Detailed Estimate

PROJECT: RETAINING WALL CONSTRUCTION


Item
S.N. Description No Length Breadth Height Quantity Remarks
no.
1 SITE CLEARANCE
Site clearance work including
collection of all construction
1.1 debris, water, removal of bushes, 1 1.00 2.39 2.39 SQ.M.
tree and disposal to the designated
place as directed by Engineer.
2 EARTH WORKS IN CUTTING & FILLING
E/W in Excavation in all types of
soils in foundation including 15 m
2.1 hauling distance & 1.5m lift all
complete work as per specification
and instruction of site engineer.
Part A: footing 1 1.00 2.39 1.73 4.12
Total Cutting 4.12 cum.

Earthwork in Filling in floor and


foundation with proper ramming
with iron rammers in 0.15m. layers
2.2 after sprinkling with water and
consolidating to as per
specification and instruction
complete work.
Back filling 30% of Excavation 1.24

Total Backfilling 1.24 cum.

3 MASONARY WORKS
Provinding and Laying 5" stone
Soling in foundation and floor with
3.1 stones of approved size and quality
to level and line and compaction
all complete work as per site
instruction of Engineer.
Part A: footing
1 1.00 2.90 0.15 0.43
Sub Total 0.43 cum.

Prepared By: Checked By Approved By:-


Arjundhara Municipality
Office Of The Municipal Executive
Sanichare, jhapa
PROVINCE NO. 1, Nepal

Detailed Estimate

PROJECT: RETAINING WALL CONSTRUCTION


Item
S.N. Description No Length Breadth Height Quantity Remarks
no.
1 SITE CLEARANCE
Providing & laying stone masonary
in 1:4 C/S mortar in superstructure
in perfect line level finish
including wetting the bricks,
3.2 racking the joints and curing the
work for at least 7 days as per
specification, drawings &
instructions of the site engineer all
complete.
1 1.00 5.73 5.73
Sub Total for superstructure 5.73 cu.m.

4 CONCRETING WORKS
Providing and Laying Plain
Cement Concrete ( P.C.C.) in 1:2:4
in foundation with cement, sand
and aggregate including mixing,
4.1
laying, finishing to approved level,
line and dimensions and curing all
complete as per specification and
instruction of site Engineer.
footing portion 1 1.00 2.90 0.08 0.22

Sub Total for foundation PCC 0.22 Cum.


5 PIPEWORKS & GEOFILTER WORKS
supplying and fixing pvc pipe
5.1 100mm diameter @ 1500mm in 20.00 0.81
length and 450mm in height 16.20 R.M.
Suplying and binding geoexttile
filter material to bind the piupe in
perfect shape in perfect linelevel 20.00
as specified by site engineer
5.2 20.00 nos

Prepared By: Checked By Approved By:-