00 2,182.00
B Subtotal (A) 2,182.00
Contractor's Overhead@ 15% of (B) 327.30
Total(A+B) 2,509.30
Rate per 1 box 2,509.30
Providing and Filling Stone /Boulder in gabion boxes/mattress etc Including dressing,bedding ,bonding all complete as per Drawing and Technical
84 Unit: per 10m3
Specification .
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
Skilled md 2 1000.00 2,000.00
Unskilled md 8 700.00 5,600.00
B Material
Boulder /Stone cum 11 2,300.00 25,300.00
C Subtotal (A+B) 32,900.00
D Contractor's Overhead@ 15% of (C) 4,935.00
Total(C+D) 37,835.00
Rate per 1 m3 3,783.50
A Labour
Skilled MD 0 1000.00 -
Unskilled MD 21.6 700.00 15,120.00
B Equipment
@ 3% of (A) LS 453.60
C Subtotal (A+B+C) 15,573.60
D Contractor's Overhead@ 15% 0f (D) 2,336.04
Total(D+E) 17,909.64
Rate per 1 m2 179.10
87 Preparation of 10cmx10cm hole on slab surface for pouring concrete in column as per drawing,specification and instruction of the Engineer. Unit: 1 No
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
88 Preparation of 35cmx35cm hole on slab surface for pouring concrete in column as per drawing,specification and instruction of the Engineer. Unit: 1 No
Remarks
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.)
A Labour
md
Unskilled 0.35 700.00 245.00
B Equipment
@ 3% of (A) LS 7.35
C Subtotal (A+B+C) 252.35
D Contractor's Overhead@ 15% of(D) 37.85
Total(D+E) 290.20
Rate per 1 no 290.20
Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of
89 appproved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and Unit: 100 m2
allowing it to dry, all complete as per the acceptance of engineer-in-charge.
Providing and applying one coat of Primer HM180 for the Carbon fibre wrapping
1 including labors, equipment and scaffolding all complete as per instructions of site Sqm 1.00 1000.00 1000.00
engineer.
Providing and applying Carbon Fibre Wrap 200 gsm by HM180C3P Epoxy
Adhesive over the item no 1 properly in line, level and reducing air voids
2 Sqm 1.00 6956.52 6956.52
including materials, labors, instruments, scaffolding all complete as per
instructions of site engineer.
Providing and applying one layer of fine coarse Sand/silica by sand blower on
4 carbon fibre wrap/epoxy surface for to receive plaster layer including materials, Sqm 1.00 100.00 100.00
labors, equipment and scaffolding all complete as per instruction of site enginer.
A Works
Prefabricated Carbon fibre Reinforced Polymer Laminate(50mm wide and 1.4 mm
1 Rm 1.00 8500.00 8500.00
thick)
Providing and applying one layer of fine coarse Sand/silica by sand blower on
2 carbon fibre wrap/epoxy surface for to receive plaster layer including materials, Rm 1.00 20.00 20.00
labors, equipment and scaffolding all complete as per instruction of site enginer.
Providing and applying one layer of fine coarse Sand/silica by sand blower on
2 carbon fibre wrap/epoxy surface for to receive plaster layer including materials, Rm 1.00 20.00 20.00
labors, equipment and scaffolding all complete as per instruction of site enginer.
90 SS plates Unit: 10 kg
A Labour
Skilled MD 0 1000.00 -
Unskilled MD 0 700.00 -
B Material
Metal door Sq.m 1 6500.00 6,500.00
C Subtotal (A+B+C) 6,500.00
D Contractor's Overhead@ 15% 0f(D) 975.00
Total(D+E) 7,475.00
Rate per 1 m2 7,475.00
92 Providing & fixing of C channel section with one coat red oxide Unit: 18.94 kg
93 Providing & fixing of angle section with one coat red oxide Unit: 18.94 kg