You are on page 1of 53

Kepilasgadhi Rural Municipality

Office of Rural Municipal Executive


Baksila, Khotang
Province No. 1, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Client : Kepilasgadhi Rural Municipality
Fiscal Year : 2079/80
SUMMMARISED ABSTRACT OF COST

Rate
S.N Description of Work Unit Quantity Amount Remarks
In Figures In Words
A PROVISIONAL WORKS
Insurance of work with third party liability and insurance of labour and Kepilasgadhi
1.0 PS 1.00 #REF! #REF!
technical staff which reimbrusement after submitting the relevant decument of insurance.
Carrying out different laboratory tests of construction materials like cement, rod, bricks,
2.0 sand, aggregate, filling materials, concrete cubes etc. during construction work as per PS 1.00 #REF! #REF!
specification and direction.
Preparation of as built Architectural, Structural, Sanitary & Electrical drawing as per
3.0 PS 1.00 #REF! #REF!
instruction all complete
-
B CIVIL WORKS -
Providing and installing the information board with 24 gauge metal sheet size of 4'*3' on
1.0 site fairly written information with appropriate stand as specified by site engineer should be Nos 1.00 9,200.00 9,200.00
place in clearly visible space.
2.0 Earth Works:- -
Earth Work in Excavation in foundation (All Type of soil) for lift up to 1.5 m. including
stacking the soil 0.90 m. minimum from the edge of foundation, filling the excavated place
Cu.m 0.00 704.77 -
& grub of soil in foundation trench & disposing the excess soil upto a lead of 10 m as per
instruction & specification all complete work
Earth Back Filling in foundation trenches in 15 c.m. layers with water sprinking & manual
Cu.m 488.75 -
compaction as per speciication and instruction all complete.
Earth work in filling:-Earth filling with soft soil in floors in layers of 15-15 cm thick by
Cu.m 684.82 -
sprinkling water and hand compaction.
3.0 Soling Works:- -
Stone filling (lead Upto 30m.) in trench with proper leveling as per drawing, specifications
Sq.m 5,603.83 -
and instructions of the Engineer.
4.0 Concreting Works:- -
Providing and laying Plain Cement Concrete of nominal mix 1:3:6 (1 cement : 3 sand : 6
coarse aggregate ) for leveling course in foundations, floors, Apron, pathway, drain, edge
wall etc in all level with river bed screened stone aggregate of approved size & quality
Cu.m 21,027.16 -
including dewatering, ,mixing, transporting, placing, compacting, curing, with all lead (upto
30) and lift, etc. all complete as per drawings, specifications and the instructions of the
Engineer.
Providing and laying Plain Cement Concrete of nominal mix 1:2:4 (1 cement : 2 sand : 4
coarse aggregate ) for leveling course in foundations, floors, Apron, pathway, drain, edge
wall etc in all level with river bed screened stone aggregate of approved size & quality
Cu.m 24,100.21 -
including dewatering, ,mixing, transporting, placing, compacting, curing, with all lead (upto
30) and lift, etc. all complete as per drawings, specifications and the instructions of the
Engineer.
Kepilasgadhi Rural Municipality
Office of Rural Municipal Executive
Baksila, Khotang
Province No. 1, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Client : Kepilasgadhi Rural Municipality
Fiscal Year : 2079/80
SUMMMARISED ABSTRACT OF COST

Rate
S.N Description of Work Unit Quantity Amount Remarks
In Figures In Words
Providing and laying machine mixed Plain Cement Concrete of nominal mix 1:1½:3 (1
cement : 1½ sand : 3 aggregate ) for Superstructure, Deck, Slab, columns, beams, Reinforced
concrete walls etc. with river bed screened stone aggregate of approved size & quality in
Cu.m 26,827.36 -
various locations and heights including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with all lead (upto 30) and
lift, etc. all complete as per drawings, specifications and the instructions of the Engineer.
5.0 Steel Reinforcement Works:- -
TMT Reinforcement bar (Fe 500) for RCC Works, tested including straightening, cleaning,
cutting, bending and fixing in position with 20 B.G. annealed binding wire as per drawing, Mton 158,680.00 -
specifications and instructions by site-engineer all complete work.
6.0 Brick Masonary Works:- -
Providing and laying first class chimney fired brick one or more brick thick wall in cement
mortar 1:6 (1 cement : 6 sand) in foundation and floor in perfect line and level including the
cost of single or multi stage scaffolding, soaking bricks, curing, raking joints, provision for -
recesses, openings, toothing etc., all complete as per drawing, specifications and instructions
of the Engineer.
Ground floor and foundation Cu.m 77.69 32,570.00 2,530,363.30
First Floor Cu.m 7.54 33,073.41 249,373.52
Second Floor Cu.m 7.74 33,778.19 261,443.20
Providing and laying first class chimney fired brick one or more brick thick wall in cement
mortar 1:4 (1 cement : 4 sand) in ground floor in perfect line and level including the cost of
single or multi stage scaffolding, soaking bricks, curing, raking joints, provision for recesses, -
openings, toothing etc., all complete as per drawing, specifications and instructions of the
Engineer.
Ground floor Cu.m 33,422.91 -
First Floor Cu.m 33,926.32 -
7.0 Shuttering /Form Works:- -
Formwork/ Centering & Shuttering with 18mm thick Plywood for all type of concrete works
necessary propping, scaffolding, staging, supporting inclusive wedging and cutting holes for
Sq.m 806.89 -
utilization work till the support is fully unyielding as per instructions & specifications
complete work .
8.0 Plaster/ Pointing Works:- -
12.5mm thick cement sand plaster (1:3) on Brick masonry in ceiling of good finish including
racking the joints, wetting the surface & curing the work as per specifications & direction all Sq.m 792.81 -
complete.
12.5mm thick cement sand plaster (1:4) on Brick masonry walls (inside/outside) of good
finish including racking the joints, wetting the surface & curing the work as per Sq.m 572.97 -
specifications & direction all complete.
20mm thick cement sand plaster (1:4) on Brick masonry walls (inside/outside) of good finish
including racking the joints, wetting the surface & curing the work as per specifications & Sq.m 792.81 -
direction all complete.
9.0 Floor Finish Works:- -
Kepilasgadhi Rural Municipality
Office of Rural Municipal Executive
Baksila, Khotang
Province No. 1, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Client : Kepilasgadhi Rural Municipality
Fiscal Year : 2079/80
SUMMMARISED ABSTRACT OF COST

Rate
S.N Description of Work Unit Quantity Amount Remarks
In Figures In Words
Providing and laying 38mm thick cement screed 1:4 (1 cement : 4 sand) above PCC
including surface preparation, cleaning of debris, applying cement slurry over hardened
Sq.m 1,101.75 -
PCC, finishing, curing, protection,etc., all complete as per drawings and instruction of the
Engineer.
3mm thick (1:1) Cement sand punning work on floor, walls etc including mixing, laying,
finishing to approved level, line and dimensions and curing as per instruction & specification Sq.m 397.49 -
all complete work.
Providing and fixing Porcelain glazed /non glazed floor tile in required line, level with
specified thickness approved brand in any colours, shades of any size with 1:4 cement sand Sq.m 4,352.62 -
mortar base as per drawing, specification and instruction of the Engineer.
Providing and fixing Porcelain glazed /non glazed wall tile in required line, level with
specified thickness approved brand in any colours, shades of any size with 1:4 cement sand Sq.m 3,844.73 -
mortar base as per drawing, specification and instruction of the Engineer.
Supplying, laying of fully fired clay tiles on roofing of approved size and quality as per
Sq.m 388.41 -
drawings,specifications and instructions of engineer.
10.0 Door & Windows Works:- -
Supplying and fixing in position well seasoned sal wood work for door, window and
ventillation frames including levelling, scafolding, all necessary hardware fitting etc. all Cu.m 328,392.63 -
complete finishing as per drawing, specification & instructions of the Engineer.
Supply, erection and fixing of Aluminum windows and ventilation of section size 90 mm
Sq.m 656.06 -
Natural colour thickness 1.1 mm , 4 mm clear glass with SS mosquito net all complete.
Supplying and fixing in position well seasoned sal wood work for door, window and
ventillation frames including levelling, scafolding, all necessary hardware fitting etc. all Sq.m 11,710.24 -
complete finishing as per drawing, specification & instructions of the Engineer.
Supplying and fixing in position 3 x 20mm Metal Grill including manufacturing,cutting,
Sq.m 2,415.00 -
welding, fabrication, fitting, painting with Aluminium paint, sand papering all complete.
11.0 Metal Works -
Supply, Providing, fabrication, fitting and fixing of stainless steel 50mm dia handrail pipe,in
between 25 mm dia ss pipe 3 line ,40 mm vertical post spaced at every 2.0m apart and 75 R.m 12,326.87 -
mm baluster pipe with 900 mm height all complete.
Providing and fixing mild steel angle (bracing) 50x50x5 mm, 16 gauge MS sheets and mild
steel sqaure pipes treated with one coats of primer and two coats of enamel paints, all Sq.m 9,200.00 -
complete as detailed in drawing, specification and instructions of the Engineer.
12.0 Painting Works:- -
Providing and applying two coat of weather coat on external wall along with one coat of
Sq.m 314.41 -
primer with approved color and proper finishing
Providing and applying two coat of Plastic Emulsion paint on inner wall and ceiling surface
Sq.m 399.70 -
along with one coat of primer with approved color and proper finishing.
Providing and applying two coats of enamel paint in the wooden and metal surfaces
including scrapping, washing the surface, applying one coat of approved quality primer,
Sq.m 357.93 -
surface preparation, scaffolding etc., all complete as per specifications and as approved by
the Engineer.
-
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


1.0 Earthwork
1.1 Earthwork in excavation, for ordinary soil, in Trenches,
Pits,foundation lift up to 1.5 m. etc. including dressing
of sides, ramming of bottom, and disposal of surplus
earth within 20m all complete
Foundation
F1 0.00
F2 0.00
Tie Beam
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL 0.00 Cum
1.2 Earthwork in 150mm layers using associated earth with

proper compaction all complete.


30% of excavated quantity 0.30 0.00 0.00
TOTAL 0.00 Cum
1.3 Earth filling work (earth transported from 10 km.
surrounding) in every 15-15 cm. layer with watering &
proper manual compaction as per drawings,
specifications and instructions of the Engineer.
Under Floors 0.00
Under Floors 0.00
Ramp 0.00
TOTAL 0.00 Cum
2.0 Soling Work.
Stone filling (lead Upto 30m.) in trench with proper
leveling as per drawing, specifications and instructions
of the Engineer.

0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


0.00
0.00
0.00
0.00
TOTAL 0.00 Cum
3.0 Plain Concrete Cement Works
3.1 Supplying mixing, placing, compacting & 1:3:6 cement
sand mortar mixes (M10) of plain cement concrete for
foundation bases & floors lead upto 30m excluding the
cost of formwork & reinforcement bars, as per drawing,
specification & instruction all complete.

0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL 0.00 Cum
3.2 Supplying mixing, placing, compacting & 1:2:4 cement
sand mortar mixes (M15) of plain cement concrete for
foundation bases & floors lead upto 30m excluding the
cost of formwork & reinforcement bars, as per drawing,
specification & instruction all complete.
0.00
0.00
0.00

0.00
0.00
0.00

0.00

0.00
0.00
0.00

0.00
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks

0.00
0.00

0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
TOTAL 0.00 Cum

3.3 Supplying mixing, placing, compacting & 1:1.5:3


cement sand mortar mixes (M20) of plain cement
concrete for foundation bases & floors lead upto 30m
excluding the cost of formwork & reinforcement bars,
as per drawing, specification & instruction all complete.

0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
TOTAL 0.00 Cum
4.0 Reinforcement Work
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


Supplying and Fixing steel reinforcement bar including
Bending, Binding of TMT reinforcement bar with 16
gauge black wire and placing in position as per drawing,
specification & instruction all complete .
TOTAL #REF! MT

5.0 Formwork
Centering and Shuttering of Plywood form work in
footings/slabs including propping, bracing and removal
of formwork all complete as per drawing, specification
& instruction.(Assume considering 6 times use of
formwork)

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00

0.00
0.00
0.00
0.00
0.00
TOTAL 0.00 Sqm
6.0 Brickwork
BRICK MASONARY WORK IN GROUND
FLOOR(1:6 C/S): Providing and laying first class
chimney fired brick one or more brick thick wall in
cement mortar 1:6 (1 cement : 6 sand) in foundation and
ground floor in perfect line and level including the cost
of single or multi stage scaffolding, soaking bricks,
curing, raking joints, provision for recesses, openings,
toothing etc., all complete as per drawing, specifications
and instructions of the Engineer.

Ground floor
along A-A 1.00 9.10 0.23 3.60 7.53
along B-B 1.00 15.80 0.23 3.60 13.08
along G-G 1.00 10.35 0.23 3.60 8.57
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


along H-H 1.00 3.10 0.23 3.60 2.57
along 1-1 1.00 22.20 0.23 3.60 18.38
along 2-2 1.00 9.10 0.23 3.60 7.53
along 3-3 1.00 2.96 0.23 3.60 2.45
along 6-6 1.00 2.55 0.23 3.60 2.11
along 7-7 1.00 4.55 0.23 3.60 3.77
along 8-8 1.00 22.20 0.23 3.60 18.38
deduct opening
w1 south -4.00 1.80 0.23 2.20 -3.64
w2 east and west -2.00 2.00 0.23 3.30 -3.04

TOTAL 77.69 Cum


BRICK MASONARY WORK IN FIRST FLOOR(1:6
C/S): Providing and laying first class chimney fired
brick one or more brick thick wall in cement mortar 1:6
(1 cement : 6 sand) in first floor in perfect line and level
including the cost of single or multi stage scaffolding,
soaking bricks, curing, raking joints, provision for
recesses, openings, toothing etc., all complete as per
drawing, specifications and instructions of the Engineer.
First Floor
along B-B 1.00 4.55 0.23 3.60 3.77
along H-H 1.00 4.55 0.23 3.60 3.77
TOTAL 7.54 Cum

BRICK MASONARY WORK IN SECOND


FLOOR(1:6 C/S): Providing and laying first class
chimney fired brick one or more brick thick wall in
cement mortar 1:6 (1 cement : 6 sand) in second floor in
perfect line and level including the cost of single or
multi stage scaffolding, soaking bricks, curing, raking
joints, provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and instructions
of the Engineer.

Top Floor

along B-B 1.00 4.55 0.23 3.20 3.35


along H-H 1.00 4.55 0.23 3.20 3.35
Triangular part
along B-B 0.50 4.55 0.23 1.00 0.52
along H-H 0.50 4.55 0.23 1.00 0.52
TOTAL 7.74 Cum
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


BRICK MASONARY WORK IN GROUND
FLOOR(1:4 C/S): Providing and laying first class
chimney fired brick one or more brick thick wall in
cement mortar 1:4 (1 cement : 4 sand) in ground floor in
perfect line and level including the cost of single or
multi stage scaffolding, soaking bricks, curing, raking
joints, provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and instructions
of the Engineer.
Partition Wall
Ground Floor
Ramp side 1.00 1.75 0.13 0.45 0.10
Along Grid C-C & D-D 2.00 3.65 0.13 2.63 2.40
Along Grid 2-2 & 3-3 2.00 9.60 0.13 2.63 6.30
Toilet Wall 2.00 1.14 0.13 2.88 0.82
1.00 2.14 0.13 2.88 0.80

Deduction
D1 -5.00 0.90 0.13 2.10 -1.18
D2 -2.00 0.75 0.13 2.10 -0.39
Staircase Opening -1.00 2.40 0.13 2.88 -0.86

Lintel & Sill Band


Along Grid B-B & E-E -4.00 3.65 0.13 0.10 -0.18
Along Grid 2-2 & 3-3 -4.00 9.60 0.13 0.10 -0.48
Toilet -4.00 1.14 0.13 0.10 -0.06
-2.00 2.14 0.13 0.10 -0.06
TOTAL 7.21 Cum
BRICK MASONARY WORK IN FIRST FLOOR(1:4
C/S): Providing and laying first class chimney fired
brick one or more brick thick wall in cement mortar 1:4
(1 cement : 4 sand) in first floor in perfect line and level
including the cost of single or multi stage scaffolding,
soaking bricks, curing, raking joints, provision for
recesses, openings, toothing etc., all complete as per
drawing, specifications and instructions of the Engineer.
First Floor
Along Grid B-B & E-E 2.00 3.65 0.13 2.63 2.40
Along Grid 2-2 & 3-3 2.00 9.60 0.13 2.63 6.30
Toilet 2.00 1.14 0.13 2.88 0.82
1.00 2.14 0.13 2.88 0.80

Deduction
D1 -2.00 0.90 0.13 2.10 -0.47
D2 -2.00 0.75 0.13 2.10 -0.39
D3 -2.00 1.20 0.13 2.10 -0.63
Staircase Opening -1.00 2.40 0.13 2.88 -0.86

Lintel & Sill Band


Along Grid B-B & E-E -4.00 3.65 0.13 0.10 -0.18
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


Along Grid 2-2 & 3-3 -4.00 9.60 0.13 0.10 -0.48
Toilet -4.00 1.14 0.13 0.10 -0.06
-2.00 2.14 0.13 0.10 -0.06
TOTAL 7.19 Cum
7.0 Plaster Works
Providing and laying 20 mm thick plastering on wall
with 1:4 Cement sand mortar including scaffolding all
complete as per drawing, specification & instruction.
(External)
Brick Cladding
250*250 Size upto 1st floor 20.00 6.10 0.75 91.50
250*250 Size upto 2nd floor 2.00 8.98 0.75 13.46

Ground Floor
Along Grid B-B 1.00 10.10 3.23 32.57
Along Grid E-E 1.00 9.60 3.23 30.96
Along Grid C-C & D-D 2.00 3.65 2.88 20.99
Along Grid 1-1 & 4-4 2.00 9.50 2.88 54.63

Deduction
W1 -4.00 1.80 1.50 -10.80
W2 -1.00 1.20 1.50 -1.80
W3 -1.00 1.20 1.00 -1.20
V -1.00 0.60 0.45 -0.27
DW -0.50 2.40 2.10 -2.52

First Floor
Along Grid B-B 1.00 10.10 2.88 29.04
Along Grid E-E 1.00 9.60 2.88 27.60
Along Grid C-C & D-D 2.00 3.65 2.88 20.99
Along Grid 1-1 & 4-4 2.00 9.50 2.88 54.63
Parapet Wall 2.00 1.80 0.90 3.24
1.00 2.55 0.90 2.30
Deduction
W1 -4.00 1.80 1.50 -10.80
W2 -1.00 1.20 1.50 -1.80
W3 -1.00 1.20 1.00 -1.20
V -1.00 0.60 0.45 -0.27
DW -0.50 2.40 2.10 -2.52

Second Floor
Along Grid C-C & D-D 1.00 3.65 2.63 9.58
Along Grid 1-1 & 2-2 2.00 2.40 2.63 12.60
Parapet Wall 1.00 45.39 0.90 40.85

Deduction
W3 -0.50 1.20 1.00 -0.60
D1 -0.50 0.90 2.10 -0.95

Top Floor
Parapet Wall 1.00 14.90 0.90 13.41
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


TOTAL 423.62 Sqm
Providing and laying 12.5 mm thick cement plaster over
concrete surface with 1:4 cement sand mortar including
scaffolding all complete as per drawing, specification &
instruction.
Ground Floor
Ramp 1.00 1.75 0.45 0.79
Along Grid B-B 1.00 10.96 2.88 31.51
Along Grid E-E 1.00 10.96 2.88 31.51
Along Grid C-C & D-D 2.00 3.65 2.88 20.99
Along Grid 1-1 & 4-4 2.00 11.10 2.88 63.83

Deduction
W1 -4.00 1.80 1.50 -10.80
W2 -1.00 1.20 1.50 -1.80
W3 -1.00 1.20 1.00 -1.20
V -1.00 0.60 0.45 -0.27
DW -0.50 2.40 2.10 -2.52

First Floor
Along Grid B-B 1.00 10.96 2.88 31.51
Along Grid E-E 1.00 10.96 2.88 31.51
Along Grid C-C & D-D 2.00 3.65 2.88 20.99
Along Grid 1-1 & 4-4 2.00 11.10 2.88 63.83
Column 2.00 2.88 1.20 6.90
Beam 2.00 1.80 0.75 2.70
1.00 2.55 0.75 1.91
Parapet Wall 2.00 1.80 0.90 3.24
1.00 2.55 0.90 2.30
Parapet Wall Top 2.00 1.80 0.25 0.90
1.00 2.55 0.25 0.64
Deduction
W1 -4.00 1.80 1.50 -10.80
W2 -1.00 1.20 1.50 -1.80
W3 -1.00 1.20 1.00 -1.20
V -1.00 0.60 0.45 -0.27
DW -0.50 2.40 2.10 -2.52

Second Floor
Along Grid C-C & D-D 1.00 3.65 2.88 10.49
Along Grid 1-1 & 2-2 2.00 2.40 2.88 13.80
Parapet Wall 1.00 44.31 0.90 39.88
Parapet Wall Top 1.00 44.31 0.25 11.08
Deduction
W3 -0.50 1.20 1.00 -0.60
D1 -0.50 0.90 2.10 -0.95

Top Floor
Parapet Wall 1.00 12.90 0.90 11.61
Inclined Slab
First Floor 1.00 52.59 0.75 39.44
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


Second Floor 1.00 52.59 0.75 39.44
Third Floor 1.00 19.70 0.75 14.78
Perimeter for Slab at First floor and Second Floor 2.00 52.59 0.10 10.52
Perimeter for inclined slab in third floor 1.00 19.70 0.10 1.97
TOTAL 473.34 Sqm
8.0 Painting
Providing and applying two coat of weather coat on
external wall along with one coat of primer with
approved color and proper finishing
20mm plaster Quantity 1.00 423.62
TOTAL 423.62 Sqm
Providing and applying two coat of Plastic Emulsion
paint on inner wall and ceiling surface along with one
coat of primer with approved color and proper finishing
12.5 mm plaster quantity 1.00 473.34
Slab Area
Ground Floor Slab 1.00 12.20 12.30 150.06
1.00 1.80 4.30 7.72
First Floor Slab 1.00 12.20 12.30 150.06
1.00 1.80 4.30 7.72
Second Floor Slab 1.00 5.55 4.30 23.87
Perimeter for slab 0.00
4.00 12.20 0.15 7.32
4.00 12.30 0.15 7.38
2.00 5.55 0.15 1.67
4.00 4.30 0.15 2.58
TOTAL 831.72 Sqm
Providing and applying two coats of enamel paint in the
wooden and metal surfaces including scrapping,
washing the surface, applying one coat of approved
quality primer, surface preparation, scaffolding etc., all
complete as per specifications and as approved by the
Engineer.
DW 2.00 2.40 2.10 10.08
D1 8.00 0.90 2.10 15.12
D2 4.00 0.75 2.10 6.30
D3 2.00 1.20 2.10 5.04
TOTAL 36.54 Sqm
9.0 Flooring Works
Providing & laying 38 mm thick screeding on floor with
1:2:4 cement sand mortar all complete as per drawing,
specification & instruction.
Slab Area
Ramp 1.00 1.79 1.20 2.14
Ground Floor Slab 1.00 12.20 12.30 150.06
1.00 1.80 4.30 7.72
First Floor Slab 1.00 12.20 12.30 150.06
1.00 1.80 4.30 7.72
Second Floor Slab 1.00 5.55 4.30 23.87
Deduct Beam Area
Along Grid A-A -2.00 2.45 0.25 -1.23
Along Grid B-B, C-C, D-D & E -8.00 11.10 0.25 -22.20
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


Along Grid 1-1 & 4-4 -4.00 11.00 0.25 -11.00
Along Grid 2-2 & 3-3 -4.00 11.10 0.25 -11.10
Along Grid C-C & D-D -4.00 3.10 0.25 -3.10
Along Grid 1-1 & 2-2 -4.00 4.35 0.25 -4.35
Parapet Wall -1.00 44.31 0.25 -11.08
TOTAL 277.51 Sqm

Providing & Laying 3 mm thick cement punning with


1:1 cement sand mortar all complete as per drawing,
specification & instruction.
Screeding Area 277.51
Deduct Bathroom floor Area -9.18
TOTAL 268.33 Sqm
Providing and fixing Porcelain glazed /non glazed floor
tile in required line, level with specified thickness
approved brand in any colours, shades of any size with
1:4 cement sand mortar base as per drawing,
specification and instruction of the Engineer.
Floor Tiles
GF 2.00 1.14 2.02 4.59
FF 2.00 1.14 2.02 4.59
TOTAL 9.18 Sqm

Providing and fixing Porcelain glazed /non glazed wall


tile in required line, level with specified thickness
approved brand in any colours, shades of any size with
1:4 cement sand mortar base as per drawing,
specification and instruction of the Engineer.
GF 2.00 6.31 2.10 26.49
FF 3.00 6.31 3.10 58.65
Deduct
D2 -1.00 0.75 2.10 -1.58

TOTAL 83.56 Sqm


Supplying, laying of fully fired clay tiles on roofing of
approved size and quality as per drawings,specifications
and instructions of engineer.
Inclined Slab
First Floor 1.00 52.59 0.75 39.44
Second Floor 1.00 52.59 0.75 39.44
Third Floor 1.00 19.70 0.75 14.78
TOTAL 93.66 Sqm
10.0 Door and Windows
10.1 Supplying and fixing in position well seasoned sal wood
work for door, window and ventillation frames
including levelling, scafolding, all necessary hardware
fitting etc. all complete finishing as per drawing,
specification & instructions of the Engineer.
DW 2.00 6.60 0.10 0.08 0.10
D1 8.00 5.10 0.10 0.08 0.31
D2 4.00 4.95 0.10 0.08 0.15
Kepilasgadhi Rural Municipality
Office of Municipal Executive
Baksila, Khotang
Province No. 01, Nepal

Project : Construction of Covered Hall at Kepilasgadhi Rural Municipality


Site: Kepilasgadhi, Khotang

Quantity Estimate of Main Building

S.N. Description of Work No L(m) B(m) H(m) Quantity Unit Remarks


D3 2.00 5.40 0.10 0.08 0.08
TOTAL 0.64 Cum
10.2 38 x100mm thick sal wood frame with 12 mm thick
commercial plywood paneled & one side 4 mm thick
Teak plywood paneled shutter fixing with all complete.
DW 2.00 2.40 2.10 10.08
D1 8.00 0.90 2.10 15.12
D2 4.00 0.75 2.10 6.30
D3 2.00 1.20 2.10 5.04
TOTAL 36.54 Sqm
10.3 Supply, erection and fixing of Aluminum windows and
ventilation of section size 90 mm Natural colour
thickness 1.1 mm , 4 mm clear glass with SS mosquito
net all complete.
W1 16.00 1.80 1.50 43.20
W2 2.00 1.20 1.50 3.60
W3 3.00 1.20 1.00 3.60
V 4.00 0.60 1.50 3.60
TOTAL 54.00 Sqm
10.4 Supplying and fixing in position 3 x 20mm Metal Grill
including manufacturing,cutting, welding, fabrication,
fitting, painting with Aluminium paint, sand papering
all complete.
W1 16.00 1.80 1.50 43.20
W2 2.00 1.20 1.50 3.60
W3 3.00 1.20 1.00 3.60
V 4.00 0.60 1.50 3.60
TOTAL 54.00 Sqm
11.0 Railing
11.1 Supply, Providing, fabrication, fitting and fixing of
stainless steel 50mm dia handrail pipe,in between 25
mm dia ss pipe 3 line ,40 mm vertical post spaced at 3.00 5.61 16.83
every 2.0m apart and 75 mm baluster pipe with 900
mm height all complete at staircase.
TOTAL 16.83 Rm
A - SITE PREPARATION WORK

S.N Norms Description Unit User Rate Contractors


Rate

1.01 DUDBC-A3 Cutting of grass, taking out of root & broken of raised soil & site Sqm. 19.55 22.48
leveling with all complete as per specifications and instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.230 Nos. 850.00 195.50
Rate analysis for : 10.00 Sqm. Total 195.50
15 % Contractor overhead 29.32
Grand Total 224.82

1.02 DUDBC- A4 Surface dressing work with cutting of raised soil & filling the ditches sqm. 8.50 9.77
Resources etc. all complete as per specifications and instructions
Level/Type Quantityof the Engineer.
Unit Rate Amount Remarks
Labour Unskilled 0.010 Nos. 850.00 8.50
Rate analysis for : 1.00 Sqm. Total 8.50
15 % Contractor overhead 1.27
Grand Total 9.77

B - EARTH & SAND WORK

2.01 DUDBC-B1 Earth work excavation in foundation in Soft clay & silty soil including Cum. 612.85 704.77
(2-1) lead upto 10 mtr. & lift 1.5 mtr. as per drawings, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.700 Nos. 850.00 595.00
Materials T & P 3 % of labour 17.85
Rate analysis for : 1.00 Cum. Total 612.85
15 % Contractor overhead 91.92
Grand Total 704.77

2.02 DUDBC- B1 Earth work excavation in foundation in hard clay & soil mixed with soft Cum. 700.40 805.46
(2-2)
murram stone (size upto 30 cm.) including lead upto 10 mtr. & lift 1.5

mtr. as per drawings, specifications and instructions of the Engineer.


Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.800 Nos. 850.00 680.00
Materials T & P 3 % of labour 20.40
Rate analysis for : 1.00 Cum. Total 700.40
15 % Contractor overhead 105.06
Grand Total 805.46

2.03 DUDBC- B2 Earth filling work in every 15-15 cm. layer with watering including Cum. 425.00 488.75
(2-25A) lead upto 10mtr. & proper manual compaction as per drawings,
specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.500 Nos. 850.00 425.00
Rate analysis for : 1.00 Cum. Total 425.00
15 % Contractor overhead 63.75
Grand Total 488.75
S.N Norms Description Unit User Rate Contractors
Rate
2.04 DUDBC- B2 Earth filling work (earth transported from 10 km. surrounding) Cum. 595.50 684.82
(2-25A) in every 15-15 cm. layer with watering & proper manual
compaction as per drawings, specifications and instructions of
the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.500 Nos. 850.00 425.00
Materials Mud 1.500 Cum. 112.00 168.00
Water 5.000 Ltr. 0.50 2.50
Rate analysis for : 1.00 Cum. Total 595.50
15 % Contractor overhead 89.32
Grand Total 684.82

C - MASONRY WORK

3.01 DUDBC- BRICK MASONARY WORK IN GROUND FLOOR(1:3 C/S): Cum. 29,853.01 34,330.96
C2(5-1-B1 & Providing and laying first class chimney fired brick one or more brick
5-2A)
thick wall in cement mortar 1:3 (1 cement : 3 sand) in ground floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled ( for Scaffolding ) 0.200 Nos. 850.00 170.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.130 M.T. 27,752.80 3,607.86
Sand 0.270 Cum. 5,296.50 1,430.05
Water 150.000 Ltr. 0.50 75.00
Scaffolding material 3 % of 5.10
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 29,853.01
15 % Contractor overhead 4,477.95
Grand Total 34,330.96

3.02 DUDBC- BRICK MASONARY WORK IN FIRST FLOOR(1:3 C/S): Providing Cum. 30,290.76 34,834.37
C2(5-1-B1 & and laying first class chimney fired brick one or more brick thick wall
5-2B)
in cement mortar 1:3 (1 cement : 3 sand) in first floor in perfect line and
level including the cost of single or multi stage scaffolding, soaking
bricks, curing, raking joints, provision for recesses, openings, toothing
etc., all complete as per drawing, specifications and instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.130 M.T. 27,752.80 3,607.86
Sand 0.270 Cum. 5,296.50 1,430.05
Water 150.000 Ltr. 0.50 75.00
Materials

S.N Norms Description Unit User Rate Contractors


Rate
Scaffolding material 3 % of 17.85
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 30,290.76
15 % Contractor overhead 4,543.61
Grand Total 34,834.37

3.03 DUDBC- BRICK MASONARY WORK IN SECOND FLOOR(1:3 C/S): Cum. 30,903.61 35,539.15
C2(5-1-B1 & Providing and laying first class chimney fired brick one or more brick
5-2B) thick wall in cement mortar 1:3 (1 cement : 3 sand) in second floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 1.400 Nos. 850.00 1,190.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.130 M.T. 27,752.80 3,607.86
Sand 0.270 Cum. 5,296.50 1,430.05
Water 150.000 Ltr. 0.50 75.00
Scaffolding material 3 % of 35.70
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 30,903.61
15 % Contractor overhead 4,635.54
Grand Total 35,539.15

3.04 DUDBC- BRICK MASONARY WORK IN GROUND FLOOR(1:4 C/S): Cum. 29,063.40 33,422.91
C2( 5-1-B2 & Providing and laying first class chimney fired brick one or more brick
5-2A)
thick wall in cement mortar 1:4 (1 cement : 4 sand) in ground floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled ( for Scaffolding ) 0.200 Nos. 850.00 170.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.100 M.T. 27,752.80 2,775.28
Sand 0.280 Cum. 5,296.50 1,483.02
Water 130.000 Ltr. 0.50 65.00
Scaffolding material 3 % of 5.10
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 29,063.40
15 % Contractor overhead 4,359.51
Grand Total 33,422.91
S.N Norms Description Unit User Rate Contractors
Rate
3.05 DUDBC- BRICK MASONARY WORK IN FIRST FLOOR(1:4 C/S): Providing Cum. 29,501.15 33,926.32
C25-1-B2 & and laying first class chimney fired brick one or more brick thick wall
5-2B) in cement mortar 1:4 (1 cement : 4 sand) in first floor in perfect line and
level including the cost of single or multi stage scaffolding, soaking
bricks, curing, raking joints, provision for recesses, openings, toothing
etc., all complete as per drawing, specifications and instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.100 M.T. 27,752.80 2,775.28
Sand 0.280 Cum. 5,296.50 1,483.02
Water 130.000 Ltr. 0.50 65.00
Scaffolding material 3 % of 17.85
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 29,501.15
15 % Contractor overhead 4,425.17
Grand Total 33,926.32

3.06 DUDBC- BRICK MASONARY WORK IN SECOND FLOOR(1:4 C/S): Cum. 30,114.00 34,631.10
C2(5-1-B2 & Providing and laying first class chimney fired brick one or more brick
5-2B) thick wall in cement mortar 1:4 (1 cement : 4 sand) in second floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 1.400 Nos. 850.00 1,190.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.100 M.T. 27,752.80 2,775.28
Sand 0.280 Cum. 5,296.50 1,483.02
Water 130.000 Ltr. 0.50 65.00
Scaffolding material 3 % of 35.70
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 30,114.00
15 % Contractor overhead 4,517.10
Grand Total 34,631.10

3.07 DUDBC- BRICK MASONARY WORK IN GROUND FLOOR(1:6 C/S): Cum. 28,321.74 32,570.00
C2(5-1-B3 & Providing and laying first class chimney fired brick one or more brick
5-2A)
thick wall in cement mortar 1:6 (1 cement : 6 sand) in ground floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.5000 Nos. 1,130.00 1,695.00
Unskilled 2.2000 Nos. 850.00 1,870.00
Unskilled ( for Scaffolding ) 0.2000 Nos. 850.00 170.00
S.N Norms Description Unit User Rate Contractors
Rate
Materials Brick chimney 560.0000 Nos. 37.50 21,000.00
Cement 0.0700 M.T. 27,752.80 1,942.69
Sand 0.3000 Cum. 5,296.50 1,588.95
Water 100.0000 Ltr. 0.50 50.00
3 % of 5.10
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 28,321.74
15 % Contractor overhead 4,248.26
Grand Total 32,570.00

3.08 DUDBC- BRICK MASONARY WORK IN FIRST FLOOR(1:6 C/S): Providing Cum. 28,759.49 33,073.41
C2(5-1-B3 & and laying first class chimney fired brick one or more brick thick wall
5-2B) in cement mortar 1:6 (1 cement : 6 sand) in first floor in perfect line and
level including the cost of single or multi stage scaffolding, soaking
bricks, curing, raking joints, provision for recesses, openings, toothing
etc., all complete as per drawing, specifications and instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.070 M.T. 27,752.80 1,942.69
Sand 0.300 Cum. 5,296.50 1,588.95
Water 100.000 Ltr. 0.50 50.00
Scaffolding material 3 % of 17.85
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 28,759.49
15 % Contractor overhead 4,313.92
Grand Total 33,073.41

3.09 DUDBC- BRICK MASONARY WORK IN SECOND FLOOR(1:6 C/S): Cum. 29,372.34 33,778.19
C2( 5-1-B3 & Providing and laying first class chimney fired brick one or more brick
5-2B) thick wall in cement mortar 1:6 (1 cement : 6 sand) in second floor in
perfect line and level including the cost of single or multi stage
scaffolding, soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 2.200 Nos. 850.00 1,870.00
Unskilled 1.400 Nos. 850.00 1,190.00
Materials Brick chimney 560.000 Nos. 37.50 21,000.00
Cement 0.070 M.T. 27,752.80 1,942.69
Sand 0.300 Cum. 5,296.50 1,588.95
Water 100.000 Ltr. 0.50 50.00
Scaffolding material 3 % of 35.70
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 29,372.34
15 % Contractor overhead 4,405.85
Grand Total 33,778.19

3.10 DUDBC-C5 Brick Masonary Work for additional each story Cum. 612.85 704.77
S.N Norms Description Unit User Rate Contractors
Rate
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.700 Nos. 850.00 595.00
material Scaffolding material 3 % of 17.85
Scaffolding
labour
Rate analysis for : 1.00 Cum. Total 612.85
15 % Contractor overhead 91.92
Grand Total 704.77

3.12 DUDBC- R.R. MASONARY WORK (1:3 C/S): Providing and laying random Cum. 16,526.64 19,005.63
C6( 6-1-1A) rubble Stone masonry Works in cement mortar (1:3 ) including
scaffolding, curing, preparation of mortar etc all complete as per
drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 5.000 Nos. 850.00 4,250.00
Materials Cement 0.194 M.T. 27,752.80 5,384.04
Sand 0.420 Cum. 5,296.50 2,224.53
Stone block 1.000 Cum. 2,648.25 2,648.25
Stone bond 0.100 Cum. 2,648.25 264.82
Water 120.000 Ltr. 0.50 60.00
Rate analysis for : 1.00 Cum. Total 16,526.64
15 % Contractor overhead 2,478.99
Grand Total 19,005.63

3.13 DUDBC- R.R. MASONARY WORK (1:4 C/S): Providing and laying random Cum. 15,704.18 18,059.80
C6( 6-1-1B) rubble Stone masonry Works in cement mortar (1:4 ) including
scaffolding, curing, preparation of mortar etc all complete as per
drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 5.000 Nos. 850.00 4,250.00
Materials Cement 0.159 M.T. 27,752.80 4,412.69
Sand 0.450 Cum. 5,296.50 2,383.42
Stone block 1.000 Cum. 2,648.25 2,648.25
Stone bond 0.100 Cum. 2,648.25 264.82
Water 100.000 Ltr. 0.50 50.00
Rate analysis for : 1.00 Cum. Total 15,704.18
15 % Contractor overhead 2,355.62
Grand Total 18,059.80

3.14 DUDBC- R.R. MASONARY WORK (1:6 C/S): Providing and laying random Cum. 14,324.21 16,472.84
C6( 6-1-1C) rubble Stone masonry Works in cement mortar (1:6) including
scaffolding, curing, preparation of mortar etc all complete as per
drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 5.000 Nos. 850.00 4,250.00
Materials Cement 0.106 M.T. 27,752.80 2,941.79
Sand 0.470 Cum. 5,296.50 2,489.35
Stone block 1.000 Cum. 2,648.25 2,648.25
Stone bond 0.100 Cum. 2,648.25 264.82
Water 70.000 Ltr. 0.50 35.00
Rate analysis for : 1.00 Cum. Total 14,324.21
S.N Norms Description Unit User Rate Contractors
Rate analysis for : 1.00 Cum. Rate
15 % Contractor overhead 2,148.63
Grand Total 16,472.84

3.15 DUDBC- ASLAR MASONARY WORK (1:4 C/S): Providing and laying Aslar Cum. 15,704.18 18,059.80
C6( 6-1-1B) (Crushed stone) stone masonry work in cement sand (1:4) mortar
including scaffolding, curing, preparation of mortar etc all complete as
per drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 5.000 Nos. 850.00 4,250.00
Materials Cement 0.159 M.T. 27,752.80 4,412.69
Sand 0.450 Cum. 5,296.50 2,383.42
Stone bond 1.100 Cum. 2,648.25 2,913.07
Water 100.000 Ltr. 0.50 50.00
Rate analysis for : 1.00 Cum. Total 15,704.18
15 % Contractor overhead 2,355.62
Grand Total 18,059.80

3.16 DUDBC- ASLAR MASONARY WORK (1:6 C/S): Providing and laying Aslar Cum. 14,324.21 16,472.84
C6( 6-1-1C) (Crused stone) stone masonry work in cement sand (1:6) mortar
including scaffolding, curing, preparation of mortar etc all complete as
per drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00 1.50
Unskilled 5.000 Nos. 850.00 4,250.00 3.00
Materials Cement 0.106 M.T. 27,752.80 2,941.79 0.04
Sand 0.470 Cum. 5,296.50 2,489.35 0.42
Stone bond 1.100 Cum. 2,648.25 2,913.07 1.10
Water 70.000 Ltr. 0.50 35.00
Rate analysis for : 1.00 Cum. Total 14,324.21
15 % Contractor overhead 2,148.63
Grand Total 16,472.84

3.17 DUDBC- ASLAR MASONARY WORK FOR DRY WALL : Providing and Cum. 5,353.04 6,155.99
C6( 6-2-1) laying Aslar (Crused stone) stone masonry for dry wall as per drawing,
specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 2.000 Nos. 850.00 1,700.00
Materials Stone block 1.000 Cum. 2,293.69 2,293.68
Stone bond 0.100 Cum. 2,293.69 229.36
Rate analysis for : 1.00 Cum. Total 5,353.04
15 % Contractor overhead 802.95
Grand Total 6,155.99

3.18 DUDBC- STONE FILLING IN TRENCH WITH PROPER LEVELLING: Stone Cum. 4,872.90 5,603.83
C10( 6-5) filling (lead Upto 30m.) in trench with proper leveling as per drawing,
specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 1.50 Nos. 1,130.00 1,695.00
Materials Stone block 1.00 Cum. 2,648.25 2,648.25
Stone bond 0.20 Cum. 2,648.25 529.65
Rate analysis for : 1.00 Cum. Total 4,872.90
15 % Contractor overhead 730.93
S.N Norms Rate analysis for : 1.00 Cum.Description Unit User Rate Contractors
Rate
Grand Total 5,603.83

D - CEMENT CONCRETE WORK

4.01 DUDBC- PLAIN CEMENT CONCRETE M10(1:3:6) WITH SCREENED Cum. 18,284.49 21,027.16
D1(7-2C) AGGREGATE: Providing and laying Plain Cement Concrete of
nominal mix 1:3:6 (1 cement : 3 sand : 6 coarse aggregate ) for leveling
course in foundations, floors, Apron, pathway, drain, edge wall etc in
all level with river bed screened stone aggregate of approved size &
quality including dewatering, ,mixing, transporting, placing,
compacting, curing, with all lead (upto 30) and lift, etc. all complete as
per drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 4.000 Nos. 850.00 3,400.00
Materials Cement 0.220 M.T. 29,877.20 6,572.98
Aggrigate 40 mm-River bed 0.650 Cum. 5,204.69 3,383.04
Aggrigate 20 mm-River bed 0.240 Cum. 5,204.69 1,249.12
Sand 0.470 Cum. 5,296.50 2,489.35
Water 120.000 Ltr. 0.50 60.00
Rate analysis for : 1.00 Cum. Total 18,284.49
15 % Contractor overhead 2,742.67
Grand Total 21,027.16

4.02 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WITH SCREENED Cum. 20,956.71 24,100.21
D1(7-2D) AGGREGATE FOR FOUNDATION: Providing and laying Plain
Cement Concrete of nominal mix 1:2:4 (1 cement : 2 sand : 4 coarse
aggregate ) for leveling course in foundations, floors, Apron, pathway,
drain, edge wall etc in all level with river bed screened stone aggregate
of approved size & quality including dewatering, ,mixing, transporting,
placing, compacting, curing, with all lead (upto 30) and lift, etc. all
complete as per drawings, specifications and the instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 4.000 Nos. 850.00 3,400.00
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-River bed 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mm-River bed 0.220 Cum. 5,204.69 1,145.03
Aggrigate 10 mm-River bed 0.110 Cum. 5,296.50 582.61
Sand 0.445 Cum. 5,296.50 2,356.94
Water 150.000 Ltr. 0.50 75.00
Rate analysis for : 1.00 Cum. Total 20,956.71
15 % Contractor overhead 3,143.50
Grand Total 24,100.21

4.03 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WITH SCREENED Cum. 23,280.71 26,772.81
D2(7-4A) AGGREGATE FOR SUPERSTRUCTURE: Providing and laying
Reinforced Cement Concrete of nominal mix 1:2:4 (1 cement : 2 sand :
4 aggregate ) for Superstructure, Deck, Slab, columns, beams etc. with
river bed screened stone aggregate of approved size & quality in
various locations and heights including transportation of concrete to site
of placing, , compaction,finished to required line & level, protection &
curing, with all lead (upto 30) and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
S.N Norms Description Unit User Rate Contractors
Rate
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-River bed 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mm-River bed 0.220 Cum. 5,204.69 1,145.03
Aggrigate 10 mm-River bed 0.110 Cum. 5,296.50 582.61
Sand crusher 0.445 Cum. 5,296.50 2,356.94
Water 150.000 Ltr. 0.50 75.00
Rate analysis Total 23,280.71
for : 1.00
Cum.
15 % Contractor overhead 3,492.10
Grand Total 26,772.81

4.04 DUDBC- PCC FOR RCC WORKS M20(1:1½:3) WITH SCREENED Cum. 25,631.92 29,476.70
D2(7-4B) AGGREGATE: Providing and laying Reinforced Cement Concrete of
nominal mix 1:1½:3 (1 cement : 1½ sand : 3 aggregate ) for
Superstructure, Deck, Slab, columns, beams, Reinforced concrete walls
etc. with graded river bed screened stone aggregate of approved size
& quality in various locations and heights including transportation of
concrete to site of placing, , compaction,finished to required line &
level, protection & curing, with all lead (upto 30) and lift, etc. all
complete as per drawings, specifications and the instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
Materials Cement 0.400 M.T. 29,877.20 11,950.88
Aggrigate 20 mm-River bed 0.570 Cum. 5,204.69 2,966.67
Aggrigate 10 mm-River bed 0.290 Cum. 5,204.69 1,509.36
Sand 0.425 Cum. 5,296.50 2,251.01
Water 200 Ltr. 0.50 100.00
Rate analysis for : 1.00 Cum. Total 25,631.92
15 % Contractor overhead 3,844.78
Grand Total 29,476.70

4.05 DUDBC- PCC FOR RCC WORKS M25(1:1:2) WITH SCREENED Cum. 31,904.08 36,689.69
D2(7-4C) AGGREGATE: Providing and laying Reinforced Cement Concrete of
nominal mix 1:1:2 (1 cement : 1 sand : 2 aggregate ) for Superstructure,
Deck, Slab, columns, beams etc. with graded river bed screened stone
aggregate of approved size & quality in various locations and heights
including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
Materials Cement 0.610 M.T. 29,877.20 18,225.09
Aggrigate 20 mm-River bed 0.640 Cum. 5,204.69 3,331.00
Aggrigate 10 mm-River bed 0.210 Cum. 5,204.69 1,092.98
Sand crusher 0.425 Cum. 5,296.50 2,251.01
Water 300 Ltr. 0.50 150.00
S.N Norms Description Unit User Rate Contractors
Rate
Rate analysis for : 1.00 Cum. Total 31,904.08
15 % Contractor overhead 4,785.61
Grand Total 36,689.69

4.06 DUDBC- PLAIN CEMENT CONCRETE M10(1:3:6) WORKS WITH Cum. 18,029.75 20,734.21
D3(A) SCREENED AGGRGATE BY USING MACHINE: Providing and
laying machine mixed Plain Cement Concrete of nominal mix 1:3:6 (1
cement : 3 sand : 6 coarse aggregate ) for leveling course in
foundations, floors, Apron, pathway, drain, edge wall etc in all level
with river bed screened stone aggregate of approved size & quality
including dewatering, ,mixing, transporting, placing, compacting,
curing, with all lead (upto 30) and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.220 M.T. 29,877.20 6,572.98
Aggrigate 40 mm-River bed 0.650 Cum. 5,204.69 3,383.04
Aggrigate 20 mm-River bed 0.240 Cum. 5,204.69 1,249.12
Sand crusher 0.425 Cum. 5,296.50 2,251.01
Water 100.000 Ltr. 0.50 50.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 18,029.75
15 % Contractor overhead 2,704.46
Grand Total 20,734.21

4.07 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WORKS WITH Cum. 20,930.21 24,069.74
D3(B) SCREENED AGGREGATE BY USING MACHINE: Providing and
laying machine mixed Plain Cement Concrete of nominal mix 1:2:4 (1
cement : 2 sand : 4 aggregate ) for leveling course in foundations,
floors, Apron, pathway, drain, edge wall etc in all level with river bed
screened stone aggregate of approved size & quality including
dewatering, ,mixing, transporting, placing, compacting, curing, with all
lead (upto 30) and lift, etc. all complete as per drawings, specifications
and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-River bed 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mm-River bed 0.330 Cum. 5,204.69 1,717.54
Sand crusher 0.445 Cum. 5,296.50 2,356.94
Water 130.000 Ltr. 0.50 65.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 20,930.21
15 % Contractor overhead 3,139.53
Grand Total 24,069.74
S.N Norms Description Unit User Rate Contractors
Rate
4.08 DUDBC- PCC FOR RCC M20(1:1½:3) WORKS WITH SCREENED Cum. 23,328.14 26,827.36
D4(A) AGGREGATE BY USING MACHINE: Providing and laying
machine mixed Plain Cement Concrete of nominal mix 1:1½:3 (1
cement : 1½ sand : 3 aggregate ) for Superstructure, Deck, Slab,
columns, beams, Reinforced concrete walls etc. with river bed screened
stone aggregate of approved size & quality in various locations and
heights including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.400 M.T. 29,877.20 11,950.88
Aggrigate 20 mm-River bed 0.570 Cum. 5,204.69 2,966.67
Aggrigate 10 mm-River bed 0.290 Cum. 5,296.50 1,535.98
Sand crusher 0.425 Cum. 5,296.50 2,251.01
Water 200.000 Ltr. 0.50 100.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 23,328.14
15 % Contractor overhead 3,499.22
Grand Total 26,827.36

4.09 DUDBC- PCC FOR RCC M25(1:1:2) WORKS WITH SCREENED Cum. 29,592.96 34,031.90
D4(B) AGGREGATE BY USING MACHINE: Providing and laying
machine mixed Plain Cement Concrete of nominal mix 1:1:2 (1
cement : 1 sand : 2 aggregate ) for Superstructure, Deck, Slab, columns,
beams, Reinforced concrete walls etc. with river bed screened stone
aggregate of approved size & quality in various locations and heights
including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.610 M.T. 29,877.20 18,225.09
Aggrigate 20 mm-River bed 0.640 Cum. 5,204.69 3,331.00
Aggrigate 10 mm-River bed 0.210 Cum. 5,296.50 1,112.26
Sand crusher 0.425 Cum. 5,296.50 2,251.01
Water 300.000 Ltr. 0.50 150.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 29,592.96
15 % Contractor overhead 4,438.94
Grand Total 34,031.90
S.N Norms Description Unit User Rate Contractors
Rate
4.10 DUDBC- PLAIN CEMENT CONCRETE M10(1:3:6) WITH MACHINE Cum. 18,284.49 21,027.16
D1(7-2C) CRUSHED AGGREGATE: Providing and laying Plain Cement
Concrete of nominal mix 1:3:6 (1 cement : 3 sand : 6 coarse aggregate )
for leveling course in foundations, floors, Apron, pathway, drain, edge
wall etc in all level with machine crushed stone aggregate of approved
size & quality including dewatering, ,mixing, transporting, placing,
compacting, curing, with all lead (upto 30) and lift, etc. all complete as
per drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 4.000 Nos. 850.00 3,400.00
Materials Cement 0.220 M.T. 29,877.20 6,572.98
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 5,204.69 3,383.04
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 5,204.69 1,249.12
Aggrigate 10 mm-crushed/ballast stone 0.470 Cum. 5,296.50 2,489.35
Water 120.000 Ltr. 0.50 60.00
Rate analysis for : 1.00 Cum. Total 18,284.49
15 % Contractor overhead 2,742.67
Grand Total 21,027.16

4.11 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WITH MACHINE Cum. 20,956.71 24,100.21
D1(7-2D) CRUSHED AGGREGATE: Providing and laying Plain Cement
Concrete of nominal mix 1:2:4 (1 cement : 2 sand : 4 coarse aggregate )
for leveling course in foundations, floors, Apron, pathway, drain, edge
wall etc in all level with machine crushed stone aggregate of approved
size & quality including dewatering, ,mixing, transporting, placing,
compacting, curing, with all lead (upto 30) and lift, etc. all complete as
per drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 4.000 Nos. 850.00 3,400.00
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mm-crushed/ballast stone 0.220 Cum. 5,204.69 1,145.03
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 5,296.50 582.61
Aggrigate 10 mm-crushed/ballast stone 0.445 Cum. 5,296.50 2,356.94
Water 150.000 Ltr. 0.50 75.00
Rate analysis for : 1.00 Cum. Total 20,956.71
15 % Contractor overhead 3,143.50
Grand Total 24,100.21

4.12 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WITH MACHINE Cum. 23,280.71 26,772.81
D2(7-4A) CRUSHED AGGREGATE: Providing and laying Reinforced Cement
Concrete of nominal mix 1:2:4 (1 cement : 2 sand : 4 aggregate ) for
Superstructure, Deck, Slab, columns, beams etc. with machine crushed
stone aggregate of approved size & quality in various locations and
heights including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
S.N Norms Description Unit User Rate Contractors
Rate
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mmcrushed/ballast stone 0.220 Cum. 5,204.69 1,145.03
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 5,296.50 582.61
Aggrigate 10 mm-crushed/ballast stone 0.445 Cum. 5,296.50 2,356.94
Water 150.000 Ltr. 0.50 75.00
Rate analysis for : 1.00 Cum. Total 23,280.71
15 % Contractor overhead 3,492.10
Grand Total 26,772.81

4.13 DUDBC- PCC FOR RCC WORKS M20(1:1½:3) WITH MACHINE Cum. 25,658.54 29,507.32
D2(7-4B) CRUSHED AGGREGATE: Providing and laying Reinforced Cement
Resources Concrete of nominal mix 1:1½:3 (1 cement : Quantity
Level/Type 1½ sand : 3 aggregate
Unit ) for Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
Materials Cement 0.400 M.T. 29,877.20 11,950.88
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 5,204.69 2,966.67
Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 5,296.50 1,535.98
Aggrigate 10 mm-crushed/ballast stone 0.425 Cum. 5,296.50 2,251.01
Water 200.000 Ltr. 0.50 100.00
Rate analysis for : 1.00 Cum. Total 25,658.54
15 % Contractor overhead 3,848.78
Grand Total 29,507.32

4.14 DUDBC- PCC FOR RCC WORKS M25(1:1:2) WITH MACHINE Cum. 31,923.36 36,711.86
D2(7-4C) CRUSHED AGGREGATE:Providing and laying Reinforced Cement
Concrete of nominal mix 1:1:2 (1 cement : 1 sand : 2 aggregate ) for
Superstructure, Deck, Slab, columns, beams etc. with graded Machine
crushed stone aggregate of approved size & quality in various
locations and heights including transportation of concrete to site of
placing, , compaction,finished to required line & level, protection &
curing, with all lead (upto 30) and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.800 Nos. 1,130.00 904.00
Unskilled 7.000 Nos. 850.00 5,950.00
Materials Cement 0.610 M.T. 29,877.20 18,225.09
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 5,204.69 3,331.00
Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 5,296.50 1,112.26
Aggrigate 10 mm-crushed/ballast stone 0.425 Cum. 5,296.50 2,251.01
Water 300.000 Ltr. 0.50 150.00
Rate analysis for : 1.00 Cum. Total 31,923.36
15 % Contractor overhead 4,788.50
Grand Total 36,711.86

4.15 DUDBC- PLAIN CEMENT CONCRETE M10(1:3:6) WITH MACHINE Cum. 18,029.75 20,734.21
D3(A) CRUSHED AGGREGATE BY USING MACHINE : Providing and
laying machine mixed Plain Cement Concrete of nominal mix 1:3:6 (1
cement : 3 sand : 6 coarse aggregate ) for leveling course in
foundations, floors, Apron, pathway, drain, edge wall etc in all level
with machine crushed stone aggregate of approved size & quality
including dewatering, ,mixing, transporting, placing, compacting,
curing, with all lead (upto 30) and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
S.N Norms Description Unit User Rate Contractors
Rate
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.220 M.T. 29,877.20 6,572.98
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 5,204.69 3,383.04
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 5,204.69 1,249.12
Aggrigate 10 mm-crushed/ballast stone 0.425 Cum. 5,296.50 2,251.01
Water 100.000 Ltr. 0.50 50.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 18,029.75
15 % Contractor overhead 2,704.46
Grand Total 20,734.21

4.16 DUDBC- PLAIN CEMENT CONCRETE M15(1:2:4) WITH MACHINE Cum. 20,930.21 24,069.74
D3(B) CRUSHED AGGREGATE BY USING MACHINE: Providing and
laying Plain Cement Concrete of nominal mix 1:2:4 (1 cement : 2 sand :
4 coarse aggregate ) for leveling course in foundations, floors, Apron,
pathway, drain, edge wall etc in all level with machine crushed stone
aggregate of approved size & quality including dewatering, ,mixing,
transporting, placing, compacting, curing, with all lead (upto 30) and
lift, etc. all complete as per drawings, specifications and the instructions
of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.320 M.T. 29,877.20 9,560.70
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 5,204.69 2,706.43
Aggrigate 20 mm-crushed/ballast stone 0.330 Cum. 5,204.69 1,717.54
Aggrigate 10 mm-crushed/ballast stone 0.445 Cum. 5,296.50 2,356.94
Water 130.000 Ltr. 0.50 65.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 20,930.21
15 % Contractor overhead 3,139.53
Grand Total 24,069.74

4.17 DUDBC- PCC FOR RCC WORKS M20(1:1½:3) WITH MACHINE Cum. 23,328.14 26,827.36
D4(A) CRUSHED AGGREGATE BY USING MACHINE: Providing and
laying Reinforced Cement Concrete of nominal mix 1:1½:3 (1 cement :
1½ sand : 3 aggregate ) for Superstructure, Deck, Slab, columns,
beams, Reinforced concrete walls etc. with graded machine crushed
aggregate of approved size & quality in various locations and heights
including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.400 M.T. 29,877.20 11,950.88
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 5,204.69 2,966.67
S.N Norms
Materials Description Unit User Rate Contractors
Rate
Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 5,296.50 1,535.98
Aggrigate 10 mm-crushed/ballast stone 0.425 Cum. 5,296.50 2,251.01
Water 200.000 Ltr. 0.50 100.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 23,328.14
15 % Contractor overhead 3,499.22
Grand Total 26,827.36

4.18 DUDBC- PCC FOR RCC WORKS M25(1:1:2) WITH MACHINE Cum. 29,592.96 34,031.90
D4(B) CRUSHED AGGREGATE BY USING MACHINE: Providing and
laying Reinforced Cement Concrete of nominal mix 1:1:2 (1 cement : 1
sand : 2 aggregate ) for Superstructure, Deck, Slab, columns, beams,
Reinforced concrete walls etc. with graded machine crushed
aggregate of approved size & quality in various locations and heights
including transportation of concrete to site of placing, ,
compaction,finished to required line & level, protection & curing, with
all lead (upto 30) and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Cement 0.610 M.T. 29,877.20 18,225.09
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 5,204.69 3,331.00
Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 5,296.50 1,112.26
Aggrigate 10 mm-crushed/ballast stone 0.425 Cum. 5,296.50 2,251.01
Water 300.000 Ltr. 0.50 150.00
Diesel 3.000 Ltr. 175.00 525.00
Petrol 0.100 Ltr. 178.00 17.80
Equipment Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 693.00 415.80
Vibrator 0.250 Hour 100.00 25.00
Rate analysis for : 1.00 Cum. Total 29,592.96
15 % Contractor overhead 4,438.94
Grand Total 34,031.90

4.19 DUDBC- STEEL REINFORCEMENT WORK: Providing and fixing in Kg. 137.99 158.68
D9(7-5) position steel reinforcement of various diameter confirming to relevant
IS code in R.C.C. works including straightening, cutting, bending,
binding with 20 SWG annealed wire for tying the reinforcement bars at
each junctions (binding wire shall not be measured separately)
including all waste and cut pieces, provision for adequate numbers of
spacers,providing and placing cement mortar (1:1) cover blocks to keep
the bars in intended position at all levels all complete as as per
drawings, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 12.000 Nos. 1,130.00 13,560.00
Unskilled 12.000 Nos. 850.00 10,200.00
Materials TOR/TMT reinforcement bar 1.050 M.T. 107,500.00 112,875.00
Binding wire 10.000 Kg. 135.50 1,355.00
Rate analysis for : 1.00 MT Total 137,990.00
15 % Contractor overhead 20,698.50
Grand Total 158,688.50
S.N Norms Description Unit User Rate Contractors
Rate
E - FORM & PROPS WORK

5.01 DUDBC- FORMWORK FOR COLUMN (USING LOCAL WOOD): Sqm. 1,275.77 1,467.14
E1(8-3A) Supplying and laying shuttering of various pattern formworks for
column using local wood including nails, supporting and bracing in
proper plumb, sealing the joints, aligning to line and levels, base fixing
and deshuttering as approved by the Engineer etc., complete at as per
drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 3.748 Nos. 1,130.00 4,235.24 Scrap
Unskilled 5.622 Nos. 850.00 4,778.70 value .75x.5
Materials Wood Local salla 0.070 Cum. 48,551.25 3,398.58 26/6= 0.07
Killa 2.500 Kg. 138.10 345.25
Rate analysis for : 10.00 Sqm. Total 12,757.77
15 % Contractor overhead 1,913.66
Grand Total 14,671.43

5.02 DUDBC- FORMWORK FOR COLUMN (USING PLY WOOD): Supplying Sqm. 701.64 806.89
E2(51B) and laying centering & shuttering of various pattern formworks for
column using ply wood including nails, propping, scaffolding, staging,
supporting and bracing in proper plumb, sealing the joints, aligning to
line and levels, base fixing and deshuttering as approved by the
Engineer etc., complete at as per drawing, specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.574 Nos. 1,130.00 1,778.62
Unskilled 2.361 Nos. 850.00 2,006.85
Materials Ply board 19 mm thick 0.693 Sqm. 885.00 613.30
Wood Local 0.019 Cum. 48,551.25 922.47
MS Black pipe(MNB 50-M) 0.540 Nos. 2,500.00 1,350.00
Killa 2.500 Kg. 138.10 345.25
Rate analysis for : 10.00 Sqm. Total 7,016.49
15 % Contractor overhead 1,052.47
Grand Total 8,068.96

5.03 DUDBC- FORMWORK FOR BEAM DEPTH UPTO 0.3M (USING LOCAL Sqm. 1,336.38 1,536.84
E3(8-4A) WOOD): Supplying and laying centering & shuttering of various
pattern formworks for beams (Depth upto 0.3m) using local wood
including nails, propping, scaffolding, staging, supporting and bracing
in proper plumb, sealing the joints, aligning to line and levels, base
fixing and deshuttering as approved by the Engineer etc., complete at as
per drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 4.000 Nos. 1,130.00 4,520.00
Unskilled 6.000 Nos. 850.00 5,100.00
Materials Wood Local 0.070 Cum. 48,551.25 3,398.58
Killa 2.500 Kg. 138.10 345.25
Rate analysis for : 10.00 Sqm. Total 13,363.83
15 % Contractor Overhead 2,004.57
Grand Total 15,368.40
S.N Norms Description Unit User Rate Contractors
Rate
5.04 DUDBC- FORMWORK FOR BEAM DPETH 0.3m-0.8m (USING LOCAL Sqm. 1,016.09 1,168.50
E4(8-4B) WOOD): Supplying and laying centering & shuttering of various
pattern formworks for beams (Depth 0.3m to 0.8m) using local wood
including nails, propping, scaffolding, staging, supporting and bracing
in proper plumb, sealing the joints, aligning to line and levels, base
fixing and deshuttering as approved by the Engineer etc., complete at as
per drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 2.670 Nos. 1,130.00 3,017.10
Unskilled 4.000 Nos. 850.00 3,400.00
Materials Wood Local 0.070 Cum. 48,551.25 3,398.58
Killa 2.500 Kg. 138.10 345.25
Rate analysis for : 10.00 Sqm. Total 10,160.93
15 % Contractor Overhead 1,524.13
Grand Total 11,685.06

5.05 DUDBC- FORMWORK FOR SLAB (USING STEEL PROP): Supplying and Sqm. 815.99 938.39
E6(8-4A) laying centering, shuttering of formworks with spcified thickness water
proof ply wood & steel adjustable props for slab including nails,
propping scaffolding, staging, supporting and bracing in proper lines
and level, sealing the joints, aligning to line and levels including Ties,
PVC Spacer, Providing openings/ cutouts/ pockets, applying
deshuttering chemical, deshuttering as approved by the Engineer etc.,
complete at all levels as per drawing, specifications and instructions of
the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 17.200 Nos. 1,130.00 19,436.00
Unskilled 25.700 Nos. 850.00 21,845.00
Materials Ply board 19 mm thick 16.500 Sqm. 885.00 14,602.50
Wood Local 0.232 Cum. 48,551.25 11,263.89
MS Black pipe(MNB 50-M) 4.400 Nos. 2,500.00 11,000.00 4.40*5.10
Killa 25.000 Kg. 138.10 3,452.50
Rate analysis for : 100.00 Sqm. Total 81,599.89
15 % Contractor Overhead 12,239.98
Grand Total 93,839.87

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.
75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6
=16.5
M kfO{k M !% k6s;Dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
88/15x0.75
=4.4
gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
0.155/6x0.75=
0.019
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
4.62/6x0.90=0
.693
S.N Norms Description Unit User Rate Contractors
Rate
M kmnfd] af]N6 M !% k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
10.68/15x0.75
=0.54
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
33.33/6*0.75=
4.16*0.0254=
0.105
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
2.03/6*0.75=0
.25375

5.06 DUDBC- FORMWORK FOR SLAB (USING BAMBOO PROPS): Supplying Sqm. 506.49 582.47
E6(8-4A) and laying centering, shuttering of formworks with spcified thickness
water proof ply wood & bamboo props for slab including nails,
propping scaffolding, staging, supporting and bracing in proper lines
and level, sealing the joints, aligning to line and levels including
deshuttering as approved by the Engineer etc., complete at all levels as
per drawing, specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 10.560 Nos. 1,130.00 11,932.80 60% of17.2
Unskilled 10.380 Nos. 850.00 8,823.00 60% of17.3
Materials Ply board 19 mm thick 16.500 Sqm. 885.00 14,602.50
Wood Local 0.232 Cum. 48,551.25 11,263.89
Bamboo (11 feet Lenghth) 6.250 Nos. 92.00 575.00 6.25
Killa 25.000 Kg. 138.10 3,452.50
Rate analysis for : 100.00 Sqm. Total 50,649.69
15 % Contractor Overhead 7,597.45
Grand Total 58,247.14

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.
75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6
=16.5
af; M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
(100*3/6)/
6*0.75 =6.25
F - ROOFING WORK

6.01 DUDBC- CGI SHEET (PLAIN) ROOFING WORKS WITH 26 GAUGE(H): Sqm. 1,180.29 1,357.34
F1( 9-1) Supply, Providing and fitting of CGI plain sheet roofing (26 gauge
heavy) including all necessary hardware fittings such as nut, bolts, J-
hooks , bitumen washers, cleats etc all complete as per requirement and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.250 Nos. 850.00 1,062.50
Materials CGI sheet 26 (H) plain 12.000 Sqm. 739.69 8,876.24
Nutbolt 8 mm. 30.000 Nos. 11.25 337.50
J-hook 25.000 Nos. 10.54 263.39
Bitumen washer 55.000 Nos. 0.37 20.35
S.N Norms Description Unit User Rate Contractors
Rate
Rate analysis for : 10.00 Sqm. Total 11,802.98
15 % Contractor overhead 1,770.45
Grand Total 13,573.43
gf]6 M !=)) j08n h:tf nDafO{{ &@Ú–)Æ / rf}8fO{ @Ú–&=%Æ dfg]sf] . -&@Ú x @Ú–&=%=+ !&=%^ j=dL=_

6.02 DUDBC- CGI SHEET (PLAIN) ROOFING WORKS WITH 26 GAUGE(M): Sqm. 1,059.54 1,218.47
F1( 9-1) Supply, Providing and fitting of CGI plain sheet roofing (26 gauge
medium) including all necessary hardware fittings such as nut, bolts, J-
hooks , bitumen washers, cleats etc all complete as per requirement and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.250 Nos. 850.00 1,062.50
Materials CGI sheet 26 (M) plain 12.000 Sqm. 639.06 7,668.72
Nutbolt 8 mm. 30.000 Nos. 11.25 337.50
J-hook 25.000 Nos. 10.54 263.39
Bitumen washer 55.000 Nos. 0.37 20.35
Rate analysis for : 10.00 Sqm. Total 10,595.46
15 % Contractor overhead 1,589.32
Grand Total 12,184.78

6.03 DUDBC- CGI SHEET (PLAIN) ROOFING WORKS WITH 26 GAUGE(L): Sqm. 990.47 1,139.04
F1( 9-1) Supply, Providing and fitting of CGI plain sheet roofing (26 gauge
light) including all necessary hardware fittings such as nut, bolts, J-
hooks , bitumen washers, cleats etc all complete as per requirement and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.250 Nos. 850.00 1,062.50
Materials CGI sheet 26 (L) plain 12.000 Sqm. 581.50 6,978.00
Nutbolt 8 mm. 30.000 Nos. 11.25 337.50
J-hook 25.000 Nos. 10.54 263.39
Bitumen washer 55.000 Nos. 0.37 20.35
Rate analysis for : 10.00 Sqm. Total 9,904.74
15 % Contractor overhead 1,485.71
Grand Total 11,390.45

6.04 DUDBC- CGI SHEET (COLOURED) ROOFING WORKS WITH 26 Sqm. 1,180.29 1,357.34
F3( 9-1) GAUGE: Supply, Providing and fitting of CGI coloured sheet roofing
(26 gauge H) including all necessary hardware fittings such as nut,
bolts, J-hooks , bitumen washers, cleats etc all complete as per
requirement and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.250 Nos. 850.00 1,062.50
Materials CGI sheet 26(H) colored 12.000 Sqm. 739.69 8,876.24
Nutbolt 8 mm. 30.000 Nos. 11.25 337.50
J-hook 25.000 Nos. 10.54 263.39
Bitumen washer 55.000 Nos. 0.37 20.35
Rate analysis for : 10.00 Sqm. Total 11,802.98
15 % Contractor overhead 1,770.44
Grand Total 13,573.42
S.N Norms Description Unit User Rate Contractors
Rate

6.05 DUDBC- CGI SHEET (COLOURED) ROOFING WORKS WITH 26 Sqm. 1,072.67 -
F3( 9-1) GAUGE(M): Supply, Providing and fitting of CGI coloured sheet
roofing (26 gauge medium) including all necessary hardware fittings
such as nut, bolts, J-hooks , bitumen washers, cleats etc all complete as
per requirement and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.250 Nos. 850.00 1,062.50
Materials CGI sheet 26 (M) coloured 12.000 Sqm. 650.00 7,800.00
Nutbolt 8 mm. 30.000 Nos. 11.25 337.50
J-hook 25.000 Nos. 10.54 263.39
Bitumen washer 55.000 Nos. 0.37 20.35
Rate analysis for : 10.00 Sqm. Total 10,726.74
15 % Contractor overhead 1,609.01
Grand Total -

6.06 DUDBC- GI SHEET (PLAIN) ROOFING RIDGE COVER WITH 26 Rmtr. 834.44 959.60
F2( 9-2) GAUGE(M): Supply, Providing and fitting of Coloured GI plane sheet
roofing ridge cover including all necessary hardware fittings such as
nut, bolts, J-hooks , bitumen washers, cleats etc all complete as per
requirement and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 2.000 Nos. 1,130.00 2,260.00
Unskilled 3.000 Nos. 850.00 2,550.00
Materials GI Ridge Cover plain sheet 12.000 Rmtr.. 290.37 3,484.42
Nutbolt L.S. 50.00
Rate analysis for : 10.00 Rmtr. Total 8,344.42
15 % Contractor overhead 1,251.66
Grand Total 9,596.08

6.07 DUDBC- CGI SHEET (PLAIN) ROOFING RIDGE COVER : Supply, Rmtr. 1,239.97 1,425.96
F4( 9-2) Providing and fitting of CGI plane sheet coloured roofing ridge cover
including all necessary hardware fittings such as nut, bolts, J-hooks ,
bitumen washers, cleats etc all complete as per requirement and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 2.000 Nos. 1,130.00 2,260.00
Unskilled 3.000 Nos. 850.00 2,550.00
Materials CGI Ridge Cover colour 26 ( L ) Plain 12.000 Rmtr.. 628.31 7,539.73
Nutbolt L.S. 50.00
Rate analysis for : 10.00 Rmtr. Total 12,399.73
15 % Contractor overhead 1,859.96
Grand Total 14,259.69

6.08 DUDBC-F5/ GI SHEET ROOFING WORKS: Supply, Providing and fitting of GI sq.m 888.01 -
F6 sheet roofing works (28 gauge) including all necessary hardware
fittings such as nut, bolts, J-hooks , bitumen washers, cleats etc all
complete as per specifications and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
S.N Norms Description Unit User Rate Contractors
Labour Rate
Unskilled 1.250 Nos. 850.00 1,062.50
Materials GI sheet 28 G 12.000 Sqm. 496.41 5,956.94
J-hook 30.000 Nos. 10.54 316.07
Nut bolt 8 mm 25.000 Nos. 11.25 281.25
Bitumen washer 55.000 Nos. 0.37 20.35
Rate analysis for : 10.00 sq.m Total 8,880.11
15 % Contractor overhead 1,332.02
Grand Total -

6.09 DUDBC-F7 GI GUTTER: Supply, Providing and fitting of 150 mm depth & Rmtr. 1,263.52 1,453.05
breadth upto 450 mm G. I. sheet Gutter fixing work with 3x40 mm
M.S. bracket nut bolt, washer etc all complete as per specifications and
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.750 Nos. 1,130.00 1,977.50
Unskilled 2.000 Nos. 850.00 1,700.00
Materials G. I. plane sheet 13.500 Rmtr 290.37 3,919.97
M.S. bracket 3*40 mm 32.000 Nos. 140.00 4,480.00
Nut bolt 48.000 Nos. 11.25 540.00
Bitumen washer 48.000 Nos. 0.37 17.76
Rate analysis for : 10.00 Rmtr. Total 12,635.23
15 % Contractor overhead 1,895.28
Grand Total 14,530.51

6.10 DUDBC-F10( ClAY TILE ROOFING: Supplying, laying of fully fired clay tiles on sq.m 337.75 388.41
9-6) roofing of approved size and quality as per drawings,specifications and
instructions of engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 1.500 Nos. 850.00 1,275.00
Materials Clay tile 125.000 Nos. 12.30 1,537.50
Rate analysis for : 10.00 sq.m Total 3,377.50
15 % Contractor overhead 506.63
Grand Total 3,884.13

6.11 DUDBC- Making and fixing of 25 mm sal wood eaves board Sqm. 5,528.26 6,357.50
F20(10-19)
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.430 Nos. 1,130.00 1,615.90
Unskilled 0.143 Nos. 850.00 121.55
Materials Wood Sal 0.275 Cum. 194,346.29 53,445.22
Killas L.S. 100.00
Rate analysis for : 10.00 Sqm. Total 55,282.67
15 % Contractor overhead 8,292.40
Grand Total 63,575.07

G - DOOR & WINDOW WORK

7.01 DUDBC- SAL WOOD CHAUKHATS: Supplying and fixing in position well Cum. 285,558.81 328,392.63
G1(10-1) seasoned sal wood work for door, window and ventillation frames
including levelling, scafolding, all necessary hardware fitting etc. all
complete finishing as per drawing, specification & instructions of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 34.000 Nos. 1,130.00 38,420.00
S.N Norms Description Unit User Rate Contractors
Labour Rate
Unskilled 3.400 Nos. 850.00 2,890.00
Materials Wood Sal 1.100 Nos. 219,451.65 241,396.81
Hold fast 92.000 Nos. 28.00 2,576.00
pech killas 184.000 Nos. 1.50 276.00
Rate analysis for : 1.00 Cum. Total 285,558.81
15 % Contractor overhead 42,833.82
Grand Total 328,392.63

7.02 DUDBC- LOCAL WOOD CHAUKHATS: Supplying and fixing in position Cum. 136,724.21 157,232.84
G1(10-1) well seasoned local wood work for door, window and ventillation
frames including levelling, scafolding, all necessary hardware fitting
etc. all complete finishing as per drawing, specification & instructions
of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 34.000 Nos. 1,130.00 38,420.00
Unskilled 3.400 Nos. 850.00 2,890.00
Materials Wood Local patle 1.100 Nos. 83,896.56 92,286.21
Hold fast 92.000 Nos. 31.00 2,852.00
pech killas 184.000 Nos. 1.50 276.00
Rate analysis for : 1.00 Cum. Total 136,724.21
15 % Contractor overhead 20,508.63
Grand Total 157,232.84

7.03 DUDBC- 38MM THICK SAL WOOD FULLY PANELED SHUTTER: Sqm. 15,570.92 17,906.55
G2(10-2) Supplying, Making and fitting fixing of 38mm thick sal wood fully
paneled shutter all complete finishing as per drawing, specification &
instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 10.000 Nos. 1,130.00 11,300.00
Unskilled 1.000 Nos. 850.00 850.00
Materials Wood Sal 0.084 Cum. 219,451.65 18,433.93
Hinge 100 mm 6.000 Nos. 40.00 240.00
Towerbolt 150 mm. 1.000 Nos. 183.00 183.00
Towerbolt 300 mm. 1.000 Nos. 214.00 214.00
Lockingset 250-300mm. 1.000 Nos. 647.00 647.00
Handle 2.000 Nos. 487.00 974.00
Pech killas L.S. 75.00
Rate analysis for : 2.114 Sqm. Total 32,916.93
15 % Contractor overhead 4,937.53
Grand Total 37,854.46

7.04 DUDBC- 38MMX75MMTHICK SAL WOOD FRAME WITH 4MM GLASS Sqm. 10,885.67 12,518.52
G3(10-4)
SHUTTER: Supplying, Making and fitting fixing of 38mmx75mm
thick salwood frame with 4mm glazing shutter all complete finishing as
per drawing, specification & instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 9.000 Nos. 1,130.00 10,170.00
Unskilled 0.900 Nos. 850.00 765.00
Materials Wood Sal 0.049 Cum. 219,451.65 10,753.13
Glass 4 mm thick-Plane 1.085 Sqm. 905.00 981.92
Hinge 75 mm 8.000 Nos. 37.00 296.00
Towerbolt 100 mm. 4.000 Nos. 65.00 260.00
Materials

S.N Norms Description Unit User Rate Contractors


Rate
Handle 2.000 Nos. 487.00 974.00
Pech killas L.S. 75.00
Rate analysis for : 2.23 Sqm. Total 24,275.05
15 % Contractor overhead 3,641.25
Grand Total 27,916.30

7.05 DUDBC- 38 mm thick sal wood frame with 4 mm thick commercial plywood Sqm. 8,773.57 10,089.60
G4(10-7) (bothside) flush shutter fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 7.000 Nos. 1,130.00 7,910.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
Ply wood 4 mm thick commercial 4.650 Sqm. 341.00 1,585.65
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Mortice lock(Brass) 1.000 Nos. 1,543.00 1,543.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. Total 19,696.67
15 % Contractor overhead 2,954.50
Grand Total 22,651.17

7.06 DUDBC- 38 mm thick sal wood frame with 3 mm thick TEAK plywood (Both Sqm. 8,517.76 9,795.42
G4(10-8) side ) flush shutter fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 7.000 Nos. 1,130.00 7,910.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
Ply wood 4 mm thick Teak 2.325 Sqm. 435.00 1,011.37
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Mortice lock(Brass) 1.000 Nos. 1,543.00 1,543.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. Total 19,122.39
15 % Contractor overhead 2,868.35
Grand Total 21,990.74

7.07 DUDBC- 38 mm thick sal wood frame with G.I. plane sheet (bothside) shutter Sqm. 9,043.05 -
G4(10-9) fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 7.000 Nos. 1,130.00 7,910.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
GI plane sheet 26 gauge 4.650 Sqm. 598.20 2,781.63
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Handle 1.000 Nos. 465.00 465.00
Lockingset 250 mm. 1.000 Nos. 487.00 487.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. Total 20,301.65
15 % Contractor overhead 3,045.24
Grand Total -

7.13 DUDBC- 38 x100mm thick sal wood frame with 12 mm thick commercial Sqm. 10,182.82 11,710.24
G8(10-3 & plywood paneled & one side 4 mm thick Teak plywood paneled shutter
10-7)
fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
S.N Norms Description Unit User Rate Contractors
Rate
Labour Skilled 9.000 Nos. 1,130.00 10,170.00
Unskilled 0.900 Nos. 850.00 765.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
Ply wood 12 mm thick commercial 1.900 Sqm. 590.50 1,121.95
Ply wood 4 mm thick Teak 1.900 Sqm. 435.00 826.50
Wooden listies ¾" 7.434 Rmtr. 23.00 170.98
Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Mortice lock(Brass) 1.000 Nos. 1,543.00 1,543.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. ( 1.092 x 2.058 =2.245 Total 22,860.45
Sqm.) 15 % Contractor overhead 3,429.06
Grand Total 26,289.51

7.14 DUDBC- 38 x100mm thick sal wood frame with 12 mm thick commercial Sqm. 10,617.20 12,209.78
G9(10-3 & plywood paneled & both side 4 mm thick Teak plywood paneled shutter
10-7)
fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 9.000 Nos. 1,130.00 10,170.00
Unskilled 0.900 Nos. 850.00 765.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
Ply wood 12 mm thick commercial 1.900 Sqm. 590.50 1,121.95
Ply wood 4 mm thick Teak 3.800 Sqm. 435.00 1,653.00
Wooden listies ¾" 14.868 Rmtr. 21.50 319.66
Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Mortice lock(Brass) 1.000 Nos. 1,543.00 1,543.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. Size of shutter 1.092 x Total 23,835.63
2.058 =2.245 Sqm. 15 % Contractor overhead 3,575.34
Grand Total 27,410.97

7.15 DUDBC- 38 x100mm thick sal wood frame with 12 mm thick water proof Sqm. 9,535.12 10,965.38
G10(10-3 & plywood paneled & one side 4 mm thick Teak plywood paneled shutter
10-7) fixing with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 7.000 Nos. 1,130.00 7,910.00
Unskilled 0.700 Nos. 850.00 595.00
Materials Wood Sal 0.0346 Cum. 219,451.65 7,593.02
Ply wood 12 mm thick water proof 1.900 Sqm. 1,110.00 2,109.00
Ply wood 4 mm thick Teak 1.900 Sqm. 435.00 826.50
Wooden listies ¾" 7.434 Rmtr. 21.50 159.83
Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 40.00 120.00
Towerbolt 150 mm. 2.000 Nos. 150.00 300.00
Mortice lock(Brass) 1.000 Nos. 1,543.00 1,543.00
Pech killas L.S. 50.00
Rate analysis for : 2.245 Sqm. (Size of shutter 1.092 x Total 21,406.35
2.058 =2.245 Sqm.) 15 % Contractor overhead 3,210.95
Grand Total 24,617.30

H - FLOORING WORK
S.N Norms Description Unit User Rate Contractors
Rate
8.01 DUDBC- 38MM THICK (1½") 1:2:4 CEMENT CONCRETE FLOOR Sqm. 958.04 1,101.75
H1(11-1B) FINISH: Providing and laying in required line , level and pattern
38mm thick (1½") cement concrete flooring 1:2:4 ( 1cement : 2 coarse
sand: 4 aggregate and finished top layer with floating coat of neat
cement slurry as per drawings, specifications and instructions.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.250 Nos. 1,130.00 1,412.50
Unskilled 2.000 Nos. 850.00 1,700.00
Materials Cement 0.130 M.T. 27,752.80 3,607.86
Sand river washed 0.180 Cum. 5,296.50 953.37
Aggrigate 12 mm-River bed 0.360 Cum. 5,296.50 1,906.74
Rate analysis for :10.00 Sqm. Total 9,580.47
15 % Contractor overhead 1,437.07
Grand Total 11,017.54

8.02 DUDBC- 50MM THICK (2") 1:2:4 CEMENT CONCRETE FLOOR Sqm. 1,191.00 1,369.65
H1(11-1C) FINISH: Providing and laying in required line , level and pattern
50mm thick (2") cement concrete flooring 1:2:4 ( 1cement : 2 coarse
sand: 4 aggregate and finished top layer with floating coat of neat
cement slurry as per drawings, specifications and instructions.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.250 Nos. 1,130.00 1,412.50
Unskilled 2.500 Nos. 850.00 2,125.00
Materials Cement 0.170 M.T. 27,752.80 4,717.97
Sand river washed 0.230 Cum. 5,296.50 1,218.19
Aggrigate 20 mm-River bed 0.460 Cum. 5,296.50 2,436.39
Rate analysis for :10.00 Sqm. Total 11,910.05
15 % Contractor overhead 1,786.50
Grand Total 13,696.55

8.03 DUDBC- 75MM THICK (3") 1:2:4 CEMENT CONCRETE FLOOR Sqm. 1,658.06 1,906.77
H1(11-1D) FINISH: Providing and laying in required line , level and pattern
75mm thick (3") cement concrete flooring 1:2:4 ( 1cement : 2 coarse
sand: 4 aggregate and finished top layer with floating coat of neat
cement slurry as per drawings, specifications and instructions.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.250 Nos. 1,130.00 1,412.50
Unskilled 3.000 Nos. 850.00 2,550.00
Materials Cement 0.260 M.T. 27,752.80 7,215.72
Sand river washed 0.340 Cum. 5,296.50 1,800.81
Aggrigate 20 mm-River bed 0.680 Cum. 5,296.50 3,601.62
Rate analysis for :10.00 Sqm. Total 16,580.65
15 % Contractor overhead 2,487.09
Grand Total 19,067.74

8.04 DUDBC- 11- 16MM THICK MARBLE FLOORING: Providing and laying of 16 Sqm. 4,166.98 4,792.03
6 mm thick marble of required size of approved shade, colour and texure
inlcluding required mortar base with polishing all complete as per
drawing, specification and instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 2.000 Nos. 1,130.00 2,260.00
Unskilled 8.000 Nos. 850.00 6,800.00
Materials Marble tile 16 mm color 11.000 Sqm. 2,478.00 27,258.00
Cement 0.13 M.T. 27,752.80 3,607.86
S.N Norms
Materials Description Unit User Rate Contractors
Rate
Sand crusher 0.183 Cum. 5,296.50 969.25
Oxalic acid powder 0.370 Kg. 437.50 161.87
Main Polish 0.118 Kg. 597.50 70.50
Tarpaintain oil 0.538 Ltr. 175.50 94.41
Carborendam Stone 2.000 Nos. 224.00 448.00 L.S. 2 Nos.
Rate analysis for :10.00 Sqm. Total 41,669.89
15 % Contractor overhead 6,250.48
Grand Total 47,920.37

8.05 DUDBC- PORECELAIN GLAZED TILE WORK: Providing and fixing Sqm. 3,784.88 4,352.62
H6(11-7) Porcelain glazed /non glazed floor tile in required line, level with
specified thickness approved brand in any colours, shades of any size
with 1:4 cement sand mortar base as per drawing, specification and
instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 13.000 Nos. 1,130.00 14,690.00
Unskilled 4.500 Nos. 850.00 3,825.00
Materials Porecelain glazed floor tile 11.000 Sqm. 1,528.48 16,813.28
Cement 0.056 M.T. 27,752.80 1,554.15
Sand crusher 0.152 Cum. 5,296.50 805.06
White cement 3.228 Kg. 50.00 161.40
Rate analysis for :10.00 Sqm. Total 37,848.89
15 % Contractor overhead 5,677.33
Grand Total 43,526.22

8.05 DUDBC- PORECELAIN GLAZED TILE WORK: Providing and fixing Sqm. 3,343.24 3,844.73
H6(11-7) Porcelain glazed /non glazed wall tile in required line, level with
specified thickness approved brand in any colours, shades of any size
with 1:4 cement sand mortar base as per drawing, specification and
instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 13.000 Nos. 1,130.00 14,690.00
Unskilled 4.500 Nos. 850.00 3,825.00
Materials Porecelain glazed wall tile 11.000 Sqm. 1,323.96 14,563.56
Cement 0.056 M.T. 1,130.00 63.28
Unskilled 0.152 Cum. 850.00 129.20
White cement 3.228 Kg. 50.00 161.40
Rate analysis for :10.00 Sqm. Total 33,432.44
15 % Contractor overhead 5,014.86
Grand Total 38,447.30

8.06 DUDBC- FLAT BRICK PAVING WORK: Flat Brick paving in 1:6 & cement Sqm. 2,079.13 2,391.00
H12(11-12) sand pointing in joints all complete as per drawing, specification and
Resources instruction
Level/Typeof the Engineer. Quantity Unit Rate Amount Remarks
Labour Skilled 2.250 Nos. 1,130.00 2,542.50
Unskilled 3.250 Nos. 850.00 2,762.50
Materials Brick chimney 322.900 Nos. 37.50 12,108.75
Cement 0.078 M.T. 27,752.80 2,164.71
Sand crusher 0.229 Cum. 5,296.50 1,212.89
Rate analysis for :10.00 Sqm. Total 20,791.35
15 % Contractor overhead 3,118.70
Grand Total 23,910.05

8.07 DUDBC- EDGE BRICK PAVING WORK: Edge Brick paving in 1:6 & cement Sqm. 2,903.88 3,339.47
H13(11-13) sand pointing in1:2 in joints all complete as per drawing, specification
and instruction of the Engineer.
S.N Norms Description Unit User Rate Contractors
Rate
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.100 Nos. 1,130.00 1,243.00
Unskilled 1.800 Nos. 850.00 1,530.00
Materials Brick chimney 550.000 Nos. 37.50 20,625.00
Cement 0.121 M.T. 27,752.80 3,358.08
Sand crusher 0.431 Cum. 5,296.50 2,282.79
Rate analysis for :10.00 Sqm. Total 29,038.87
15 % Contractor overhead 4,355.83
Grand Total 33,394.70

8.08 DUDBC- FLAT BRICK SOLING WORK: One layer dry chimney made flat Sqm. 1,728.42 1,987.68
H15(11-15A) brick soling work over rammed earth or sand including proper line,
Resources level & proper slope with sand filling in
Level/Type gaps as Unit
Quantity per drawing, Rate Amount Remarks
Labour Skilled 0.500 Nos. 1,130.00 565.00
Unskilled 1.000 Nos. 850.00 850.00
Materials Brick chimney 322.900 Nos. 37.50 12,108.75
Sand crusher 0.710 Cum. 5,296.50 3,760.51
Rate analysis for :10.00 Sqm. Total 17,284.26
15 % Contractor overhead 2,592.63
Grand Total 19,876.89

8.09 DUDBC- EDGE BRICK SOLING WORK: One layer dry chimney made edge Sqm. 2,827.80 3,251.97
H15(11-15B) brick soling work over rammed earth or sand including proper line,
Resources level & proper slope with sand filling in
Level/Type gaps as Unit
Quantity per drawing, Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 3.250 Nos. 850.00 2,762.50
Materials Brick chimney 550.000 Nos. 37.50 20,625.00
Sand crusher 0.710 Cum. 5,296.50 3,760.51
Rate analysis for :10.00 Sqm. Total 28,278.01
15 % Contractor overhead 4,241.70
Grand Total 32,519.71

8.10 DUDBC- STONE SOLING WORK: Supply, Providing and laying dry stone Cum. 8,898.86 10,233.68
H16( 11-16) soling work over rammed earth in proper line, level & proper slope with
sand filling in gaps as per drawing, specification and instruction of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 3.500 Nos. 850.00 2,975.00
Materials Stone block 1.100 Cum. 2,648.25 2,913.07
Sand Local 0.710 Cum. 2,649.00 1,880.79
Rate analysis for :1.00 Cum. Total 8,898.86
15 % Contractor overhead 1,334.82
Grand Total 10,233.68

8.11 DUDBC- PUNNING WORK: Providing and laying 3 mm thick neat cement Sqm. 345.64 397.49
H20( 11-20) punning work as per drawing, specification and instruction of the
Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
S.N Norms Description Unit User Rate Contractors
Rate
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 1.000 Nos. 850.00 850.00
Materials Cement 53.200 Kg. 27.75 1,476.44
Rate analysis for :10.00 Sqm. Total 3,456.44
15 % Contractor overhead 518.46
Grand Total 3,974.90

8.13 DUDBC- GRANITE FLOORING WORKS(PLAIN): Supply, Providing and Sqm. 7,708.11 8,864.33
H26(11-6) laying of 16mm thick Granite (plain) on floor with 20 mm thick cement
sand mortar 1:2 rubbing & polishing work with all complete as per
drawing, specification and instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 2.000 Nos. 1,130.00 2,260.00
Unskilled 8.000 Nos. 850.00 6,800.00
Materials Granite 16mm thick plain 13.500 Sqm. 3,786.00 51,111.00
Cement 0.133 M.T. 27,752.80 3,691.12
sand crusher 0.183 Cum. 5,296.50 969.25
Oxalic acid powder 0.370 Kg. 437.50 161.87
Main Polish 0.118 Kg. 597.50 70.50
Tarpaintain oil 0.538 Ltr. 175.50 94.41
Carborendam Stone 2.000 Nos. 224.00 448.00 L.S. 2 Nos.
Equipment Unskilled 13.500 Nos. 850.00 11,475.00
Rate analysis for :10.00 Sqm. Total 77,081.15
15 % Contractor overhead 11,562.17
Grand Total 88,643.32

8.14 DUDBC- GRANITE FLOORING WORKS(COLOURED): Supply, Providing Sqm. 7,708.11 8,864.33
H26(11-6)
and laying of 16mm thick Granite (Coloured) on floor with 20 mm
thick cement sand mortar 1:2 rubbing & polishing work with all
complete as per drawing, specification and instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 2.000 Nos. 1,130.00 2,260.00
Unskilled 8.000 Nos. 850.00 6,800.00
Materials Granite 16mm thick coloured 13.500 Sqm. 3,786.00 51,111.00
Cement 0.133 M.T. 27,752.80 3,691.12
sand crusher 0.183 Cum. 5,296.50 969.25
Oxalic acid powder 0.370 Kg. 437.50 161.87
Main Polish 0.118 Kg. 597.50 70.50
Tarpaintain oil 0.538 Ltr. 175.50 94.41
Carborendam Stone 2.000 Nos. 224.00 448.00 L.S. 2 Nos.
Equipment Unskilled 13.500 Nos. 850.00 11,475.00
Rate analysis for :10.00 Sqm. Total 77,081.15
15 % Contractor overhead 11,562.17
Grand Total 88,643.32
S.N Norms Description Unit User Rate Contractors
Rate

8.16 DUDBC-H23 60MMTHICK INTERLOCKING BLOCK(PLAIN): Supply, Sqm. 2,899.12 3,333.99


providing and laying of 60 mm thick interlocking block(Plain) over 50
mm thick Crusser stone dust in perfect line and level all complete as per
drawing, specification and instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 10.000 Nos. 850.00 8,500.00
Materials Interlocking Block 60mm Thick -plain 11.000 Sqm. 1,416.00 15,576.00
Stone dust 0.550 Sqm. 45.00 24.75
Sand crusher 0.710 Cum. 5,296.50 3,760.51
Rate analysis for :10.00 Sqm. Total 28,991.26
15 % Contractor overhead 4,348.68
Grand Total 33,339.94

I - PLASTER & POINTING WORK

9.01 DUDBC- 12.5MM THICK PLASTER(1:4) ON WALL: Providing and Sqm. 498.23 572.97
I1(12-1C)
applying at all levels and shape 12.5mm thick cement plaster in
specified cement mortar 1:4(1 cement : 4 coarse sand) in all surface at
all height including mixing mortar, laying in perfect line, level and
plumb and finishing in regular and even surface including all necessary
single or multi-stage scaffolding,threading, dusting, dripping, wetting,
curing, protection, etc., all complete as per drawing , specification and
instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 12.000 Nos. 1,130.00 13,560.00
Unskilled 16.000 Nos. 850.00 13,600.00
Materials Cement 0.538 M.T. 27,752.80 14,931.00
sand crusher 1.460 Cum. 5,296.50 7,732.89
Rate analysis for :100.00 Sqm. Total 49,823.89
15 % Contractor overhead 7,473.58
Grand Total 57,297.47

9.02 DUDBC- 12.5MM THICK PLASTER(1:6) ON WALL: Providing and Sqm. 460.77 529.88
I1(12-1D) applying at all levels and shape 12.5mm thick cement plaster in
specified cement mortar 1:6(1 cement : 6 coarse sand) in all surface at
all height including mixing mortar, laying in perfect line, level and
plumb and finishing in regular and even surface including all necessary
single or multi-stage scaffolding,threading, dusting, dripping, wetting,
curing, protection, etc., all complete as per drawing , specification and
instruction of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 12.000 Nos. 1,130.00 13,560.00
Unskilled 16.000 Nos. 850.00 13,600.00
Materials Cement 0.382 M.T. 27,752.80 10,601.56
sand crusher 1.570 Cum. 5,296.50 8,315.50
Rate analysis for :100.00 Sqm. Total 46,077.06
15 % Contractor overhead 6,911.55
Grand Total 52,988.61

9.03 DUDBC- 20MM THICK PLASTER(1:3) ON WALL: Providing and Sqm. 689.40 792.81
I4(12-4A) applying at all levels and shape 20mm thick cement plaster in
specified cement mortar 1:3(1 cement : 3 coarse sand) in all surface
S.N Norms Description Unit User Rate Contractors
Rate
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 14.000 Nos. 1,130.00 15,820.00
Unskilled 19.000 Nos. 850.00 16,150.00
Materials Cement 0.960 M.T. 27,752.80 26,642.68
sand crusher 1.950 Cum. 5,296.50 10,328.17
Rate analysis for :100.00 Sqm. Total 68,940.85
15 % Contractor overhead 10,341.12
Grand Total 79,281.97

9.04 DUDBC- 20MM THICK PLASTER(1:4) ON WALL: Providing and Sqm. 661.02 760.17
I4(12-4B) applying at all levels and shape 20mm thick cement plaster in
Resources specified
Level/Typecement mortar 1:4(1 cement : 4 coarse sand) Unit
Quantity in all surface Rate Amount Remarks
Labour Skilled 14.000 Nos. 1,130.00 15,820.00
Unskilled 19.000 Nos. 850.00 16,150.00
Materials Cement 0.810 M.T. 27,752.80 22,479.76
sand crusher 2.200 Cum. 5,296.50 11,652.30
Rate analysis for :100.00 Sqm. Total 66,102.06
15 % Contractor overhead 9,915.30
Grand Total 76,017.36

9.05 DUDBC- 20MM THICK PLASTER(1:6) ON WALL: Providing and Sqm. 602.35 692.71
I4(12-4C) applying at all levels and shape 20mm thick cement plaster in
Resources specified
Level/Typecement mortar 1:6(1 cement : 6 coarse sand) Unit
Quantity in all surface Rate Amount Remarks
Labour Skilled 14.000 Nos. 1,130.00 15,820.00
Unskilled 19.000 Nos. 850.00 16,150.00
Materials Cement 0.570 M.T. 27,752.80 15,819.09
sand crusher 2.350 Cum. 5,296.50 12,446.77
Rate analysis for :100.00 Sqm. Total 60,235.86
15 % Contractor overhead 9,035.37
Grand Total 69,271.23

9.06 DUDBC- 12.5MM THICK PLASTER(1:3) IN CEILING: Providing and Sqm. 580.75 667.86
I7(12-1B) applying at all levels and shape 12.5mm thick cement plaster in Ceiling
Resources specified
Level/Typecement mortar 1:3(1 cement : 3 coarse sand) inUnit
Quantity all surface at Rate Amount Remarks
Labour Skilled 15.000 Nos. 1,130.00 16,950.00
Unskilled 20.000 Nos. 850.00 17,000.00
Materials Cement 0.625 M.T. 27,752.80 17,345.50
sand crusher 1.280 Cum. 5,296.50 6,779.52
Rate analysis for :100.00 Sqm. Total 58,075.02
15 % Contractor overhead 8,711.25
Grand Total 66,786.27

9.07 DUDBC- 12.5MM THICK PLASTER(1:4) IN CEILING: Providing and Sqm. 566.13 651.05
I7(12-1C) applying at all levels and shape 12.5mm thick cement plaster in Ceiling
Resources specified
Level/Typecement mortar 1:4(1 cement : 4 coarse sand) inUnit
Quantity all surface at Rate Amount Remarks
Labour Skilled 15.000 Nos. 1,130.00 16,950.00
Unskilled 20.000 Nos. 850.00 17,000.00
Materials Cement 0.538 M.T. 27,752.80 14,931.00
sand crusher 1.460 Cum. 5,296.50 7,732.89
Rate analysis for :100.00 Sqm. Total 56,613.89
15 % Contractor overhead 8,492.08
Grand Total 65,105.97
S.N Norms Description Unit User Rate Contractors
Rate
9.08 DUDBC- POINTING WORKS (1:3) ON STONE MASONARY WALL: Sqm. 216.52 248.99
I10(14-3) Providing and applying flush/rulled pointing in specified cement
Resources mortar 1:3(1 cement : 3 coarse sand) in stone
Level/Type masonary
Quantity Unitwall at all Rate Amount Remarks
Labour Skilled 8.000 Nos. 1,130.00 9,040.00
Unskilled 10.000 Nos. 850.00 8,500.00
Materials Cement 0.110 M.T. 27,752.80 3,052.80
sand crusher 0.200 Cum. 5,296.50 1,059.30
Rate analysis for :100.00 Sqm. Total 21,652.10
15 % Contractor overhead 3,247.81
Grand Total 24,899.91

9.09 WALL PUTTY WORKS: Providing and applying 2mm thick plane Sqm. 266.62 306.62
Resources wall putting of approved quality to the surfaces
Level/Type of wall
Quantity and ceiling
Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 1.000 Nos. 850.00 850.00
Materials White patti plaster 10.640 Kg. 64.50 686.28
Rate analysis for :10.00 Sqm. Total 2,666.28
15 % Contractor overhead 399.94
Grand Total 3,066.22

J - PAINTING WORK

10.01 DUDBC- WHITE WASHING ON WALL (TWO COATS) : Providing and Sqm. 41.01 47.16
J1(13-1B) applying two coats of white washing work on wall including
Resources scraping,
Level/Typesurface preparation, scaffoldingQuantity
etc., all complete
Unit as per Rate Amount Remarks
Labour Skilled 1.500 Nos. 1,130.00 1,695.00
Unskilled 1.100 Nos. 850.00 935.00
Materials White lime 22.000 Kg. 53.00 1,166.00
gum 0.880 Kg. 347.00 305.36
Rate analysis for :100.00 Sqm. Total 4,101.36
15 % Contractor overhead 615.20
Grand Total 4,716.56

10.02 DUDBC- WHITE WASHING ON CEILING (TWO COATS) : Providing Sqm. 47.58 54.72
J1(13-1B) and applying two coats of white washing work on ceiling including
Resources scraping,
Level/Typewashing the surface, surface preparation,
Quantity scaffolding
Unit etc., Rate Amount Remarks
Labour Skilled 1.875 Nos. 1,130.00 2,118.75 25% Add
Unskilled 1.375 Nos. 850.00 1,168.75 for ceilling
Materials White lime 22.000 Kg. 53.00 1,166.00
gum 0.880 Kg. 347.00 305.36
Rate analysis for :100.00 Sqm. Total 4,758.86
15 % Contractor overhead 713.82
Grand Total 5,472.68

10.03 DUDBC- WHITE WASHING ON WALL (THREE COATS) : Providing and Sqm. 78.25 89.98
J1(13-1C) applying three coats of white washing work on wall including
Resources scraping,
Level/Typewashing the surface, surface preparation,
Quantity scaffolding
Unit etc., Rate Amount Remarks
Labour Skilled 3.000 Nos. 1,130.00 3,390.00
Unskilled 2.700 Nos. 850.00 2,295.00
Materials White lime 32.000 Kg. 53.00 1,696.00
gum 1.280 Kg. 347.00 444.16
Rate analysis for :100.00 Sqm. Total 7,825.16
15 % Contractor overhead 1,173.77
S.N Norms Rate analysis for :100.00 Sqm.Description Unit User Rate Contractors
Rate
Grand Total 8,998.93

10.04 DUDBC- WHITE WASHING ON CEILING (THREE COATS) : Providing Sqm. 92.46 106.33
J1(13-1C) and applying three coats of white washing work on ceiling including
Resources scraping,
Level/Typewashing the surface, surface preparation,
Quantity scaffolding
Unit etc., Rate Amount Remarks
Labour Skilled 3.750 Nos. 1,130.00 4,237.50 25% Add
Unskilled 3.375 Nos. 850.00 2,868.75 for ceilling
Materials White lime 32.000 Kg. 53.00 1,696.00
gum 1.280 Kg. 347.00 444.16
Rate analysis for :100.00 Sqm. Total 9,246.41
15 % Contractor overhead 1,386.96
Grand Total 10,633.37

10.06 DUDBC- ONE COAT DISTEMPER PAINT OVER PRIMER COAT: Sqm. 137.33 157.92
J3(13-3AB) Providing and applying One coat distemper paint over primer coat
Resources including
Level/Type scraping, surface preparation, scaffolding
Quantity Unit etc., all Rate Amount Remarks
Labour Skilled 4.00 Nos. 1,130.00 4,520.00
Unskilled 4.00 Nos. 850.00 3,400.00
Materials Distemper primer 8.00 Ltr. 491.00 3,928.00
Distemper 6.50 Kg. 290.00 1,885.00
Rate analysis for :100.00 Sqm. Total 13,733.00
15 % Contractor overhead 2,059.95
Grand Total 15,792.95

10.07 DUDBC- TWO COAT DISTEMPER PAINT OVER PRIMER COAT: Sqm. 187.47 215.59
J3(13-3ABC) Providing and applying two coat distemper paint over primer coat
including scraping, surface preparation, scaffolding etc., all
complete as per specifications, instructions and as approved by the
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 5.80 Nos. 1,130.00 6,554.00
Unskilled 5.80 Nos. 850.00 4,930.00
Materials Distemper primer 8.00 Ltr. 491.00 3,928.00
Distemper 11.50 Kg. 290.00 3,335.00
Rate analysis for :100.00 Sqm. Total 18,747.00
15 % Contractor overhead 2,812.05
Grand Total 21,559.05

10.08 DUDBC- ONE COAT DISTEMPER PAINT WITHOUT PRIMER: Sqm. 58.45 67.21
J3(13-3B) Providing and applying One coat distemper paint without primer
Resources including
Level/Type scraping, surface preparation, scaffolding
Quantity Unit etc., all Rate Amount Remarks
Labour Skilled 2.00 Nos. 1,130.00 2,260.00
Unskilled 2.00 Nos. 850.00 1,700.00
Materials Distemper 6.50 Kg. 290.00 1,885.00
Rate analysis for :100.00 Sqm. Total 5,845.00
15 % Contractor overhead 876.75
Grand Total 6,721.75

10.09 DUDBC- TWO COAT DISTEMPER PAINT WITHOUT PRIMER: Sqm. 108.59 124.87
J3(13-3BC) Providing and applying two coat distemper paint without primer
Resources including
Level/Type scraping, surface preparation, scaffolding
Quantity Unit etc., all Rate Amount Remarks
Labour Skilled 3.80 Nos. 1,130.00 4,294.00
Unskilled 3.80 Nos. 850.00 3,230.00
Materials Distemper 11.50 Kg. 290.00 3,335.00
Rate analysis for :100.00 Sqm. Total 10,859.00
15 % Contractor overhead 1,628.85
Grand Total 12,487.85
S.N Norms Description Unit User Rate Contractors
Rate
10.10 DUDBC- ONE COAT WEATHER COAT PAINT OVER ONE COAT Sqm. 178.54 205.32
J3(13-3AB) PRIMER: Providing and applying one coat of weather coat paint
Resources over primer including scraping, surface Quantity
Level/Type preparation,Unit
scaffolding Rate Amount Remarks
Labour Skilled 4.00 Nos. 1,130.00 4,520.00
Unskilled 4.00 Nos. 850.00 3,400.00
Materials Weather proof primer 8.00 Ltr. 290.00 2,320.00
Weather proof paint 9.00 Ltr. 846.00 7,614.00
Rate analysis for :100.00 Sqm. Total 17,854.00
15 % Contractor overhead 2,678.10
Grand Total 20,532.10

10.11 DUDBC- TWO COAT WEATHER COAT PAINT OVER ONE COAT Sqm. 273.40 314.41
J3(13-3ABC) PRIMER: Providing and applying two coats of weather coat paint
over one coat of primer including scraping, surface preparation,
scaffolding etc., all complete as per specifications, instructions and
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 5.80 Nos. 1,130.00 6,554.00
Unskilled 5.80 Nos. 850.00 4,930.00
Materials Weather proof primer 8.00 Ltr. 290.00 2,320.00
Weather proof paint 16.00 Ltr. 846.00 13,536.00
Rate analysis for :100.00 Sqm. Total 27,340.00
15 % Contractor overhead 4,101.00
Grand Total 31,441.00

10.12 DUDBC- ONE COAT WEATHER COAT PAINT WITHOUT PRIMER: Sqm. 115.74 133.10
J3(13-3B) Providing and applying one coat of weather coat paint without
Resources primer including scraping, surface preparation,
Level/Type scaffolding
Quantity Unit etc., all Rate Amount Remarks
Labour Skilled 2.00 Nos. 1,130.00 2,260.00
Unskilled 2.00 Nos. 850.00 1,700.00
Materials Weather proof paint 9.00 ltr 846.00 7,614.00
Rate analysis for :100.00 Sqm. Total 11,574.00
15 % Contractor overhead 1,736.10
Grand Total 13,310.10

10.13 DUDBC- TWO COATS WEATHER COAT PAINT WITHOUT PRIMER: Sqm. 210.60 242.19
J3(13-3BC) Providing and applying two coats of weather coat paint without
Resources primer including scraping, surface preparation,
Level/Type scaffolding
Quantity Unit etc., all Rate Amount Remarks
Labour Skilled 3.80 Nos. 1,130.00 4,294.00
Unskilled 3.80 Nos. 850.00 3,230.00
Materials Weather proof paint 16.00 ltr 846.00 13,536.00
Rate analysis for :100.00 Sqm. Total 21,060.00
15 % Contractor overhead 3,159.00
Grand Total 24,219.00

10.16 DUDBC- ONE COAT OF ENAMEL PAINT OVER ONE COAT OF Sqm. 203.73 234.28
J5(13-5AB) PRIMER: Providing and applying one coat of enamel paint in the
Resources wooden
Level/Typeand metal surfaces including Quantity
scrapping, Unit
washing the Rate Amount Remarks
Labour Skilled 8.00 Nos. 1,130.00 9,040.00
Unskilled 5.00 Nos. 850.00 4,250.00
Materials Enamel Primer 8.10 Ltr. 290.00 2,349.00
Enamel paint 9.00 Ltr. 526.00 4,734.00
Rate analysis for :100.00 Sqm. Total 20,373.00
15 % Contractor overhead 3,055.95
Grand Total 23,428.95
S.N Norms Description Unit User Rate Contractors
Rate
10.17 DUDBC- TWO COATS OF ENAMEL PAINT OVER ONE COAT OF Sqm. 311.25 357.93
J5(13-5ABC) PRIMER: Providing and applying two coats of enamel paint in the
wooden and metal surfaces including scrapping, washing the
surface, applying one coat of approved quality primer, surface
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 12.00 Nos. 1,130.00 13,560.00
Unskilled 8.00 Nos. 850.00 6,800.00
Materials Enamel Primer 8.10 Ltr. 290.00 2,349.00
Enamel paint 16.00 Ltr. 526.00 8,416.00
Rate analysis for :100.00 Sqm. Total 31,125.00
15 % Contractor overhead 4,668.75
Grand Total 35,793.75

10.18 DUDBC- ONE COAT OF PLASTIC EMULSION PAINT OVER ONE Sqm. 224.16 257.78
J5(13-5AB) COAT OF PRIMER: Providing and applying one coat of plastic
Resources emulsion
Level/Typepaint including scrapping, washing the surfaceUnit
Quantity with water, Rate Amount Remarks
Labour Skilled 8.00 Nos. 1,130.00 9,040.00
Unskilled 5.00 Nos. 850.00 4,250.00
Materials Enamel Primer 8.10 Ltr. 290.00 2,349.00
Plastic emulsion paint 9.00 Ltr. 753.00 6,777.00
Rate analysis for :100.00 Sqm. Total 22,416.00
15 % Contractor overhead 3,362.40
Grand Total 25,778.40

10.19 DUDBC- TWO COATS OF PLASTIC EMULSION PAINT OVER ONE Sqm. 347.57 399.70
J5(13-5AB) COAT OF PRIMER: Providing and applying two coats of plastic
Resources emulsion
Level/Typepainting work including scrapping, applyingUnit
Quantity one coat of Rate Amount Remarks
Labour Skilled 12.00 Nos. 1,130.00 13,560.00
Unskilled 8.00 Nos. 850.00 6,800.00
Materials Enamel Primer 8.10 Ltr. 290.00 2,349.00
Plastic emulsion paint 16.00 Ltr. 753.00 12,048.00
Rate analysis for :100.00 Sqm. Total 34,757.00
15 % Contractor overhead 5,213.55
Grand Total 39,970.55

10.21 DUDBC- ONE COAT OF VARNISH: Providing and applying one coat varnish Sqm. 77.54 89.17
J8(13-9A) paint as per specifications and as approved by the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 3.00 Nos. 1,130.00 3,390.00
Unskilled 2.00 Nos. 850.00 1,700.00
Materials Varnish paint 6.00 Ltr. 444.00 2,664.00
Rate analysis for :100.00 Sqm. Total 7,754.00
15 % Contractor overhead 1,163.10
Grand Total 8,917.10

10.22 DUDBC- TWO OR MORE COATS OF VARNISH: Providing and applying Sqm. 144.59 166.27
J8(13-9AB) two or more coats of varnish paint as per specifications and as approved
Resources by the Engineer.
Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 6.00 Nos. 1,130.00 6,780.00
Unskilled 4.00 Nos. 850.00 3,400.00
Materials Varnish paint 11.00 Ltr. 389.00 4,279.00
Rate analysis for :100.00 Sqm. Total 14,459.00
15 % Contractor overhead 2,168.85
Grand Total 16,627.85

10.23 DUDBC- THREE COATS OF CHAPRA PAINT: Providing and applying three Sqm. 223.48 257.00
J10(13-11) coats of chapra paint as per specifications and as approved by the
Engineer.
S.N Norms Description Unit User Rate Contractors
Rate
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 10.00 Nos. 1,130.00 11,300.00
Unskilled 5.00 Nos. 850.00 4,250.00
Materials Chapra paint 2.00 Kg. 2,699.00 5,398.00
Sprit 10.00 Ltr. 140.00 1,400.00
Rate analysis for :100.00 Sqm. Total 22,348.00
15 % Contractor overhead 3,352.20
Grand Total 25,700.20

10.24 DUDBC- ONE COAT OF RED OXIDE PAINT: Providing and applying one Sqm. 157.56 181.19
J11(13-4C) coat of red oxide paint as per specifications and as approved by the
Resources Engineer.
Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.70 Nos. 1,130.00 1,921.00
Unskilled 1.70 Nos. 850.00 1,445.00
Materials Red oxide paint 30.00 Kg. 413.00 12,390.00
Rate analysis for :100.00 Sqm. Total 15,756.00
15 % Contractor overhead 2,363.40
Grand Total 18,119.40

10.25 DUDBC- TWO COATS OF RED OXIDE PAINT: Providing and applying two Sqm. 269.60 310.04
J11(13-4C) coats of red oxide paint as per specifications and as approved by the
Resources Engineer.
Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 3.50 Nos. 1,130.00 3,955.00
Unskilled 3.50 Nos. 850.00 2,975.00
Materials Red oxide paint 48.50 Kg. 413.00 20,030.50
Rate analysis for :100.00 Sqm. Total 26,960.50
15 % Contractor overhead 4,044.07
Grand Total 31,004.57

10.32 DUDBC-J26 TWO COATS OF DISTEMPER PAINT WITH PRIMER: Sqm. 200.52 230.59
Resources Providing
Level/Typeand applying two coats of washable distemper
Quantity Unit painting Rate Amount Remarks
Labour Skilled 5.80 Nos. 1,130.00 6,554.00
Unskilled 5.80 Nos. 850.00 4,930.00
Materials Distemper primer 8.00 Ltr. 491.00 3,928.00
Distemper washable 16.00 Kg. 290.00 4,640.00
Rate analysis for :100.00 Sqm. Total 20,052.00
15 % Contractor overhead 3,007.80
Grand Total 23,059.80

10.33 Sqm. 400.00 460.00


Resources Level/Type Quantity Unit Rate Amount Remarks
Labour+ 1.00 Sqm. 400.00 400.00
Material
Rate analysis for :100.00 Sqm. Total 400.00
15 % Contractor overhead 60.00
Grand Total 460.00

K - DAMP PROOFING WORK

11.01 DUDBC- 20 mm thick D.P.C. work in cement sand mortar in 1:2 with Sqm. 818.49 941.27
K1(18-7) W.P.Compound.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 0.750 Nos. 1,130.00 847.50
Unskilled 0.800 Nos. 850.00 680.00
Materials Cement 0.135 M.T. 27,752.80 3,746.62
sand crusher 0.180 Cum. 5,296.50 953.37
S.N Norms
Materials Description Unit User Rate Contractors
Rate
W.P.Compound 2.700 Kg. 725.00 1,957.50
Rate analysis for :10.00 Sqm. Total 8,184.99
15 % Contractor overhead 1,227.74
Grand Total 9,412.73

11.02 DUDBC- 25 mm thick D.P.C. work in cement concrete in 1:1½:3 withwith Sqm. 886.85 1,019.88
K2(18-8) W.P.Compound.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.0000 Nos. 1,130.00 1,130.00
Unskilled 1.2500 Nos. 850.00 1,062.50
Materials Cement 0.1125 M.T. 27,752.80 3,122.19
sand crusher 0.1130 Cum. 5,296.50 598.50
Aggrigate 12 mm river bed 0.2500 Cum. 5,296.50 1,324.12
W.P.Compound 2.2500 Kg. 725.00 1,631.25
Rate analysis for :10.00 Sqm. Total 8,868.56
15 % Contractor overhead 1,330.28
Grand Total 10,198.84

11.03 DUDBC- 18- 38 mm thick D.P.C. work in cement concrete in 1:2:4 with with Sqm. 1,094.95 1,259.19
9 W.P.Compound.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 1.000 Nos. 1,130.00 1,130.00
Unskilled 2.000 Nos. 850.00 1,700.00
Materials Cement 0.120 M.T. 27,752.80 3,330.33
sand crusher 0.170 Cum. 5,296.50 900.40
Aggrigate 12 mm river bed 0.340 Cum. 5,296.50 1,800.81
W.P.Compound 2.880 Kg. 725.00 2,088.00
Rate analysis for :10.00 Sqm. Total 10,949.54
15 % Contractor overhead 1,642.43
Grand Total 12,591.97

L - MAINTAINANCE & DISMANTLING WORK

M - METAL, FENCING & RAILING WORK

3 x 20mm Metal Grill including manufacturing,cutting, welding,


DUDBC- fabrication, fitting, painting with Aluminium paint, sand papering all
13.01 Sqm. 2,100.00 2,415.00
M1(24-1A) complete
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled - Nos. 850.00 -
Material MS grill 3*20 mm (15 kg/sqm) 150.000 Kg. 140.00 21,000.00
Total 21,000.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,150.00
Grand Total 24,150.00

13.09 DUDBC-M11 Supplying, Fitting, Fabricating & fixing of different size M.S. black Kg. 193.01 221.96
pipe tubular truss including metal primer all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 0.687 Nos. 1,130.00 776.31
Unskilled 0.781 Nos. 850.00 663.85
Material MS black pipe 18.940 Kg. 111.70 2,115.59
Primer etc L.S. 100.00
Rate analysis for : 18.94 Kg. Total 3,655.75
15 % Contractor overhead 548.36
S.N Norms Rate analysis for : 18.94 Kg. Description Unit User Rate Contractors
Rate
Grand Total 4,204.11

13.09 DUDBC-M14 Supply, Providing, fabrication, fitting and fixing of stainless steel Rm 10,719.02 12,326.87
50mm dia handrail pipe,in between 25 mm dia ss pipe 3 line ,40 mm
vertical post spaced at every 2.0m apart and 75 mm baluster pipe
with 900 mm height all complete
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours stainless steel 50mm dia handrail pipe,in 1.000 Rm 10,719.03 10,719.02
+Material between 25 mm dia ss pipe 3 line ,40 mm
vertical post spaced at every 2.0m apart and
75 mm baluster pipe with 900 mm height
all complete
Rate analysis for : 1 Rm Total 10,719.02
15 % Contractor overhead 1,607.85
Grand Total 12,326.87

O - ROAD WORK

P- MISCELLANEOUS WORK

16.01 Supply, erection and fixing of Aluminum windows and ventilation Sqm. 570.49 656.06
of section size 90 mm Natural colour thickness
Resources Level/Type 1.1 mmUnit
Quantity , 4 mm clear Rate Amount Remarks
Materials and Supply, erection and fixing of Aluminum 1.00 Sqm. 570.49 570.49
Labour windows and ventilation of section size 100
mm Natural colour thickness 1.1 mm , 4
mm clear glass with SS mosquito net all
complete.
Total 570.49
15 % Contractor overhead 85.57

Grand Total 656.06

13.09 h23 Providing and fixing mild steel angle (bracing), 50*50*5mm ,16 sqm 8,000.00 9,200.00
gauge MS sheets and mild steel sqaure pipes treated with one coats
of primer and two coats of enamel paint, all complete as detailed in
drawing, specification and instructions of the Engineer.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Skilled 0.000 Nos. 1,130.00 -
Unskilled 0.000 Nos. 850.00 -
Material Metal Gate 10.000 sqm. 8,000.00 80,000.00
Rate analysis for : 10 sqm Total 80,000.00
15 % Contractor overhead 12,000.00
Grand Total 92,000.00

You might also like