525,777.41
3 Contingency @ 5% of A
1,367,021.26
4 VAT @ 13% of A
5
Grand Total 12,408,346.85
In Words: Rs One crore twenty four lakhs eighty three thousands three hundred and forty
six rupees and paisa eighty five`only.
Supplying and laying dry brick flat soiling with chimney made
4 bricks as instruction of site engineer, specification and drawing 159.75 Sq.m 1,085.85 173459.65
all materials and labour complete
6 RCC Work
13 Flooring work
Supplying and laying dry brick flat soiling with chimney made
13.3 bricks as instruction of site engineer, specification and drawing 16.29 Cum 1,085.85 17683.61 143 H16
all materials and labour complete
14 Plastering works
15 Painting Works
Colouring with two coat distemper paint with one coat primer
to give uniform colouring after rendering the surface all
15.1 469.67 Sq.m 287.25 134912.13
complete as per drawing, specification in approval of site
engineer
Providing 1.5 meter high chain link fence having mesh size
50mm x 50mm woven with SWG 10 heavy GI coated wire
with 50x50x5 mm ISA line post spaced at 2.5 meter center to
center, 50x50x5 mm corner and end post , 50x50x5 mm ISA
bracing post at every 15 meter straight run and at every change
in direction more than 15 degree and at end and corner post,
17 40x40x4 mm ISA top and bottom rail including installation of 696.23 Sqm 2,307.44 1606497.41
all post by excavating hole (300x300x600) and filling with
concrete 1:2:4 (1 cement : 2 sand : 4 stone aggregate 20 mm
and down grade), rails, stretching chain link fabric, fixing chain
link fabric securely in all post, top and bottom rail, etc., all
complete as per drawings, specification and instruction of the
Engineer.
Total 9,092,980.97
septik
manhole soakpit Toilet Office Parafit Ground
tank Total
S. N. Description Unit block block part part
Quantity
A CIVIL WORKS
Cutting of grass, taking of root & brocken of
uplecutting of raised soil & site leveling with all
1 complete job 40.13 68.44 94.38 5,356.93 5559.88
septik
manhole soakpit Toilet Office Parafit Ground
tank Total
S. N. Description Unit block block part part
Quantity
Flooring work
13 0.00
septik
manhole soakpit Toilet Office Parafit Ground
tank Total
S. N. Description Unit block block part part
Quantity
septik
manhole soakpit Toilet Office Parafit Ground
tank Total
S. N. Description Unit block block part part
Quantity
Total 6.00
6 Valves with all complete accessories.
GM Gate valve 32 mm dia. 1.00 1.00
ball valve20 mm dia. 1.00 1.00
Supplying and Fixing UPVC pipe with
fittings/ specials (Tees, elbows,
Unions ,Door Tee and Pipe clamp etc)
7
all complete set as per specification and
instruction. (Panchakanya ,
Prince,Supreme )
50 mm PVC pipe of 6 kg/cm2
10.00 10.00
10.00
75mm PVC pipe of 6 kg/cm2
12.00 12.00
26.00 26.00
38.00
110mm PVC pipe of 6 kg/cm2
0 15.00 15.00
15.00
32mm dia PPR pipe with fittings 1.00 500.00
20 mm dia PPR pipe with Fittings 1.00 500.00
-
Set 1,831.89 10,991.34
Rm 495.47 4,954.70
Rm 748.93 28,459.34
Rm 1268.91 19,033.65
Rm 1268.91 634,455.00
Rm 1268.91 634,455.00
Rm 395.08 17,778.60
Rm 516.47 27,372.91
Rm 579.26 48,657.84
108.94 m
. Total 1.69 Sq m
Dry brick laying around the soakpit, all complete a per design,
2 1.00 3.86 2.50 9.66 Cum
drawing, specification and instruction of site engineer.
15.70 Cu.m.
Brick Blast in side of wall including supply of filling materials,
5 watering, ramming etc. all complete as per drawing, specification in
approval of site engineer
1.00 7.22 2.50 18.06
18.06 Cu.m.
5 RCC Work
Plain cement Concrete (PCC) in 1:2:4 ratio (M15) for RCC works in
counter slab etc. with approved quality of cement and sand and stone
5.1 aggregate including mixing, laying, compacting and curing etc all
complete as per design, drawing, specification and instruction of site
engineer.
slab 1.00 4.40 0.10 0.44 area
0.44 Cum
For wall
Wall along the length of parafit 6.00 28.00 0.45 75.60
At parafit Tread 5.00 28.00 0.43 60.20
Total 75.60
Plain cement Concrete (PCC) in 1:3:6
ratio for foundations of the post with
supplying approved quality of cement,
sand and stone aggregate including
5
mixing, laying, copmacting and curing
etc all complete as per design, drawing,
specification and instruction of site
engineer
For wall
Wall along the length of parafit 6.00 28.00 0.45 0.08 6.05
At parafit Tread 5.00 28.00 0.66 0.038 3.51
Total 6.05
6 Brick Masonry
Brick masonry work (Chimney) in 1:6
C/S mortar with approved quality of
brick in perfect line, layer, plumb and
finishing including racking the joints and
curing the work for at least 7 days etc.all
complete as per design, drawing,
specification and instruction of site
engineer.
Up to plinth level
1st step
Wall along the length of parafit 1.00 28.00 0.23 0.87 5.60
2nd step
Wall along the length of parafit 1.00 28.00 0.23 1.17 7.53
3rd step
Wall along the length of parafit 1.00 28.00 0.23 1.47 9.4668
4th step
Wall along the length of parafit 1.00 28.00 0.23 1.77 11.3988
5th step
Wall along the length of parafit 1.00 28.00 0.23 2.07 13.3308
6th step
Wall along the length of parafit 1.00 28.00 0.23 2.07 13.3308
Total 60.66
12.5mm thick cement sand plaster in
(1:4) ratio on wall with good finish
including supplying of approved quality
of cement & sand, racking the joint,
7.0
Chiping the concerte surface, wetting of
surfaces & curing the work all complete
as per the design, drawing, specification
and instruction of site engineer.
Sq.m
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Sqm
Sqm
Budanillakantha Municipality
Office of Municipal Executive
Hattigauda, Budanilakantha
Bagmati province, Nepal
Quantity estimate of Toilet block
Project: Preparation of DER of football ground inside Budanilakantha school
Site: Budanilakantha school.
S. N. Description No Length Breadth Height Quantity
Site clearance before and after
completion of work including
desposing the remaining construction
1 1.00 40.13 40.13
materials & plants & making the site in
working condition all complete as per
instruction of site engineer.
Total 40.13
Earthwork in excavation in Boulder
mixed and hard soil in foundation,
trenches including timbering and
2 shoring & 30m Lead and 1.5 m. lift all
complete as per design, drawing,
specification and instruction of site
engineer.
For wall
Long wall 2.00 8.82 0.90 1.00 15.88
Short wall 3.00 4.10 0.90 1.00 11.07
Total 26.95
Earthwork backfilling by ramming &
watering at required places as per
3 instruction & disposing all surplus @60% OF ITEM NO 2 16.17
excavated materials within the site all
complete.
Total 16.17
Supplying and laying dry brick flat
soiling with chimney made bricks as
4 instruction of site engineer,
specification and drawing all materials
and labour complete
For wall
Long wall 2.00 8.82 0.90 15.88
Short wall 3.00 4.10 0.90 11.07
Total 26.95
Plain cement Concrete (PCC) in 1:3:6
ratio for foundations of the post with
supplying approved quality of cement,
sand and stone aggregate including
5
mixing, laying, copmacting and curing
etc all complete as per design,
drawing, specification and instruction
of site engineer
For wall
Long wall 2.00 8.82 0.90 0.08 1.27
Short wall 3.00 4.10 0.90 0.08 0.89
Total 2.16
6 Brick Masonry
Up to plinth level
1st step
Long wall 2.00 8.82 0.90 0.3 4.76
Short wall 3.00 4.10 0.90 0.3 3.32
2nd step 0.00
Long wall 2.00 8.82 0.6 0.3 3.18
Short wall 3.00 4.10 0.6 0.3 2.21
3rd step
Long wall 2.00 8.82 0.23 0.7 2.84004
Short wall 3.00 4.10 0.23 0.7 1.9803
Sub-total 18.29
Total 39.46
7 RCC Works
Beam
Long wall 2.00 8.82 0.23 0.3 1.22
Short wall 3.00 4.10 0.23 0.3 0.85
lintel Band 1.00 46.16 0.23 0.10 1.06
Sill Band 1.00 43.91 0.23 0.10 1.01
5 inch RCC slab 1.00 86.65 0.13 10.83
Total 14.97
TMT-Steel reinforcement bar of Fe
500 grade including straightening,
cleaning, cutting, bending, placing in
7.2 position and binding with annealed
binding wire all complete as per
design, drawing, specification and
instruction of site engineer.
For beam@1.5% 487.19
For slab @ 1% 850.25
Total 1337.44
Formwork, shuttering, centering with
waterproof ply wood and wooden post
necessary propping, scaffolding,
8 staging, supporting all complete in
perfect line and level as per drawing,
specification and instruction of site
engineer
Beam
Long wall 4.00 8.82 0.3 10.58
Short wall 6.00 4.10 0.3 7.38
For lintel band 1.00 92.32 0.10 9.23
For sill band 1.00 87.82 0.10 8.78
For Slab 1.00 86.65 86.65
Total 104.66
9.0 Aluminium door / Windows
Sq.m
Sqm
0.75
Cum
Cum
443.628
Cum
Cum
Cum
Cum
Cu.m
Cum
Cu.m
Kg
Sq.m
Sqm
Sqm
Sqm
1.35
Cum
Cu.m
CUm
Sqm
Sq.m
Sqm
Sqm
Sq.m
Budanillakantha Municipality
Office of Municipal Executive
Hattigauda, Budanilakantha
Bagmati province, Nepal
Quantity estimate of Office block
Project: Preparation of DER of football ground inside Budanilakantha school
Site: Budanilakantha school.
S. N. Description No Length Breadth Height Quantity Remarks
Site clearance before and after
completion of work including
desposing the remaining
1 construction materials & plants & 1.00 68.44 68.44 Sq.m
making the site in working
condition all complete as per
instruction of site engineer.
Total 68.44 Sqm
For wall
Long wall 2.00 14.30 0.90 1.00 25.74
Short wall 4.00 4.39 0.90 1.00 15.80
Total 41.54 Cum
Earthwork backfilling by ramming
& watering at required places as per
3 instruction & disposing all surplus @60% OF ITEM NO 2 24.92 Cum
excavated materials within the site
all complete.
Total 24.92 Cum
Supplying and laying dry brick flat
soiling with chimney made bricks as
instruction of site engineer,
4 specification and drawing all
materials and labour complete
For wall
Long wall 2.00 14.30 0.90 25.74
Short wall 4.00 4.39 0.90 15.80
Total 41.54 Cum
For wall
Long wall 2.00 14.30 0.90 0.08 2.06
Short wall 4.00 4.39 0.90 0.08 1.26
Total 3.32 Cum
6 Brick Masonry
Up to plinth level
1st step
Long wall 2.00 14.30 0.90 0.3 7.72
Short wall 4.00 4.39 0.90 0.3 4.74
2nd step 0.00
Long wall 2.00 14.30 0.6 0.3 5.15
Short wall 4.00 4.39 0.6 0.3 3.16
3rd step
Long wall 2.00 14.30 0.23 0.7 4.6046
Short wall 4.00 4.39 0.23 0.7 2.82716
Sub-total 28.20 Cum
Beam
Long wall 2.00 14.30 0.23 0.3 1.97
Short wall 4.00 4.39 0.23 0.3 1.21
lintel Band 1.00 46.16 0.23 0.10 1.06
Sill Band 1.00 42.39 0.23 0.10 0.97
5 inch RCC slab 1.00 86.65 0.13 10.83
Total 16.05 Cu.m
Beam
Long wall 4.00 14.30 0.3 17.16
Short wall 8.00 4.39 0.3 10.54
For lintel band 1.00 92.32 0.10 9.23
For sill band 1.00 84.78 0.10 8.48
For Slab 1.00 86.65 86.65
Total 104.36 Sq.m
9.0 Aluminium door / Windows