Professional Documents
Culture Documents
A GENERAL WORKS
Provide insurance for the loss of damage to works, plant, material, equipment, property
1 1.00 PS 85,234.91 85,234.91
and personnel injury or death as per specification and instruction.
Provision of laboratory tests as required and order outside the project Laboratory as
2 1.00 PS 18,849.00 18,849.00
per the specification and instructions of the Site engineers.
Provide , erect and maintain project site notice boards as per instruction of Site
3 1.00 PS 17,553.60 17,553.60
engineer and specification all complete.
As Built Drawing of project (civil, electrical, sanitation in 1:100 scale 5 sets hard copy
4 1.00 PS 40,033.40 40,033.40
including digital copy as per the instruction of the Site Engineer
Total Works of A 161,670.91
B CIVIL WORKS
1 Site clearance
Site clearance before and after completion of work including disposing the remaining
1.1 construction materials & plants & making the site in working condition all complete as 128.25 Sqm 18.51 2,373.91
per instruction of site Engineer.
2 Earthworks
Earthwork in excavation in hard/boulder mix soils in foundation including 10m hauling
2.1 distance and 1.5 m. lift all complete as per design, drawing, specification and 100.85 Cum 663.32 66,895.82
instruction of site Engineer.
Earthwork backfilling in 150 mm layers by ramming & watering at required places as
2.2 per instruction & disposing all surplus excavated materials within the site as per 51.86 Cum 799.25 41,445.11
design, drawing, specification and instruction of site Engineer all complete.
Flat dry brick soling on flat in foundation and floor including sand filling in joints,
2.3 leveling, ramming etc. with sand as per design, drawing, specification and instruction of 97.81 sq.m. 1,019.63 99,730.01
site engineer
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
8 Brick Works
Brickwork in cement sand mortar (1:4) in Superstructure (Ground Floor) with supplying
of approved quality first class chimney burnt bricks, in perfect line and level including
8.1 soaking bricks in water, provision for recesses, openings, toothings, packing the joints 22.33 Cum 15,646.11 349,377.64
and curing the work in all types and thickness of wall as per specification, drawing and
instruction of Site Engineer, all complete.
Brickwork in cement sand mortar (1:4) above Ground Floor level with supplying of
approved quality first class chimney burnt bricks, in perfect line and level including
8.2 soaking bricks in water, provision for recesses, openings, toothings, packing the joints 19.37 Cum 16,060.69 311,095.57
and curing the work in all types and thickness of wall as per specification, drawing and
instruction of Site Engineer, all complete.
9 Plaster Works
12.5mm thick cement sand plaster in (1:4) ratio on wall with good finish including
supplying of approved quality of cement & sand, racking the joint, Chipping the
9.1 concrete surface, wetting of surfaces & curing the work all complete including 499.00 Sq. m 402.69 200,941.91
necessary single or multiple stage scaffolding at all heights. as per the design,
drawing, specification and instruction of site engineer.
12.5mm thick cement sand plaster in (1:3) ratio on ceiling with good finish including
supplying of approved quality of cement & sand, chipping the concrete surface, wetting
9.2 the surfaces & curing the work all complete including necessary single or multiple stage 62.20 Sq. m 480.24 29,870.93
scaffolding at all heights. as per the design, drawing, specification and instruction of
site engineer.
10 Flooring Works
Flat brick soling on flat in foundation and floor including sand filling in joints, leveling,
10.1 ramming etc. with sand as per design, drawing, specification and instruction of site 43.02 sq.m. 1,019.63 43,864.48
engineer
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
10.2 sand and crushed stone aggregate including mixing, laying and compacting and curing 52.74 Sqm 1,212.41 63,942.50
etc. all complete as per design, drawing, specification and instruction of site Engineer
Supplying and laying of one layer of 500 gauge Polythene sheet on prepared surface
10.3 39.78 Sqm 153.75 6,116.18
50 mm thick (1:2:4) concrete screeding work with water proof compound including
10.4 mixing laying and rubbing with steel trowel to a hard, smooth and shining surface and 91.66 Sqm 891.31 81,697.47
curing all complete.
Floor Finishing Works
Providing and Laying 3 mm thick cement sand punning on floor, skriting, dado etc.,
including mixing laying and rubbing with steel trowel to a hard, smooth and shining
10.5 132.26 sq.m. 293.80 38,857.99
surface and curing all complete.as per specification, drawing and instruction of Site
Engineer.
Providing and laying 8 mm thick glazed/nonglazed ceramic tiles (Spartek, Kajaria, or
approved equivalent) of approved shade, size and pattern on Skirting, perapet wall top
and floor in perfect line and level on 12.5 mm thick base cement sand mortar (1:4) and
10.6 32.72 Sq.m 3,113.43 101,855.86
jointed with cement slurry mixed with pigment to match the shade of the tile including
adhesive chemical all complete as per specification, drawing and instruction of Site
Engineer.
11 Door / Windows
Suppling and fixing Salwood chaukhat frame works for doors & windows as approved
11.1 by site engineer , the timber shall be matured, seasoned free from wraps. Knots holes 1.21 Cum 301,732.63 365,096.48
and other defects all complete.
Making and fitting, fixing sal wood Panelled door shutter with 38 mm thick sal wood
11.2 6.21 Sqm 15,511.76 96,328.03
frame including all necessary hardware fitting all complete.
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
C ELECTRICAL WORKS
1 DISTRIBUTION BOARDS
1.1 DISTRIBUTION BOARDS (Breaker make Schneider , L& T or Equivalent) 1.00 Set 27,600.00 27,600.00
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
Point Wiring( Switch socket make : Schneider or equivalent, Wire make: Pioneer,
3 10.00 points 2,500.00 25,000.00
Mahalaxmi, Trishakti make)
3.1 6/16 A twin Power point wiring
Supplying, wiring, testing and commissioning and putting into
operation for 6/16 A and 13 A power point using 2 x 4 sq mm
+ 1 x 2.5 Sq mm stranded copper conductor, 1100 volts grade, PVC insulated wires
drawn through HDP conduit, cable sleeve/support but including specified dia pipes
concealed in wall and floor/false ceiling including all fixing and connecting materials.
The rate for point wiring shall include the circuit wiring from deginated Distribution
Board (DB) up to the first power point then the looping between sockets. The cost
shall be including modular formation twin switch sockets and their flushing GI box ,
cutting and filling chases for recessed pipes as deemed as per drawing and lay out
plan all complete.(Average Length=12 m)
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
D SANITARY WORKS
Supply and Install 110 mm UPVC Rainwater down pipe including Screen, Inlet and all
1 30.00 Rm 419.78 12,593.52
required fittings & accessories all complete as per engineer instruction
Supply and Install 150 mm HDP Pipe 4kgf. including required all accessories all
2 40.00 Rm 1,102.49 44,099.60
complete as per engineer instruction
Checked By:
Prepared By: Approved By:
Government Of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit (CLPIU)
(Grant Management and Local Infrastructure)
Earthquake Monastery Reconstruction Section
Jwagal, Lalitpur, Nepal
E Others Component
Providing and Fixing Chatras (placed on corners of parapets. Made up of Fibre
1 4.00 Nos. 35,000.00 140,000.00
moulding.) Diameter= 1'-6" Height= 2'-8"
Providing and Fixing Gajur (main) Placed on top of main sloped roof
2 1.00 Nos. 40,000.00 40,000.00
Diameter=0'-6" Height= 2'-6" Made up of Fibre moulding
Providing and Fixing Gajur (secondary) Placed on top of main sloped roof of secondary
3 1.00 Nos. 35,000.00 35,000.00
entrance . Diameter=0'-6" Height= 1'-6" Made up of Fibre moulding
Providing and Fixing Dharmachakra and 2 deers (Placed above the entry porch. Made
up of concrete moulding.) Two nos of deers placed above the entry porch. Made up of
4 1.00 Nos. 50,000.00 50,000.00
Fibre moulding. Diameter= 1'-6" Height= 3'-6" Length= 2'-6" Height= 2'-0" breath= 1'-0"
Providing and fixing Dragons Placed on corners of pagodas. Made of metal moulding
5 4.00 Nos. 10,000.00 40,000.00
Length= 1'-6" breath= 1'-0" Made up of Fibre moulding
Total Works of E 305,000.00
F Miscelleneous Works
Providing and Fixing 9 Kg BC/ABC type Dry Pouder Fire Extinguisher Attack fire Brand
1 2.00 Nos. 9,775.00 19,550.00
or equivalent
Type of Fire:BC/AB&C
Extinguishing Type:Stored Pressure
Extinguishing Media
Dry Powder:(Mono Ammonium Phospate/Sodium-bi-carbonate) IS: 4308 / IS: 14609 Pressured
with N2 Gas
Total Works of F 19,550.00
Checked By:
Prepared By: Approved By: