You are on page 1of 6

Page 1 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks


A GENERAL WORK
1 Making fitting & fixing Hoarding Board of 4'x5'
size with project information all complete work as
PS 1.00 5,000.00 5,000.00
per specification and instruction of site engineer

2 Insurance : Insurance of works, construction


equipments and against accident to workmen PS 1.00 25,000.00 25,000.00
including third party insurance.
3 Additional Laboratory Test: Additional lab testing
of materials, specimen, mix design etc. not
PS 1.00 10,000.00 10,000.00
considered in item rate(specification) as
instructed by Engineer if required.
B CIVIL WORK
Site clearance: after completion of work including
disposing of unused materials away from site all
1 L.S. 1.00 5,000.00 5,000.00
complete as per instruction of site technician

Providing and laying PCC (1:1.5:3) M20 for RCC


work in foundation, column, beam, slab, lintel etc.
with cement sand and crosser aggregate of
2 Cu.m. 76.52 16,419.55 1,256,501.06
required size including mixing with concrete
mixture, compacting the concrete with vibrator
machine, laying, finishing to approved level, lines
and dimension and curing all complete work as
per specification and instruction of site Engineer.
3 Providing Reinforcement bars (Grade Fe 415 or
above) work including straightening, cleaning,
cutting, bending, binding with 20 SWG annealed
wire & fixing in position as per design drawing,
bar bending schedule for raft foundation column, Kg. 11010.73 112.84 1,242,478.44
beam, wall, stair, slab in all RCC works as per
specification, drawing & instruction of site
Engineer. Approved brand : Himal Iron,
Panchakanya or Equivalent.

Form Work of RCC work with necessary wood,


nails, proping, scaffolding, stagging, support
4 Sq.m. 668.39 863.20 576,950.64
inclusive of wedging and cutting holes for
utilization work till the support is full unyielding
nett for Column/Beam/Slab etc. Complete works.

Prepared By Checked By Approved BY


Page 2 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks

BRICK MASONRY WORK: Providing and laying


brick masonary using first class chimney burnt
bricks (terai), with cement sand mortar 1:4
5 including scaffolding, curing, filling, cleaning and Cu.m. 65.59 13,305.90 872,707.49
racking out mortar joints,making ducts,recesses
where required including all materials,labour,lead
and lift as per drawing, specification. per
instruction of site Engineer.
Making, supply and fixing sesoned salwood 4"x3"
frame : Making, supply and fixing sesoned
6 salwood 4"x3" frame including centring and Cu.m. 0.97 289,787.06 280,254.88
shuttering all complete as per drawing,
specification.

Fixing Door Frame Shutter: Making and fixing 38


mm thick door frame with 25 mm salwood plank
7 Sq.m. 28.38 13,841.66 392,826.34
shutter for each door including supply of
materials, labor, centring and shuttering etc. all
complete as per drawing , specification.

Fixing 38mm glazed shutter incl. 4mm glass:


8 38mm glazed shutter incl. 4mm glass including Sq.m. 36.30 9,615.25 349,033.41
supply of materials, labor, making and fixing etc.
all complete as per drawing , specification.
MS GRILL: Grill of 20mmX3mm MS iron with two
coat of almunium paint for windows including
9 kg 720.27 142.70 102,786.48
supplying, fixing and fitting all complete as per
drawing, specification .
12.5 MM PLASTER ON WALL: 12.5 mm thick
cement sand plaster work (1:4) including supply
10 of materials, labor, mixing, levelling, curing & Sq.m. 487.03 343.49 167,288.54
scaffolding etc. all complete as per drawing,
specification.
20 MM PLASTER ON CEILING: 20 mm thick
plaster work on ceiling, beam and stair case with
cement sand ratio of (1:4) including supply of
11 Sq.m. 349.82 481.51 168,439.38
materials, labor, mixing, levelling, curing &
scaffolding etc. all complete as per drawing,
specification.
50mm thick P.C.C. in (1:2:4) with cement
punning (1:1) for floors approved quality of
12 cement, sand & crushed stone aggregare Sq.m. 274.95 793.32 218,123.06
including mixing,laying curing all complete work
in approved of site eng.
Prepared Enamel paint application: Prepared
Enamel paint application with one coat primer
13 Sq.m. 52.41 287.15 15,048.00
and 2 coats with enamel paints all complete as
per drawing, specification.

Prepared By Checked By Approved BY


Page 3 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks


MARBLE FLOORING 25 mm thick marble
flooring in 20 mm thick cement mortar (1:2) in
14 proper line and level including supplying, mixing , Sq.m. 43.23 3,585.86 155,005.78
placing, curing all complete as per drawing and
specification.
TILE FLOORING ON FLOOR: Supplying, Laying,
fitting and fixing Glazed tile flooring on floor with
15 Sq.m. 14.84 4,408.78 65,435.14
1:4 cement sand mortar joints all complete as
per drawing and specification.
TILE FLOORING ON WALL: Supplying, Laying,
fitting and fixing Glazed tile flooring on wall with
16 Sq.m. 41.34 3,304.92 136,615.55
1:4 cement sand mortar joints all complete as
per drawing and specification.
WEATHER COAT PAINT ON WALL: Coloring
with two coats of weather coat paint (Apex or
eqvt.) of approved color over one coat primer to
17 Sq.m. 96.00 286.95 27,547.01
give uniform coloring after rendering the surface
clean and moist as per specification and
instruction all complete

CEMENT PAINT ON WALL : Colouring with two


18 coat Plastic Emulsion paint on wall of approved Sq.m. 391.03 110.90 43,365.32
color over one coat primer to give uniform
colouring after rendering the surface all complete.
CEMENT PAINT ON Ceiling : Colouring with two
coat Plastic Emulsion paint on ceiling of
19 approved color over one coat primer to give Sq.m. 349.82 118.38 41,409.56
uniform colouring after rendering the surface all
complete.
Handrail: Supplying, fitting and fixing of hand rail
made of steenless steel bar Four line railing all
20 R.m. 13.65 2,339.35 31,920.47
complete work as per specified and instruction by
Engineer.

Handrail: Supplying, fitting and fixing of hand rail


21 R.m. 109.32 956.00 104,505.14
made of black iron pipe railing all complete work
as per specified and instruction by Engineer.

C Sanitary Works
1 WATER CLOSET: Providing and fixing in postion
white glazed earthen ware water Closets
European type Pan ISI with S or P trap, with or
without vent, and 10 ltr. Porcelain clay low level set 4.00 15,489.35 61,957.40
flushing cistern, accessoriesall complete as per
drawings, specification and instruction.

Prepared By Checked By Approved BY


Page 4 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks


2 20"x16"hand wash basin WASH BASIN SET:
Providing and fixing in postion white glazed
earthen ware single hole hand wash basins
(Hindustan/ Paryware or equivalent) with a pair of
CI standard brackets with nuts, 1/2" CP
approved pillar cocks, 1 1/4" CP waste couplin
with plug and CP chain and ring1 1/4" CP heavy
set 4.00 8,947.00 35,788.00
casted bottle trap with tail and pieces, 1/2" CP
approved angle cocks with 460mm long PVC
reinforced connector pipes with pipes both end
coupling joints etc, all complete with testing and
ready for operation drawing, specification and
approval of Engineer.

3 50mm' dia PVC pipe confirming Soil, Waste and


Rain Water Drainage Pipe Line (from Toilets to
the ducts then to the nearest manholes):
Providing and installating rigid PVC/GI pipe for
soil and waste disposal (tested to 4kg/cm2 for
PVC pipe) with high density metal tapering grip R.m. 40.00 266.11 10,644.40
bolt clamping, with approved clamps, cutting wall
and floor etc,. Making good to its original finish
etc. all complete with testing and ready for
operation as per drawings, specification .

4 75mm dia PVC pipe confirming Soil, Waste and


Rain Water Drainage Pipe Line (from Toilets to
the ducts then to the nearest manholes):
Providing and installating rigid PVC/GI pipe for
soil and waste disposal (tested to 4kg/cm2 for
PVC pipe) with high density metal tapering grip R.m. 39.00 407.30 15,884.70
bolt clamping, with approved clamps, cutting wall
and floor etc,. Making good to its original finish
etc. all complete with testing and ready for
operation as per drawings, specification .

5 FLOOR TRAP: Providing and fixing PVC floor


trap of 4"dia OD inlet and 3" dia OD outlet with 4"
dia stainless steel grating of heavy typeincluding
cutting and making good the walls and floors etc,. nos 8.00 660.56 5,284.48
all complete as per drawings, specification and
approval of Engineer.

Prepared By Checked By Approved BY


Page 5 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks


6 1'' dia. CVPC pipe SDR-11 for WATER SUPPLY:
Providing and fixing 1'' dia. CVPC pipe SDR-13.5
with necessary fittings clamps, chase cutting in
floor, walls etc. and making good the damages
R.m. 100.00 454.02 45,402.00
where ever required at its original finish all
complete with testing and ready for operation, as
per drawing, specification and approval of
Engineer.
7 3/4'' dia. CVPC pipe SDR-11 for WATER
SUPPLY: Providing and fixing 1'' dia. CVPC pipe
SDR-13.5 with necessary fittings clamps, chase
cutting in floor, walls etc. and making good the
R.m. 80.00 359.26 28,740.80
damages where ever required at its original finish
all complete with testing and ready for operation,
as per drawing, specification and approval of
Engineer.
8 1" CPVC Pipe Compact ball Valve plastic body
nos 3.00 1,080.08 3,240.24
9 3/4" CPVC Pipe Compact ball Valve plastic body
nos 2.00 1,080.08 2,160.16
10 SOAP DISH: Supplying fixing and fitting of fency
type Chromium plated soap dish including all nos 4.00 438.38 1,753.52
required accesorries.
11 LOOKING MIRROR: Providing and fixing in
position approved looking mirror sized 16"X20"
nos 4.00 1,217.39 4,869.56
including all required accesorriesas per
specification.
12 BIB COCK :1/2" dia CP fancy type bib cock
including all necessary materials as per drawing nos 8.00 1,043.05 8,344.40
specification and instruction.
13 Shower rose: Supplying and fixing fency type 3"
CP shower all complete including all required nos 4.00 1,155.29 4,621.16
accessories.
14 Towel rod: Supplying and fixing fency type18" CP
towel rod all complete including allrequired R.m. 4.00 632.50 2,530.00
accessories.

D Electrical Works
1 Supply and Fixing of 3/22 copper Wire for Light
Point Wiring in PVC Conduit Pipe and Supply R.m. 300.00 37.82 11,346.28
Power also.
2
Supply and Fixing of 1/2" HDPE Conduit Pipe for R.m. 60.00 26.45 1,587.00
light for holding wires and connecting properly.
3 Supply and Fixing of 3/4" HDPE Conduit Pipe for
Power Point wiring for holding wires and R.m. 90.00 38.53 3,467.25
connecting properly.

Prepared By Checked By Approved BY


Page 6 of 6

District Coordination Committee Office


Dang Nepal
`

Abstract of Cost of Building


Name of the Project :- Office Building Construction (addition first floor)
Project Locaation :- Dang, Nepal

S.N. Description Unit Quantity Rate Amount Remarks


4
Supply and Fixing of 7/22 copper Wire for Power
R.m. 200.00 64.55 12,909.39
Popint Wiring in HDPE Conduit Pipe from sub DB
to each room and Supply Power also.
5 Supply and Fixing of 1/18 copper Wire for neutral
Point of Power Point Wiring in HDPE Conduit R.m. 100.00 35.71 3,571.26
Pipe.
6 Supply and Fixing of 5/15 Amp Power Socket
nos 8.00 441.60 3,532.80
with light indicator .
7 Supplying and fixing of dome light. nos 20.00 539.93 10,798.50
8 Supply and fixing of 1 gang switch socket with
nos 14.00 357.65 5,007.10
metal box.
9 Supply and fixing of 4 gang switch socket with
nos 5.00 700.35 3,501.75
metal box.
10 Supply and fixing of 6 gang switch socket with
nos 7.00 700.35 4,902.45
metal box.
11 Supply sand Fixing of 1*40 Watt Tube Light in
Rooms with fixing accessories with chains nos 9.00 1,213.00 10,917.00
Properly.
12 Supply and fixing of Distribution Board in each
floor with each MCB's and one MCB to connect
further 1nd and 2nd Floor Distribution line for nos 1.00 31,211.00 31,211.00
every junction of required rating from 6- 32 AMP
as per needed.
13 Supply and fixing of 4"*6" PVC Junction Box
nos 15.00 339.25 5,088.75
where ever neceaary.
14 Supplying and fixing of ceiling fan with regulator
nos 9.00 3,309.00 29,781.00

Total Cost 6,622,084.04


13% Vat 860,870.93
Total Cost with 13% Vat 7,482,954.97
5% Contingencies 331,104.20
Grand Total 7,814,059.17

Prepared By Checked By Approved BY